Doe Run Resources Corporation v. St. Paul Fire & Marine Ins Co
This insurance coverage dispute involves claims for coverage by Doe Run Resources Corporation against its insurer, St. Paul Fire & Marine Insurance Company, stemming from multiple lawsuits against Doe Run’s Peruvian subsidiary, Doe Run Peru, which allege various claims stemming from Doe Run Peru’s alleged release of toxic chemicals from a metallurgical plant. After an earlier coverage dispute in state court, where the court determined that a pollution exclusion in St. Paul’s policy precluded coverage, Doe Run filed this action alleging that additional, newly discovered facts implicated an exception to the exclusion that was not raised in the previous state court action. St. Paul filed a motion to dismiss based on issue and claim preclusion. The district court granted the motion based on issue preclusion, and Doe Run appeals.
The Eighth Circuit affirmed, concluding that the district court did not err in granting St. Paul’s motion to dismiss based on issue preclusion, and because the district court did not err, the court wrote, it need not consider the parties arguments regarding claim preclusion. The court explained that in the absence of subsequent events or circumstances representing an actual change between the prior state court action and this action, issue preclusion applies. Here, St. Paul did reconsider Doe Run’s claim for coverage when Doe Run resubmitted the claim following the nine newly filed lawsuits alleging pollution from the La Oroya plant, which alleged a new theory of liability. View "Doe Run Resources Corporation v. St. Paul Fire & Marine Ins Co" on Justia Law
Newfield Exploration Company, et al. v. North Dakota, et al.
The State of North Dakota, ex rel. the North Dakota Board of University and School Lands, and the Office of the Commissioner of University and School Lands, a/k/a the North Dakota Department of Trust Lands appealed a judgment dismissing its claim against Newfield Exploration Company relating to the underpayment of gas royalties. The North Dakota Supreme Court found that the district court concluded the State did not establish a legal obligation owed by Newfield. However, the State pled N.D.C.C. § 47-16-39.1 in its counterclaim, which the court recognized at trial. Because the State satisfied both the pleading and the proof requirements of N.D.C.C. § 47-16-39.1, the Supreme Court held the district court erred in concluding the State did not prove Newfield owed it a legal obligation to pay additional royalties. Rather, as the well operator, Newfield owed the State an obligation under N.D.C.C. § 47-16-39.1 to pay royalties according to the State’s leases. The court failed to recognize Newfield’s legal obligations as a well operator under N.D.C.C. § 47-16-39.1. The Supreme Court concluded the district court erred in dismissing the State's counterclaim; therefore, judgment was reversed and the matter remanded for findings related to the State's damages and Newfield's affirmative defenses. View "Newfield Exploration Company, et al. v. North Dakota, et al." on Justia Law
United Heritage v. Zech
After receiving reminder notices by mail, the insureds failed to pay a renewal premium for a rented home by the due date. Fourteen days after payment was due, the insureds mailed a check to the insurance company for the late renewal premium. Six days later, but before the insurance company reviewed the late payment, a fire occurred at the home. Two days after the fire, the insurance company returned the late payment, denied coverage for the loss, and denied reinstatement of the policy. The insurance company subsequently brought a declaratory judgment action against the insureds. The district court granted summary judgment in favor of the insurance company. Finding no reversible error in that judgment, the Idaho Supreme Court affirmed. View "United Heritage v. Zech" on Justia Law
Payne-Elliott v. Roman Catholic Archdiocese of Indianapolis, Inc.
The Supreme Court affirmed the judgment of the superior court dismissing this action under Indiana Trial Rule 12(B)(6) but modified the judgment to reflect that the dismissal was without prejudice, holding that the church-autonomy doctrine applied in this case and required its dismissal under Rule 12(B)(6).Plaintiff sued the Roman Catholic Archdiocese of Indianapolis, Inc., asserting intentional interference with his contract and employment with Cathedral High School. The Archdiocese moved to the dismiss the complaint and invoked three defenses under the First Amendment, including the church-autonomy defense. The trial court dismissed the case with prejudice for failure to state a claim and for lack of subject-matter jurisdiction. The Supreme Court affirmed, holding that dismissal under Rule 12(B)(1) was improper but that the church-autonomy doctrine barred Plaintiff's claims. View "Payne-Elliott v. Roman Catholic Archdiocese of Indianapolis, Inc." on Justia Law
24th & Hoffman Investors, LLC v. Northfield Insurance Co.
Northfield issued a policy to insure an apartment complex. The coverage excludes liability for violations of the insured’s duty to maintain habitable premises; this exclusion also encompasses coverage for “any claim or ‘suit’ ” that also alleges habitability claims. Tenants sued the insured, alleging multiple habitability claims and other causes of action that were arguably not based on habitability. Northfield declined to defend the tenants’ lawsuit. After settling the underlying action, the insured sued Northfield for breach of its duty to defend. The trial court concluded the case presented a “mixed” action containing both potentially covered and uncovered claims, and that Northfield was obliged to provide a defense.The court of appeal reversed. The policy exclusion is plain and clear. The court rejected arguments that claims for retaliation, conversion, and trespass to chattels did not arise from the duty to provide habitable premises. The retaliation concerned complaints about habitable conditions and the claims are alleged in a suit that also alleges habitability claims. View "24th & Hoffman Investors, LLC v. Northfield Insurance Co." on Justia Law
Greenbank v. Great American Assurance Co.
Greenbank purchased “Thomas” for $500,000, for use as a competitive showhorse. Greenbank obtained insurance from GA that included coverage for Thomas’s “death” or “authorized humane destruction.” In February 2018, Thomas became sick. Over the next few months, Thomas lost 50 pounds and developed cellulitis in all four legs and uveitis in his eye. In April 2018, Greenbank reported Thomas’s pneumonia to GA. Greenbank's veterinarian informed GA that Thomas “probably” needed to be euthanized. GA retained its own veterinarians. Thomas was transported to its facility, where Dr. MacGillivray advised that it would not be unreasonable to make a euthanasia recommendation but she wanted to try treatment. Greenbank objected, arguing that treatment would destroy Thomas’s future athleticism. After his surgery, Thomas made a "remarkable" recovery. Thomas is still doing well.GA denied coverage for certain treatments and rejected Greenbank’s renewal payment of $14,725.000, citing her failure to provide immediate notice of Thomas’s illness in February 2018. Greenbank argued that GA acted in bad faith by unreasonably withholding consent for authorized humane destruction and that GA’s continued care and control over Thomas after the policy terminated constituted conversion and theft.The Seventh Circuit affirmed the dismissal of her claims. Thomas saw three veterinarians in five months; no veterinarian certified that Thomas needed to be euthanized. Nothing in the contract requires GA to protect Thomas’s use as a show horse. Greenbank never made an unqualified demand for Thomas’s return nor did she establish that any demand would have been futile. View "Greenbank v. Great American Assurance Co." on Justia Law
STATE OF HAWAII V. USEDU
In an action brought by the State of Hawaii challenging the U.S. Department of the Army’s changes to the operation of its dining facilities at Schofield Barracks and Wheeler Army Airfield in Honolulu, Hawaii, the Ninth Circuit reversed the district court’s conclusion that the Randolph-Shepard Act (“RSA”) did not apply to Dining Facility Attendant (“DFA”) contracts, and affirmed the district court’s conclusion that the RSA advance review provision applied to the reclassification of a Schofield Barracks contract.
The panel held that the district court applied an incorrect standard of review to the RSA arbitration panel’s construction of 20 U.S.C. Section 107(a) when it deferred heavily to the arbitration panel’s interpretation. Because the RSA did not delegate interpretive authority to the arbitration panel, the panel reviewed de novo. The panel held that the term “operate” was ambiguous in Section 107(a).
The panel held further that the statutory structure of the RSA supported a broad interpretation in favor of increased opportunities for blind vendors, and the implementing regulations swept even more broadly and counseled strongly in favor of applying the RSA to DFA contracts. The panel affirmed the district court’s conclusion that the RSA advance review requirement applied to the Army’s reclassification of Schofield Barracks’ dining facilities. View "STATE OF HAWAII V. USEDU" on Justia Law
NW AR Conservation Authority v. Crossland Heavy Contractors
The Northwest Arkansas Conservation Authority is a public corporation created to handle wastewater treatment for municipalities in northwest Arkansas. After a series of pipeline failures, the Authority sued the pipeline contractor and its surety, alleging deficient construction. The Authority sued outside the time periods specified in the relevant statutes of limitations and repose, but asserted that the time did not run against its claims, because the Authority was suing as a public entity seeking to vindicate public rights. The district court concluded that the rights the Authority sought to enforce were merely proprietary and that its claims were therefore time-barred.
The Eighth Circuit affirmed. The court explained that the relevant proprietary interests are not transformed into public rights just because the Authority spent public money to repair the pipeline. Every action by a public entity impacts the public fisc to some degree. But if financial implications alone were enough to invoke nullum tempus, then the public-rights exception would swallow the general rule that statutes of limitations and repose run against municipal entities. Here, the damages sought would replenish the public entity’s coffers, but the relief would not vindicate a distinct public right. The Authority therefore cannot invoke nullum tempus to avoid the statutes of limitations or repose. View "NW AR Conservation Authority v. Crossland Heavy Contractors" on Justia Law
CX Reinsurance Co. v. Johnson
The Court of Appeals held that an injured tort claimant's rights under a general liability insurance policy do not vest until the claimant has obtained a judgment against, or entered into a qualifying settlement with, an insured.CX Reinsurance Company issued commercial general liability policies to several Baltimore residential Landlords that included coverage for bodily injuries resulting from lead paint exposure at the Landlords' rental properties. CX field contract rescission actions against the Landlords, which the parties settled. Under the terms of the rescission settlements, the coverage for lead paint-related losses was substantially reduced. Claimants alleged they suffered bodily injuries from lead paint exposure while residing in the Landlords' rental properties, but the majority of claimants had not obtained final judgments against, or entered into settlements with, the Landlords before CX and the Landlords settled. The lower courts ruled that the Claimants were intended beneficiaries of the polices. The Court of Appeals reversed in part, holding (1) the Claimants who did not hold final judgments against or enter into approved settlement agreements with the Landlords were not the intended beneficiaries under the policies; and (2) the Claimants who obtained final judgments against their Landlords prior to the settlements of the applicable rescission cases may enforce the pre-settlement terms of the policies. View "CX Reinsurance Co. v. Johnson" on Justia Law
Robert Gelschus v. Clifford Hogen
Plaintiff made contributions to a 401(k) plan during her employment at Honeywell International Inc. She originally designated her husband, Defendant, as the sole beneficiary in the event of her death. The parties later divorced and in the marital termination agreement (MTA), they agreed that Plaintiff will be awarded, free and clear of any claim on the part of Defendant’s, all of the parties’ right, title, and interest in and to the Honeywell 401(k) Savings and Ownership Plan. Plaintiff submitted a change-of-beneficiary form to Honeywell. She, however, did not comply with a requirement.
Plaintiff died in 2019 and Honeywell paid the benefits to Defendant. The personal representative of Plaintiff’s estate sued Honeywell for breach of fiduciary duty, and Defendant for breach of contract, unjust enrichment, conversion, and civil theft. The Eighth Circuit affirmed summary judgment for Honeywell and reversed summary judgment for Defendant on the breach of contract and unjust enrichment claims.
The court explained that even if the Plan gave the administrator discretion to accept Plaintiff’s defective Form, it is not an abuse of discretion to act in accordance with plan documents. ERISA directs administrators to “discharge [their] duties . . . in accordance with the documents and instruments governing the plan.” Thus, because Honeywell followed plan documents in rejecting Plaintiff’s defective change-of-beneficiary form and distributing benefits, the breach of fiduciary duty claim fails. Further, even if the MTA were ambiguous, a reasonable jury could find that Plaintiff and Defendant intended for the MTA to waive his beneficiary interest in the 401(k). View "Robert Gelschus v. Clifford Hogen" on Justia Law