Justia Contracts Opinion Summaries
Articles Posted in Government Contracts
New Jersey v. Perini Corporation
In February 1995, the State executed a contract with Perini Corporation to design and build South Woods in Bridgeton (the Project), a twenty-six building medium- and minimum-security correctional facility. Perini subcontracted with L. Robert Kimball & Associates, Inc. as the architect and engineer. Defendant Natkin & Company was designated the principal contractor for heating, ventilation, and air conditioning (HVAC). The design that Kimball provided to Perini included an underground HTHW distribution system to serve the entire Project. It also included a central plant from which the hot water was distributed to the various buildings that comprised the Project. Perma-Pipe, Inc. manufactured the underground piping used in the HTHW system. Natkin furnished and installed the underground piping system and the boilers and heat exchangers housed in the central plant. Defendant Jacobs Facilities, Inc. (formerly known as CRSS Constructors, Inc.), was retained by the State to provide construction oversight services. In 2008, the State filed a complaint against Perini, Kimball, Natkin, Jacobs, and Perma-Pipe in which it alleged that the HTHW system failed in March 2000, and on several subsequent occasions, and that these failures were caused by various defects including design defects, defective site preparation for the pipes, defective pipes, and deficient system design. The State asserted breach of contract against Perini, negligence and professional malpractice against Kimball, negligence and breach of contract against Natkin, and breach of contract against Jacobs. Against Perma-Pipe, the State asserted a claim under the New Jersey Products Liability Act (PLA), as well as breach of implied warranties, negligence, and strict liability in tort. All defendants moved for summary judgment, arguing that the Project was substantially complete well before April 28, 1998, and that, therefore, the statute of repose barred the State's complaint. The Appellate Division reversed the orders granting summary judgment in favor of defendants Perini, Kimball, Natkin, and Jacobs. The panel held that the statute of repose was triggered when defendants substantially completed their work on the entire project, no earlier than May 1, 1998, the date when the minimum-security unit and garage were certified as substantially complete. After its review, the Supreme Court held that the statute of repose does not begin to run on claims involving an improvement that serves an entire project (including those parts constructed in multiple, uninterrupted phases) until all buildings served by the improvement have been connected to it. In addition, the Court held that the statute of repose did not apply to claims relating solely to manufacturing defects in a product used in the HTHW system. View "New Jersey v. Perini Corporation" on Justia Law
East West Bank v. Rio School Dist.
After Rio School District’s new school was completed, the District and its general contractor (FTR) engaged in a decade-long legal battle, resulting in a judgment for FTR exceeding $9 million. Public Contract Code section 7107 allows a public entity to withhold funds due a contractor when there are liens on the property or a good faith dispute concerning whether the work was properly performed. The trial court assessed penalties against District because it did not timely release the retained funds. The court of appeal affirmed in part. A dispute over the contract price does not entitle a public entity to withhold funds due a contractor; the doctrine of unclean hands does not apply to section 7107; the trial court properly rejected the District's action under the False Claims Act, Government Code section 12650 and properly assessed prejudgment interest, subject to adjustment for any extra work claims found untimely on remand. The trial court erred in its interpretation of a contract provision imposing time limitations to submit the contractor's claims for extra work as requiring a showing of prejudice and erred in awarding fees for work not solely related to FTR's section 7107 cause of action. View "East West Bank v. Rio School Dist." on Justia Law
Bannum, Inc. v. United States
Bannum protested decisions of the Bureau of Prisons of the U.S. Department of Justice to award two contracts to other bidders, alleging a common defect in the terms of the solicitations and problems in the evaluation of competing bids. Bannum cited a requirement of compliance with Prison Rape Elimination Act of 2003, 42 U.S.C. 15601–15609 and the government’s failure to provide pricing information with respect to the requirement. In each case, the Court of Federal Claims dismissed Bannum’s suit. Finding that Bannum’s proposal, by failing to commit Bannum to a fixed price, was materially out of compliance with the terms of the solicitation, the court concluded that Bannum was not an “interested party” entitled to bring its protest under 28 U.S.C. 1491(b). The Federal Circuit affirmed in consolidated appeals, holding that, because Bannum did not adequately present its objection to the solicitations before the awards, Bannum waived its ability to challenge the solicitations. On appeal, Bannum failed to preserve its separate challenges to the bid evaluations. View "Bannum, Inc. v. United States" on Justia Law
Posted in:
Contracts, Government Contracts
G4S Tech., LLC v. United States
The Department of Agriculture’s Rural Utilities Service (RUS) made a $267 million loan to Open Range to finance construction of wireless broadband networks in 540 RUS-approved markets. Open Range subcontracted with G4S. The FCC suspended a permit, so that Open Range lost the spectrum rights necessary to operate the planned network. RUS gave notice of its intent to terminate remaining funds on the loan unless Open Range could obtain replacement rights. Open Range began failing to meet its obligations to subcontractors. The Secretary of Agriculture made loan money available, provided a press release, and offered to reassure subcontractors, but Open Range was unable to regain the full spectrum rights necessary to complete the original project. RUS and Open Range executed an amendment to reflect a loan amount reduced to $180 million, and 160 RUS-approved markets, but Open Range remained unable to satisfy its debts and filed for bankruptcy. G4S filed suit. The Claims Court held that G4S was not a third party beneficiary to the agreement. The Federal Circuit affirmed, stating that G4S asked that the government incur liability simply because it talked to the individuals in charge of a failing project in an attempt to fix the problems. View "G4S Tech., LLC v. United States" on Justia Law
Reliable Contracting Grp., LLC v. Dep’t of Veterans Affairs
In 2003, the VA entered into a contract with Reliable for electrical improvements at a VA medical center, requiring installation of three backup generators, “new and of the most suitable grade.” Federal Acquisition Regulation 52.211-5, incorporated by reference, requires that supplies be “new, reconditioned, or remanufactured,” and defines “new” as “composed of previously unused components.” Reliable sub-contracted to Fisk, which contracted with DTE. In 2004, DTE delivered two Cummins Power Generation generators to the construction site. The VA’s senior resident engineer inspected the generators and determined that they were not “new.” He wrote to Reliable, stating: They show a lot of wear and tear including field burns to enlarge mounting holes. Are they new and will you certify them as such? I cannot pay you … without that certification. Fisk and Reliable initially agreed that the generators did not meet the contract specification. After investigation, they concluded that the generators, manufactured in 2000, had been previously purchased by others but never used. Fisk obtained different generators, which were accepted by the VA. In 2007, Reliable submitted a claim, seeking $1,100,000 for additional costs incurred as a result of rejection of the original generators. In 2013, the Board of Contract Appeals denied Reliable’s claim. The Federal Circuit vacated, holding that the Board erred in its interpretation of the contract. View "Reliable Contracting Grp., LLC v. Dep't of Veterans Affairs" on Justia Law
Lydig Constr., Inc. v. Martinez Steel Corp.
Lydig Construction was the general contractor on a large public works project. Martinez Steel was the original steel supply subcontractor on the project. Lydig sued Martinez for additional costs Lydig incurred because Martinez failed to timely supply steel for the project; Lydig, with the public agency's approval, had been required to replace Martinez as the steel supplier. Lydig moved for a right to attach order and a writ of attachment and presented the trial court with its business records and declarations from its employees. Martinez opposed Lydig's motion and presented declarations from one of its employees that set forth its contention Lydig owed it for, among other items, steel Martinez had delivered to the project. Martinez filed a cross-complaint in which it alleged claims that, if successful, would entirely offset Lydig's claims against it. The trial court granted Lydig's motion and issued writs of attachment in the amount of $203,315. The court of appeal affirmed, rejecting Martinez's contentions that its cross-complaint, as a matter of law, prevented the trial court from issuing a writ of attachment against it and that Lydig's application for a writ of attachment was not supported by substantial evidence. View "Lydig Constr., Inc. v. Martinez Steel Corp." on Justia Law
EM Logging v. Dep’t of Agric.
The Forest Service awarded EM Logging a timber sale contract for the Kootenai National Forest in Montana. The contract’s load limit clause states that “[a]ll vehicles shall comply with statutory load limits unless a permit from the Forest Service and any necessary State permits are obtained,” the haul route clause states that “[a]ll products removed from Sale Area shall be transported over the designated routes of haul” and a notification clause requires that “Purchaser shall notify Forest Service when a load of products … will be delayed for more than 12 hours in reaching weighing location.” The provision under which the Forest Service terminated the contract refers to: “a pattern of activity that demonstrates flagrant disregard for the terms of this contract.” The Forest Service issued multiple notifications of breach with respect to the clauses, suspended operations, and terminated the contract. The Federal Circuit reversed, finding that one instance of route deviation necessitated by illness, one load limit violation, and two instances of delayed notifications. None of the alleged violations independently substantiated the finding of flagrant disregard. Even together, the violations were not substantial evidence of a pattern of activity demonstrating that EM’s actions were in flagrant disregard of the contract. View "EM Logging v. Dep't of Agric." on Justia Law
K-Con Bldg. Sys., Inc. v. United States
In 2004, K-Con entered into a contract with the federal government to construct a Coast Guard building in Port Huron Michigan for $582,641. Once K-Con finished, the government imposed liquidated damages of $109,554 for tardiness of 186 days in completion. KCon sued, seeking remission of the liquidated damages on two grounds—that the contract’s liquidated-damages clause was unenforceable and that KCon was entitled to an extension of the completion date. KCon also requested additional compensation based on work performed in response to government requests that K-Con alleges amounted to contract changes. The Court of Federal Claims held that the contract’s liquidated damages clause was enforceable; that K-Con did not comply with the written-notice precondition for invoking the contract clause governing changes; and that K-Con’s claim for an extension on the completion date must be dismissed for lack of jurisdiction. The Federal Circuit affirmed. K-Con failed to comply with the changes clause, and its after-the-fact speculations about what would have happened had it complied do not create a genuine dispute of material fact regarding whether it should be excused for its failure. View "K-Con Bldg. Sys., Inc. v. United States" on Justia Law
FTR Int’l, Inc. v. Rio Sch. Dist.
FTR has constructed buildings for public entities for 15 years. In 1999, FTR submitted the winning bid of $7.345 million to construct a District school. During construction, FTR submitted approximately 150 proposed change orders (PCO). FTR claimed some were necessary because the District’s plans were inadequate or misleading. The District denied most of the PCOs on the grounds that the work was covered under the basic contract, the amounts claimed were excessive, or that a PCO was not timely under the contract. Construction was completed in 2001. Public Contract Code 7107 allows a public entity to withhold funds due a contractor when there are liens on the property or a good faith dispute concerning whether the work was properly performed. The court of appeal held that the trial court properly assessed penalties against District because it did not timely release retained funds; properly rejected the District's action under the False Claims Act, Government Code 12650; and properly assessed prejudgment interest. The court erred in its interpretation of a contract provision imposing time limitations to submit claims for extra work as requiring a showing of prejudice and erred in awarding fees for work not solely related to FTR's section 7107 cause of action. View "FTR Int'l, Inc. v. Rio Sch. Dist." on Justia Law
Los Angeles Mem’l Coliseum Comm’n v. Insomniac, Inc.
The Los Angeles Memorial Coliseum Commission and Los Angeles Memorial Coliseum Association alleged that defendants, who promoted and staged music events at the Coliseum and related venues, paid an employee of the Commission for services related to those music events and that such payments were inappropriate and not disclosed to plaintiffs. The trial court dismissed. The court of appeal reversed in part, finding that the plaintiffs adequately stated causes of action under the conflicts of interest prohibition in Government Code section 1090, conspiracy to defraud, violation of the Unfair Competition Law (UCL), and accounting. The court upheld dismissal of claims of violation of the False Claims Act, fraud, and negligence. View "Los Angeles Mem'l Coliseum Comm'n v. Insomniac, Inc." on Justia Law
Posted in:
Contracts, Government Contracts