Justia Contracts Opinion Summaries

by
In February 1995, the State executed a contract with Perini Corporation to design and build South Woods in Bridgeton (the Project), a twenty-six building medium- and minimum-security correctional facility. Perini subcontracted with L. Robert Kimball & Associates, Inc. as the architect and engineer. Defendant Natkin & Company was designated the principal contractor for heating, ventilation, and air conditioning (HVAC). The design that Kimball provided to Perini included an underground HTHW distribution system to serve the entire Project. It also included a central plant from which the hot water was distributed to the various buildings that comprised the Project. Perma-Pipe, Inc. manufactured the underground piping used in the HTHW system. Natkin furnished and installed the underground piping system and the boilers and heat exchangers housed in the central plant. Defendant Jacobs Facilities, Inc. (formerly known as CRSS Constructors, Inc.), was retained by the State to provide construction oversight services. In 2008, the State filed a complaint against Perini, Kimball, Natkin, Jacobs, and Perma-Pipe in which it alleged that the HTHW system failed in March 2000, and on several subsequent occasions, and that these failures were caused by various defects including design defects, defective site preparation for the pipes, defective pipes, and deficient system design. The State asserted breach of contract against Perini, negligence and professional malpractice against Kimball, negligence and breach of contract against Natkin, and breach of contract against Jacobs. Against Perma-Pipe, the State asserted a claim under the New Jersey Products Liability Act (PLA), as well as breach of implied warranties, negligence, and strict liability in tort. All defendants moved for summary judgment, arguing that the Project was substantially complete well before April 28, 1998, and that, therefore, the statute of repose barred the State's complaint. The Appellate Division reversed the orders granting summary judgment in favor of defendants Perini, Kimball, Natkin, and Jacobs. The panel held that the statute of repose was triggered when defendants substantially completed their work on the entire project, no earlier than May 1, 1998, the date when the minimum-security unit and garage were certified as substantially complete. After its review, the Supreme Court held that the statute of repose does not begin to run on claims involving an improvement that serves an entire project (including those parts constructed in multiple, uninterrupted phases) until all buildings served by the improvement have been connected to it. In addition, the Court held that the statute of repose did not apply to claims relating solely to manufacturing defects in a product used in the HTHW system. View "New Jersey v. Perini Corporation" on Justia Law

by
David Friedlen had worked for Runzheimer International, Ltd. for more than fifteen years when Runzheimer began requiring its employees to sign restrictive covenants or be fired. Friedlen signed the covenant and continued to work for Runzheimer for more than two years until he was terminated. Friedlen subsequently began working at Corporate Reimbursement Services (CRS), one of Runzheimer’s competitors. Runzheimer sued Friedlen and CRS, alleging that Friedlen’s employment at CRS constituted a breach of the restrictive covenants. Defendants moved for summary judgment, claiming that the covenant was unenforceable because it lacked consideration. The circuit court granted summary judgment for Defendants. The Supreme Court reversed, holding (1) an employer’s forbearance in exercising its right to terminate an at-will employee constitutes lawful consideration for signing a restrictive covenant; and (2) because the circuit court made no determination as to the reasonableness of the covenant’s terms, the cause must be remanded for further proceedings. View "Runzheimer Int’l, Ltd. v. Friedlen" on Justia Law

Posted in: Contracts
by
In 2001, representatives from the Moody Bible Institute of Chicago and Sysix Financial signed a master agreement, laying the groundwork for future leases of equipment from Sysix to Moody. In 2008, two lease schedules for computer items were executed; they appeared to have been signed by Moody’s vice president and Sysix’s president. Sysix assigned its interest in both leases to Rockwell, which acquired loans from PNB to finance the leases. PNB procured indemnification coverage for those loans from RLI in the form of a financial institution bond. Sysix’s president had forged the signature of Moody’s vice president on both lease schedules. Moody never agreed to either schedule nor did it ever receive any of the promised equipment. PNB notified RLI of its potential loss, but PNB itself soon went under. As receiver for PNB, the FDIC sued RLI. The district court granted summary judgment in FDIC’s favor. The Seventh Circuit affirmed, finding that the plain language of the bond covered FDIC’s losses The Financial Institutions Reform Recovery and Enforcement Act limitations period applies,12 U.S.C. 1821(d)(14), so the suit was timely. View "Fed. Deposit Ins. Corp. v. RLI Ins. Co." on Justia Law

by
After Karrie Lynn Serrania went to Discovery Dental Group, PLLC (DDG) for a toothache, DDG referred her account to LPH, Inc., a debt collection agency. Serrania later sued LPH and DDC, alleging, among other claims, that LPH violated the Fair Debt Collection Practices Act (FDCPA). LPH and DDG counterclaimed for breach of contract. The district court (1) sanctioned Serrania’s attorney for failing to attend a pretrial conference, (2) entered summary judgment against Serrania on the contract and FDCPA claims, and (3) sanctioned Serrania and her attorney for their conduct in the course of litigation. After the district court entered judgment, Serrania underwent bankruptcy, and her dental debts and the district court’s orders were discharged. The Supreme Court affirmed in part and vacated and remanded in part, holding (1) some of Serrania’s arguments on appeal are moot, but her appeal of the district court’s summary judgment order on her FDPCA claim is live, and her attorney has an interest in overturning the sanctions entered against him; (2) the district court correctly entered judgment to LPH on the FDCPA claim; and (3) the district court erred in ordering Serrania and her attorney jointly to pay $24,797 to DDG and $41,113 to LPH as sanctions. View "Serrania v. LPH, Inc." on Justia Law

by
Attorney Novak represented Kelly between 2007 and 2012. The two executed a contingency attorney fee agreement that granted Novak lien rights over any settlement Kelly received. In 2011, Novak filed a probate petition which alleged Kelly was a pretermitted spouse of Teitler and negotiated a considerable settlement. The probate court approved the settlement which awarded Kelly a substantial interest in the Dana Teitler Trust. Kelly died. Novak filed suit to enforce the attorney lien in the 2007 fee agreement. The probate court denied the petition, holding that the proper procedure to recover fees was by claim against Kelly’s estate under section 9000; plaintiff was required to file a creditor’s claim within one year of Kelly’s death; the statute of limitations barred the claim; and section 5000(a), which provides a nonprobate transfer, was inapplicable. The court of appeal reversed. Novak had not forfeited a claim under section 9391, that he was an equitable lienholder and did not need to file a creditor’s claim in probate. An assignment provision in the settlement agreement in the event of Kelly’s death did not destroy Novak’s pre-existing attorney fee lien rights. View "Novak v. Fay" on Justia Law

by
In anticipation of renting an apartment from Sheldon Ashby, Jennifer Roussel gave Ashby a security deposit. Roussel never moved into the apartment and sought the return of her security deposit. When Ashby did not respond to Roussel’s demand for a refund, Roussel filed a complaint against Ashby. The superior court entered default against Ashby and entered judgment for Roussel in the amount of $24,628. Roussel appealed, and Ashby cross-appealed the denial of his motion to set aside the default. The Supreme Court affirmed, holding that the trial court did not err in (1) declining to aware punitive damages to Roussel; (2) denying Roussel’s motion to amend the judgment by awarding additional attorney fees; and (3) denying Ashby’s motion to set aside the default. View "Roussel v. Ashby" on Justia Law

by
Chivalry contracted with Rehtmeyer to develop and manufacture a board game. Chivalry paid Rehtmeyer over $128,000, but the relationship deteriorated. Rehtmeyer never produced the game. Chivalry sued for breach of contract and won a judgment of $168,331.59, plus $621.25 in costs in Illinois state court. Rehtmeyer never paid. Chivalry issued a citation to discover assets. At the citation examination, Rehtmeyer testified that she had no ownership interest in any real estate; securities, stocks, bonds or similar assets; office or electronic equipment; nor a personal checking or savings account. Because Rehtmeryer had not produced required documents, Chivalry continued the citation and filed a motion to compel production, which was granted. She did not comply. The state court twice more ordered her to produce all the documents required by the citation. Months later, Chivalry sought a rule to show cause. The day before the scheduled hearing, Rehtmeyer filed a Chapter 7 bankruptcy petition. Chivalry appeared to object to the discharge of the debt owed to it, claiming that Rehtmeyer had concealed her assets and income during the citation proceedings. The bankruptcy court denied Chivalry’s objection. The district court affirmed. The Seventh Circuit reversed, finding that Rehtmeyer concealed assets with the requisite intent. View "Jacobs v. Marcus-Rehtmeyer" on Justia Law

by
Benihana America obtained a preliminary injunction in aid of arbitration of a dispute arising under its license agreement with Benihana of Tokyo, prohibiting Tokyo from: selling unauthorized food items at the restaurant it operates under the license agreement; using certain trademarks in connection with that restaurant in a manner not approved by the license agreement; and arguing to the arbitral panel, if it rules that Tokyo breached the license agreement, that Tokyo should be given additional time to cure any defaults. The Second Circuit affirmed with respect to the menu offering and trademark use injunctions. The court reasonably concluded that each of the relevant factors favored Benihana America. The court reversed the prohibition on arguing to the arbitral panel for an extended cure period. When a dispute is properly before an arbitrator, a court should not interfere with the arbitral process on the ground that, in its view of the merits, a particular remedy would not be warranted. Benihana America may challenge an arbitrator’s decision in court only after it has been issued. It may not subvert its agreement to arbitrate by obtaining an advance judicial determination that there are no grounds for the arbitrator to grant a particular remedy. View "Benihana, Inc. v. Benihana of Tokyo, LLC" on Justia Law

by
United operates a nationwide household goods moving network with more than 400 independently owned and operated agents. Since 1993, Chavis has been a full-service United agent. The parties' relationship is governed by a 2007 Agency Agreement. Chavis filed suit for breach of contract, alleging that United breached the Agency Agreement by unilaterally changing the roles that United agents play in servicing shipments by not assigning Chavis to certain roles in the chain of interstate shipments. According to Chavis, it should have been assigned the roles of origin agent and destination agent, based on its status as the "local" or "authorized" agent in the case of non-military shipments, i.e., its status as the agent closest to the original or destination address, and based on its designation as the United agent "authorized" to service Shaw Air Force Base in South Carolina for military shipments. The district court entered summary judgment for United, finding the Agreement unambiguous. The Eighth Circuit affirmed. None of the documents that Chavis identified supported its argument that it is the only "authorized" agent for its home market for non-military shipments or the exclusive agent for military shipments to and from Shaw AFB. View "Chavis Van & Storage of Myrtle Beach, Inc. v. United Van Lines, LLC" on Justia Law

by
In this commercial dispute, Petitioner obtained a $6 million breach-of-contract and tort judgment against Respondents. After filing the lawsuit, Petitioner assigned its claims to its commercial lender. Respondents filed a motion to dismiss for lack of jurisdiction, alleging that Petitioner had no standing to pursue the litigation because it had assigned the claims to the lender. The trial court concluded that Petitioner had standing. The court of appeals vacated the judgment and dismissed for want of jurisdiction. The Supreme Court reversed, holding that the court of appeals failed to consider pertinent evidence before the trial court, and therefore, the cause must be remanded to the trial court for reconsideration. View "Vernco Constr., Inc. v. Nelson" on Justia Law