Justia Contracts Opinion Summaries

Articles Posted in Contracts
by
The Sponsors formed West Run to construct and manage West Virginia University off-campus housing and retained CBRE to secure financing. CBRE provided prospective lenders with confidential information. Huntington’s predecessor loaned $39.975 million and construction began. A competing project (Copper Beach) was built across the street. West Run learned that Huntington had loaned $20 million for that project; West Run alleged that Huntington divulged to Copper Beach proprietary West Run information provided by CBRE. West Run‘s occupancy dropped from 95 percent to 64 percent. West Run sued, alleging that Huntington had breached its duty of good faith and fair dealing by financing Copper Beech. Two similar projects, involving the Sponsors, alleged breach of contract based on Huntington‘s failure to provide funds under their construction loan agreements. Huntington claimed that they had sold insufficient units to require Huntington to disburse additional funds under the agreements. The district court dismissed. The Third Circuit affirmed in part, holding that the complaint contained no corroborating facts that confidential information was disclosed and that no contract terms prohibited Huntington from lending to competitors. The court vacated with respect to the other projects for a chance to provide evidence showing that the pre-sale numbers in the original complaint were incorrect. View "W. Run Student Hous. v. Huntington Nat'l Bank" on Justia Law

by
Plaintiff sought a declaratory judgment against Jax, the exclusive manufacturer and distributor of a game he invented. Plaintiff alleged that Jax breached their contract by granting unauthorized sublicenses and failing to apprise him of unauthorized sales and Jax's response to them. The court held that, even if plaintiff did not waive Jax's breach with his own breach, any factual disputes were not outcome determinative because Jax's breach was neither damaging nor material. Accordingly, the district court properly granted summary judgment. Further, the district court did not err in denying plaintiff's motion to amend the complaint. View "Reuter v. Jax Ltd., Inc." on Justia Law

by
This case arose out of a verbal agreement entered into by Contractor and Landowner to construct a subdivision on a parcel of land. Disagreements arose between the parties, and the subdivision was never completed. Landowner filed this action against Contractor asserting Contractor had failed to make payments on an endloader that had been purchased for the project. Contractor counterclaimed for unjust enrichment based on excavation services he performed on the property. The jury found in favor of Landowner with regard to the endloader and in favor of Contractor with regard to his counterclaim. The trial court found Contractor was entitled to a prejudgment interest on his award of damages on his unjust enrichment claim. Contractor filed a motion to amend the judgment order, contending that the court erred in determining the date on which prejudgment interest began to accrue and had utilized an incorrect prejudgment interest date. The circuit court denied the motion. The Supreme Court reversed the denial of Contractor's motion to amend the judgment order, holding that the trial court erred by awarding Contractor prejudgment interest instead of allowing the jury to determine whether an award of prejudgment interest was warranted. Remanded. View "Ringer v. John" on Justia Law

by
Defendants installed video surveillance cameras at the entrance to an easement crossing their property. Members of a subdivision who benefitted from the easement (Plaintiffs) filed an action for a declaratory judgment and to enjoin Defendants from obstructing their easement rights. Plaintiffs relied on a 2006 settlement to support their position that Defendants were prohibited from installing the cameras. The trial court concluded that Defendants' video surveillance cameras constituted an unreasonable interference with the easement. The Supreme Court vacated the judgment of the superior court, holding (1) the 2006 settlement was relevant evidence to the reasonableness of the cameras, although it was not binding as between the parties to this suit, and the trial court did not err by considering that agreement because its terms provided evidence of the need for injunctive relief; and (2) the placement of the video cameras at issue here did not unreasonably interfere with the access easement benefitting Plaintiffs, nor did the cameras violate the non-disturbance clause in the settlement. Remanded for entry of judgment in favor of Defendants on the video camera issue. View "Flaherty v. Muther" on Justia Law

by
Cogent sued, alleging that Hyalogic was disseminating false information regarding Cogent’s product Baxyl, an “oral, liquid HA supplement that is sold into the human natural products market.” Shortly after the filing, the parties entered into a settlement agreement. Cogent moved to enforce the settlement agreement, claiming that Hyalogic caused false and misleading videos to be uploaded to You Tube and by statements made at a conference. The district court found no breach of the settlement agreement and denied the motion. The Sixth Circuit affirmed. The contract unambiguously refers to a clear statement “about the other Party’s product.” Statements that refer to preservatives that can be found in a number of products, including Cogent’s products, are not statements “about the other Party’s products.” View "Cogent Solutions Grp, LLC v. Hyalogic, LLC" on Justia Law

by
The law firm represented a potential buyer in the purchase of a drugstore. Buyer and Seller executed the sales contract separately. The firm misfiled the contract executed by Buyer, however, and Seller subsequently attempted to rescind the contract, which it characterized as an offer, because it had not timely received a copy of the contract executed by Buyer. When Seller’s efforts to avoid the purported contract were successful, Buyer sent a “formal notice of claim” to the firm, which sought coverage from its professional liability insurer. That insurer concluded that the firm was not entitled to coverage because it failed to properly notify the insurer of the mistake that ultimately led to the malpractice claim. The firm sought a declaratory judgment. The district court granted the insurer summary judgment. The Seventh Circuit affirmed, finding that the firm’s knowledge of the email exchange with Seller’s counsel and of an Alabama declaratory-judgment action constituted knowledge of “any circumstance, act or omission that might reasonably be expected to be the basis of” a malpractice claim. View "Koransky, Bouwer & Poracky, P. C. v. Bar Plan Mut. Ins. Co." on Justia Law

by
In 1983, the Nuclear Waste Policy Act established a plan for spent nuclear fuel (SNF) generated by nuclear power plants, 42 U.S.C. 10101–10270. The Act made utilities responsible for SNF storage until the U.S. Department of Energy (DOE) accepts the material. The Secretary of Energy entered into contracts with nuclear utilities to accept SNF in return for payment of fees. The Act provided that the Nuclear Regulatory Commission “shall not issue or renew a license” to any nuclear utility unless the utility has entered into a contract with DOE or DOE certifies ongoing negotiations. Nuclear utilities, including the owner of the Entergy nuclear power stations, entered into contracts and began making payments, which have continued. By 1994, DOE knew it would be unable to accept SNF by the Act’s January 31, 1998 deadline. In 1995, DOE issued a “Final Interpretation” that took the position that it did not have an unconditional obligation to begin performance on that date. Entergy sued, asserting that DOE’s partial breach caused it to incur additional costs for SNF storage. The claims court struck an unavoidable delay defense, based on a prior decision rejecting DOE’s argument that its failure was “unavoidable” under the contract. The Federal Circuit affirmed. View "Entergy Nuclear Fitzpatrick, LLC v. United States" on Justia Law

by
The Whites were dealers of Kinkade’s artwork. The parties agreed to arbitrate disputes in accordance with the Commercial Arbitration Rules of the American Arbitration Association. In 2002, they commenced arbitration in which Kinkade claimed that the Whites had not paid hundreds of thousands of dollars, and the Whites counterclaimed that they had been fraudulently induced to enter the agreements. Kinkade chose Ansell as its arbitrator; the Whites chose Morganroth. Together Ansell and Morganroth chose Kowalsky as the neutral who would chair the panel. The arbitration dragged on; in 2006, Kinkade discovered that the Whites’ counsel, Ejbeh, had surreptitiously sent a live feed of the hearing to a hotel room. Ejbeh’s replacement departed after being convicted of tax fraud. The Whites did not comply with discovery requests, but after closing arguments and over objections, the panel requested that the Whites supply additional briefs. The Whites and their associates then began showering Kowalsky’s law firm with business. Kinkade objected, to no avail. A series of arbitration irregularities followed, all favoring the Whites. Kowalsky entered a $1.4 million award in the Whites’ favor. The district court vacated the award on grounds of Kowalsky’s “evident partiality.” The Sixth Circuit affirmed. View "Thomas Kinkade Co. v. White" on Justia Law

by
The issue before the Supreme Court in this case concerned the grant of summary judgment dismissing an action to enforce an oral agreement to guaranty the debt of another on the ground that the agreement was barred by the statute of frauds. Sunshine Secretarial Services subleased office space from Accelerated Paving, Inc., and at times provided it with secretarial services. Accelerated Paving owed Plaintiff-Appellant Mickelsen Construction, Inc. money ($34,980.00) for providing asphalt to an Accelerated jobsite. Mickelsen threatened to file a materialmen’s lien against the real property on which the work was being done, and Accelerated's vice president asked that it not do so because that would delay the receipt of payment for the construction job. The vice president offered to pay the debt with an American Express credit card, but Mickelsen responded that it did not accept American Express credit cards. There was disagreement as to what happened next: Accelerate's vice president said there was not enough credit on the card to fund the payment, but when Accelerated received payment for the project it would pay down the balance so that there was enough credit to pay Mickelsen with the card. Mickelsen agreed not to file the lien if Accelerated could find someone to guaranty the payment by the credit card. Defendant-Respondent Lesa Horrocks of Sunshine agreed to do so and gave Mickelsen a check in the amount owed, drawn on Sunshine's account. Sunshine had a credit card machine that was capable of transacting with several credit cards including American Express credit cards. They told her that American Express had approved the transaction and asked her to use Sunshine credit card machine to run the transaction. It appeared to her that the transaction had been approved by American Express. issued the check. Several days later, Accelerated informed her that American Express had not approved the transaction. Accelerated then filed for bankruptcy. Mickelsen then sued Ms. Horrocks and Sunshine alleging that they had agreed to guaranty the credit card payment and so issued the check. The Defendants filed a motion for summary judgment, arguing that the alleged guaranty was barred by the statute of limitations in Idaho Code section 9-505. In response, Mickelsen argued that the check was a sufficient writing under the statute of frauds and, if not, that the transaction was governed by Idaho Code section 9-506 and therefore exempt from the statute of frauds. The district court held that the check was an insufficient writing and that section 9-506 did not apply because the Defendants did not receive any direct benefit. The court granted the motion for summary judgment and entered a judgment dismissing this action. Mickelsen then appealed. Finding no error with the district court's decision, the Supreme Court affirmed. View "Mickelsen Const v. Horrocks" on Justia Law

by
Biolitec, Inc. (BI), a U.S.-based subsidiary of Biolitec AG (BAG), sold medical equipment to Plaintiff AngioDynamics, Inc. (ADI) and agreed to indemnify ADI or any patent infringement claims. Patent infringement claims were subsequently brought against ADI, and ADI settled the claims. In a separate lawsuit, ADI obtained a $23 million judgment against BI under the indemnification clause. Attempting to secure payment on that judgment, ADI sued BAG, BI, and other related entities (collectively, Defendants) on claims including corporate veil-piercing and violation of the Massachusetts Uniform Fraudulent Transfers Act MUFTA), alleging that BAG looted more than $18 million from BI to move BI's assets beyond reach. The district court granted ADI a preliminary injunction barring Defendants from carrying out the proposed downstream merger of BAG with its Austrian subsidiary and from transferring any ownership interest the held in any other defendant. The First Circuit Court of Appeals affirmed, holding (1) as a matter of law, preliminary injunctive relief was not barred in this case; and (2) the district court did not err in finding that ADI had demonstrated likelihood of success on the merits and irreparable harm. View "AngioDynamics, Inc. v. Biolitec AG" on Justia Law