Justia Contracts Opinion Summaries

Articles Posted in U.S. Federal Circuit Court of Appeals
by
In 1993, Bowers and the FAA entered into a lease for office and warehouse space. The FAA agreed to monthly payments, $19,509, beginning in January 1994, payable each month “in arrears.” The parties modified the lease eight times until termination on September 30, 2006. In 2008, Bowers filed a claim of $82,203.72 with the contracting officer (41 U.S.C. 7103(a)(1)), for the final month’s rent and property damage. Bowers claimed that because the contract provided for payment “in arrears,” payment made in September, 2006 was for the August rent. The contracting officer held that rent was actually paid in advance, but allowed other, minor, claims. Before the Civilian Board of Contract Appeals, Bowers attempted to establish that the FAA had not paid rent for three months in 1994. CBCA rejected the attempt and Bowers signed a certificate of finality. In 2009 Bowers submitted two more claims: $56,640.78 (plus interest) for assertedly unpaid rent for January, February, and March of 1994 and that the FAA underpaid by $664 every month from October 1, 1998 to October 1, 2006, a total of $64,408.00 (plus interest). The contracting officer denied the claims. The Claims Court held that the CBCA’s final decision precluded the litigation. The Federal Circuit affirmed. View "Bowers Inv. Co, LLC v. United States" on Justia Law

by
In 2007 the Postal Service awarded Tip Top a contract under which the Postal Service would assign individual projects by issuing work orders. In 2009, the Postal Service issued a work order to replace the air conditioning system at the Main Post Office in Christiansted, Virgin Islands, for the price of $229,736.92. As a result of that work Tip Top submitted a claim and request for an equitable adjustment under the Contract Disputes Act, 41 U.S.C. 7101-7109, in the amount of $34,553.77, consisting of a subcontractor’s price for a change, plus 10% profit, 4% insurance, and 4% gross receipts tax, plus $9,655 for “Preparation Costs & Extended Overhead” and $2,745 for “Legal Fees.” The Postal Service Board of Contract Appeals ruled that Tip Top was entitled to recover $2,565. The Board ruled that Tip Top was not entitled to recover the balance of the amount claimed because it had failed to demonstrate that the costs at issue were incurred as a result of the change order. The Federal Circuit reversed and remanded, with directions to grant the appeal in its entirety. The ruling was based upon an error of law and not supported by substantial evidence. View "Tip Top Constr., Inc.v. Donahoe" on Justia Law

by
In 2009 the Forest Service awarded Scott contracts to remove timber on federally-owned plots during a designated period. Scott was then pursuing litigation based on delays in other contracts resulting from environmental litigation. The government therefore included provisions in the contracts at issue, authorizing suspension of the contracts to comply with court orders or for environmental reasons. The contracts provided for term adjustment, but prohibited award of lost profits, attorney’s fees, replacement costs, and similar losses. Another environmental suit arose in Oregon, resulting in an injunction that included the contracts at issue. The Forest Service suspended the contracts and began protected species surveys required by that litigation. Surveys were completed in late 2000, but the suspensions continued, due to new litigation, until 2003. In 2004-2008, Scott harvested the total contractual amount of timber. In 2005, Scott sought damages. The Claims Court found breach of an implied duty of good faith and fair dealing and that the government unreasonably delayed the surveys and continued the suspensions. The court found that Scott was entitled to $28,742 in lost profits and $129,599 in additional costs, offset by some actual profit; the government was also liable to a log-processing subcontractor, for $6,771,397 in lost profits; The Federal Circuit reversed. View "Scott Timber Co. v. United States" on Justia Law

by
The Army solicited proposals for aerial target flight operations and maintenance services. Kratos provided these services under a predecessor contract. The solicitation listed three evaluation factors: Technical/Management; Past Performance; and Price/Cost to be rated as “outstanding,” “satisfactory,” “marginal,” or “unsatisfactory.” The contract was subject to the Service Contract Act of 1965, under which the Federal Acquisition Regulation requires that “successor contractors … in the same locality must pay wages and fringe benefits … at least equal to those contained in any bona fide collective bargaining agreement … under the predecessor contract.” The Army received three proposals, including the offers from SA-TECH and Kratos. After review, the Technical Evaluation Committee announced a Final Evaluation Report, noting potential difficulties for SA-TECH under the Labor sub-factor, but rating SA-TECH as “outstanding” for all factors. Kratos also received “outstanding” ratings. The Source Selection Authority concluded that SA-TECH offered the best value for the government. Kratos filed a protest with the Government Accountability Office. SA-TECH subsequently protested the Army’s decision to engage in corrective action instead of allowing SA-TECH’s award to stand. The Claims Court denied the Army’s motion to dismiss and found the Army’s actions unreasonable and contrary to law. The Federal Circuit affirmed. View "Sys. Application & Tech., Inc. v. United States" on Justia Law

by
Whiteman was employed by the FAA and reported violations of regulations, mismanagement, and abuses of authority. Whiteman alleged that colleagues and supervisors began to threaten and intimidate her. She filed EEO actions and reported one incident to police. She was excluded from the radar room and stripped of duties, then reassigned to the control tower instead of her previous job. In 2003, Whiteman settled with the FAA resolving all claims, “known or unknown” in exchange for guaranteed priority consideration for the next available supervisor position. December 9, 2003, Whiteman applied for a position. No other applicants were considered. December 18, 2003, the FAA adopted pay scale changes, which reduced the salary of the position. Whiteman accepted the position, but sued, alleging that the FAA’s delay in notifying her of the vacancy breached the settlement agreement and caused loss of earnings. The district court dismissed for lack of subject matter jurisdiction. Whiteman appealed to the Merit Systems Protection Board contending that the FAA had unlawfully retaliated against her for whistleblowing. The Board concluded that the claim was barred. The Federal Circuit affirmed in part. The MSPB incorrectly concluded that Whiteman’s post-settlement retaliation claim was collaterally estopped, but its conclusion that the settlement agreement is enforceable is supported by substantial evidence. View "Whiteman v. Dep't of Transp." on Justia Law

by
Defense contractor Raytheon, specializes in infrared imaging. Indigo, also specializing in infrared imaging, was founded by former Raytheon employees including Woolaway, who promised not to recruit Raytheon employees. Indigo began consulting for Raytheon, governed by Confidential Disclosure Agreements. In 1997, Raytheon became concerned that Indigo was recruiting Raytheon personnel to gain access to trade secrets. The companies settled the matter by agreement. The relationship between Raytheon and Indigo terminated in 2000. In 2000, Indigo won a military contract; in 2003, Indigo was selected over competitors, including Raytheon, to receive another subcontract. In 2004, Raytheon acquired and disassembled an Indigo infrared camera and found what it believed was evidence of patent infringement and trade secret misappropriation. In 2007, Raytheon found a correlation with the expertise of former employees who had departed for Indigo. The district court dismissed claims of trade secret misappropriation as time barred. The Federal Circuit reversed. The district court erred by resolving genuine factual disputes in favor of Indigo, the moving party, and concluding that Raytheon should have discovered its claims before March 2, 2004. View "Raytheon Co. v. Indigo Sys. Inc." on Justia Law

by
Plaintiff, a U.S. citizen employed in international disaster relief assistance, returned from an overseas business trip and was detained by Immigration and Customs Enforcement at Dulles International Airport. An agent seized his laptop and two flash drives after permitting him to copy and retain one computer file and providing Customs Form 6051D indicating that the equipment would be detained for up to 30 days. While the laptop was detained, its hard drive failed, destroying much of its business software. A Customs representative sent a letter seeking to assure plaintiff that a prompt resolution of the issue would be addressed. About 10 weeks after its seizure, the laptop was returned. Plaintiff’s suit alleged breach of an implied-in-fact contract and a taking, with damages totaling $469,480.00 due to lost contracts resulting from inability to access files as well as replacement hardware, software, and warranty costs. The Claims Court dismissed, finding that the complaint did not sufficiently allege a bailment contract and that the property was not taken for a public use within the context of the Fifth Amendment Takings Clause. The Federal Circuit affirmed.

by
In 1983, the Nuclear Waste Policy Act, 42 U.S.C. 10101-10270, authorized the Department of Energy to contract with nuclear facilities for disposal of spent nuclear fuel and high level radioactive waste. The Standard Contract provided that rights and duties may be assignable with transfer of SNF title. Plaintiff entered into the Standard Contract in 1983 and sold its operation and SNF to ENVY in 2002, including assignment of the Standard Contract, except one payment obligation. Plaintiff transferred claims related to DOE defaults. As a result of DOE’s breach, ENVY built on-site dry-storage facilities. The Claims Court consolidated ENVY’s suit with plaintiff’s suit. The government admitted breach; the Claims Court awarded ENVY $34,895,467 (undisputed damages) and certain disputed damages. The Federal Circuit affirmed in part. Plaintiff validly assigned pre-existing claims; while partial assignment of rights and duties under the contract was not valid, the government waived objection. The assignment encompassed claims against the government. Legal and lobbying fees to secure Vermont approval for mitigation were foreseeable, but other expenses were not recoverable. ENVY failed to prove costs of disposing of contaminated material discovered due to the breach and its characterization of spent fuel moved to dry storage. ENVY is not entitled to recover cost of capital for funding mitigation, or Resource Code 19 payroll loader overhead costs, but may recover capital suspense loader overhead costs,.

by
In February, 2002, the Navy awarded GM&W a contract for floor coating at a military base. GM&W subcontracted with FloorPro, which completed the work on February 27, 2002 and billed GM&W. On March 8, the Navy informed GM&W that the work was completed satisfactorily. On April 17, FloorPro informed the Navy’s contracting officer that it had not been paid. GM&W had claims pending and was not sure whether funds that the Navy directly deposited would be available to FloorPro. In April 2002, the Navy and GM&W entered into contract modification providing for mailing to FloorPro of a check payable to GM&W and Floor-Pro. The Navy paid GM&W directly by electronic transfer and informed FloorPro that its recourse was to sue GM&W. In December 2002, FloorPro submitted a claim to the Navy’s contracting officer. On March 27, 2003, FloorPro filed at the Armed Services Board of Contract Appeals, which awarded $37,500. The Federal Circuit reversed, holding that under the Contract Disputes Act, 41 U.S.C. 7101, ASBCA has no jurisdiction over a claim by a subcontractor. In 2009, FloorPro filed in the Court of Claims, which ruled in favor of FloorPro. The Federal Circuit vacated, ordering dismissal under the six-year limitations period of 28 U.S.C. 2501.

by
In 1983, Congress enacted the Nuclear Waste Policy Act, 42 U.S.C. 10101-10270, authorizing the Department of Energy to enter into contracts with nuclear facilities for the disposal of spent nuclear fuel (SNF) and high-level radioactive waste (HLW). Congress mandated that, under the Standard Contract, DOE dispose of SNF and HLW beginning not later than January 31, 1998. In 1983, DOE entered into a Standard Contract with Consolidated Edison under which DOE agreed to accept SNF stored at the Indian Point facility. Following DOE’s breach, the Claims Court awarded two categories of damages: wet storage costs for continued operation of its Unit 1 spent fuel pool and regulatory fees paid to the U.S. Nuclear Regulatory Commission. The Federal Circuit reversed the awards, affirmed denial of damages for the cost of financing mitigation activities, but reversed denial of damages for indirect overhead costs associated with mitigation. The company had chosen to prioritize removal of Unit 2 SNF and Unit 1 material would not have been removed by the time at issue; the company did not establish that the breach caused an increase in fees to the NRC.