Redondo Constr. Corp. v. Izquierdo
In 1999, Redondo Construction Corporation pled guilty to aiding and abetting the making of false statements during its work on a federal highway project. The Puerto Rico Highway and Transportation Authority (“PRHTA”) and the Puerto Rico Public Guildings Authority (“PBA”) subsequently revoked the bids it had awarded Redondo before the plea and suspended Redondo from bidding on new contracts. Redondo challenged both decisions, which resulted in settlement agreements with both agencies allowing Redondo to resume bidding for contracts. After Puerto Rico passed Law 458, which prohibited Puerto Rico agencies from awarding contracts corporations convicted of offenses involving public funds, the PBA cancelled several of Redondo’s bids and the contract it had executed with Redondo, and the PRHTA withdrew from its settlement with Redondo. Redondo sued PRHTA, PBA, and several officials at both agencies, alleging that Defendants were in breach of the settlement agreements, that this caused Redondo’s bankruptcy, and that Defendants were liable in damages. The district court granted the PRHTA’s and the individual defendants’ motions for summary judgment and sua sponte dismissed Redondo’s claims against the PBA. The First Circuit Court of Appeals (1) affirmed the entry of summary judgment as to the PRHTA and the individual defendants, as Redondo had no record of evidence of damages against these defendants; but (2) vacated the dismissal of the claim against the PBA, as the court did not meet the necessary conditions for entering judgment sua sponte. View "Redondo Constr. Corp. v. Izquierdo" on Justia Law
Century Exploration New Orleans, LLC v. United States
The companies obtained an oil and gas lease from the government for a 5760-acre tract on the Outer Continental Shelf. They made an initial bonus payment of $23,236,314 and have paid additional rental payments of $54,720 per year. The lease became effective on August 1, 2008, and had an initial term running through July 31, 2016. It provided that it issued pursuant to and was subject to the Outer Continental Shelf Lands Act of August 7, 1953, (OCSLA) 43 U.S.C. 1331 and “all regulations issued pursuant to the statute in the future which provide for the prevention of waste and conservation of the natural resources of the Outer Continental Shelf and the protection of correlative rights therein; and all other applicable statutes and regulations.” In 2010, an explosion and fire on the Deepwater Horizon semi-submersible oil drilling rig in the Gulf of Mexico killed 11 workers and caused an oil spill that lasted several months. As a result, the government imposed new regulatory requirements, Oil Pollution Act (OPA), 33 U.S.C. 2701. The companies sued for breach of contract. The Claims Court and Federal Circuit ruled in favor of the government, finding that the government made the changes pursuant to OCSLA, not OPA. View "Century Exploration New Orleans, LLC v. United States" on Justia Law
Falls Road Cmty. Ass’n, Inc. v. Baltimore County
This case concerned a dispute over the paving of a parking lot located on park land leased to a restaurant. A formal agreement between the restaurant and a community organization restricted the paving of the property, and the restriction was incorporated in administrative zoning orders. Still, the lot was paved. Baltimore County was, in this case, landlord of the property, code enforcer, and final administrative adjudicator of disputes arising under local land use laws. As administrative adjudicator, the County forbade the paving. As landlord, the County directed its tenant, Oregon, LLC, to pave the lot. As code enforcer, it refrained from taking action in response to the apparent violation of a final administrative order issued by the Board of Appeals. Plaintiffs brought suit against the County and Oregon seeking declaratory and mandamus relief. The circuit court ruled against Plaintiffs. The court of special appeals affirmed, concluding that Plaintiffs had failed to exhaust administrative remedies. The Court of Appeals largely affirmed, albeit on different grounds, holding (1) Plaintiffs need not initiate an administrative proceeding to pursue enforcement of the Board’s orders; (2) the circuit court properly granted summary judgment with respect to the mandamus counts of the complaint; and (3) the circuit court has authority to issue a declaratory judgment as to whether the Board’s orders were violated. Remanded. View "Falls Road Cmty. Ass'n, Inc. v. Baltimore County" on Justia Law
In the Matter of the Rehabilitation of the Home Insurance Company
Appellant, Century Indemnity Company (CIC) appealed a Superior Court order that granted Respondent Roger Sevigny, Commissioner of Insurance and Liquidator of the Home Insurance Company (Home) an award of statutory prejudgment interest on certain monies owed to Home by CIC. Home is an insurance company, organized under the laws of New Hampshire, which was declared insolvent and placed in liquidation in 2003. CIC is an insurance company organized under the laws of Pennsylvania. CIC and Home have a set of co-insurance and reinsurance relationships. In prior litigation, the Supreme Court held that an asserted $8 million setoff claim by CIC, which had been waived and then reacquired by CIC in a pair of settlement agreements with PECO, was impermissible under New Hampshire law. The New Hampshire Court explicitly declined, without prejudice, to decide the issue at issue here: whether Home’s estate was entitled to prejudgment interest on the payments CIC wrongfully withheld based upon setoff. The Court denied CIC’s motion for reconsideration in the "Home IV" appeal; after remand, the Liquidator filed a motion in superior court for interest on amounts withheld by CIC based upon improper setoff, to which CIC objected. CIC removed the PECO setoff from its monthly statement to Home and paid the previously withheld $8 million to the Liquidator. The trial court entered an order granting the motion and finding that Home was entitled to prejudgment statutory interest under RSA 524:1-a (2007) accruing from October 2007 (the date of the Liquidator’s letter notifying CIC of his determination to disallow the PECO setoff). This appeal followed. Finding no reversible error in the Superior Court's order, the Supreme Court affirmed. View "In the Matter of the Rehabilitation of the Home Insurance Company" on Justia Law
Kellogg Brown & Root Servs. v. United States
In 2001 KBR agreed to provide the Army with logistics support services during Operation Iraqi Freedom. Individual task orders required KBR to install, operate and maintain dining services near Mosul, Iraq on a cost-plus-award-fee basis. KBR selected ABC, a subcontractor, to build a prefabricated metal dining facility and to provide dining services for a camp population of 2,573. In June 2004, the Army ordered KBR to stop construction of the metal facility and begin construction of a reinforced concrete facility for an estimated 2,573 to 6,200+ persons. Instead of requesting bids for the new work, KBR kept ABC as the subcontractor due to the urgency of the request. ABC submitted a new proposal with a total monthly cost about triple the monthly cost initially quoted. ABC attributed the increased costs to additional labor and equipment to serve a larger population and to a drastic increase in the cost of labor and a severe shortage of staff willing to work in Iraq. Due to a calculation error, it was determined that ABC’s proposal was reasonable. KBR’s management reviewed and approved a change order, embodying ABC’s proposal. In 2005 the subcontract ended and title to the dining facility passed to the Army. In 2007, the Defense Contract Auditing Agency suspended payment of certain costs paid by KBR to ABC pursuant to the change order. KBR prepared a new price justification for the concrete dining facility and ultimately filed suit, seeking recovery of the $12,529,504 in costs disapproved for reimbursement. The Claims Court awarded $6,779,762. The Federal Circuit affirmed.View "Kellogg Brown & Root Servs. v. United States" on Justia Law
Lake Cyrus Development Company, Inc. v. Bessemer Water Service
This case involves a dispute between Bessemer Water Service (BWS) and Lake Cyrus Development Company, Inc. (LCDC) over a contract referred to as the "1998 water agreement." In "Bessemer I," the Supreme Court concluded that the trial court had exceeded its discretion in holding that the 1998 water agreement was a valid binding contract and in awarding LCDC $224,979.83 because the agreement was entered into violation of section 39-2-2 and was therefore void. On appeal, the Attorney General intervened and filed a complain seeking to recover payments BWS made to LCDC under the 1988 water agreement. The trial court ultimately entered a judgment in favor of the Attorney General (for the benefit of BWS). LCDC thereafter filed a postjudgment motion requesting the trial court alter, amend or vacate its judgment, or in the alternative, order a new trial. The trial court denied LCDC's motion; that denial was brought before the Supreme Court in this case. After review, the Supreme Court held the trial court's denial of LCDC's motion should have been reversed. The case was then remanded for further proceedings.
View "Lake Cyrus Development Company, Inc. v. Bessemer Water Service " on Justia Law
Vermont v. Prison Health Services, Inc.
The issue before the Supreme Court in this case centered on a contract dispute between the State of Vermont and Corizon Health, Inc., formerly known as Prison Health Services, Inc. (PHS). The State appealed a declaratory judgment ruling that PHS was not contractually obligated to defend the State and its employees against certain claims brought by the estate of an inmate who died while in the custody of the Department of Corrections. Upon review of the contract in question, the Supreme Court reversed, concluding that PHS had a duty to defend. View "Vermont v. Prison Health Services, Inc." on Justia Law
Ind. Gas Co., Inc. v. Ind. Fin. Auth.
The Indiana Utility Regulatory Commission (IURC) approved a contract for the purchase of substitute natural gas and directed the procedure for resolving future related disputes. The court of appeals reversed the IURC's approval of the contract because a definition term in the contract deviated from the required statutory definition. The parties to the contract subsequently amended the contract to delete the language that the court of appeals found improper. The Supreme Court vacated the reversal of the IURC's order, held that the amended contract that corrected the definitional error rendered the definitional issue moot, and summarily affirmed the court of appeals as to all other claims. View "Ind. Gas Co., Inc. v. Ind. Fin. Auth." on Justia Law
Bachner Company, Inc. v. Weed
Bachner Company and Bowers Investment Company were unsuccessful bidders on a public contract proposal. They filed a claim for intentional interference with prospective economic opportunity against four individual procurement committee members. The superior court found that the bidders failed to present a genuine issue of material fact regarding the committee members' alleged bad faith conduct. The superior court then held that the committee members were protected by qualified immunity and that the lawsuit was barred by the exclusive remedy statute. The bidders thereafter appealed. Upon review, the Supreme Court concluded that the bidders indeed failed to present a genuine issue of material fact regarding the committee members' alleged bad faith. Furthermore, the exclusive remedy statute barred the bidders' suit. Accordingly, the Court affirmed the trial court's decision.
View "Bachner Company, Inc. v. Weed" on Justia Law
Southwest Power Pool, Inc. v. FERC
This case concerned SPP and MISO's, two regional transmission organizations (RTOs), dispute over the interpretation of a single contract provision. FERC resolved the conflict against SPP. The court applied both the Administrative Procedure Act (APA), 5 U.S.C. 500 et seq., and the "Chevron-like analysis" that governs review of such an interpretation and found that the Commission failed to provide a reasoned explanation for its decision. Accordingly, the court concluded that the Commission's decision was arbitrary and capricious. The court vacated and remanded the orders. View "Southwest Power Pool, Inc. v. FERC" on Justia Law