Justia Contracts Opinion Summaries

Articles Posted in Construction Law
by
Petitioner, The Affiliated Construction Trades Foundation (ACT), filed a declaratory judgment action seeking a declaration that a public highway construction contract awarded to Respondent, Nicewonder Contracting, Inc., by Respondent, West Virginia Department of Transportation, Division of Highways (DOH), violated state competitive bidding and prevailing wage laws. The circuit court dismissed ACT's action, finding it lacked standing to challenge the highway construction contract. The Supreme Court reversed, finding that ACT had representative standing to seek the declarations. On remand, the circuit court determined that the Court's opinion in ACT I did not completely decide the issue of ACT's standing and ordered that ACT join the Federal Highway Administration (FHWA) as a defendant in the action. The Supreme Court subsequently granted ACT's requested writ of prohibition because the circuit court did not give effect to the mandate of the Court in ACT I, holding (1) ACT, as a matter of law, had standing to prosecute its lawsuit; and (2) FHWA was not an indispensable party to the lawsuit.

by
This case arose from a contract entered into by the parties where Ewing agreed to construct tennis courts for the school district. At issue was the interpretation of a Commercial General Liability (CGL) insurance policy under Texas law. The district court held that a CGL policy's contractual liability exclusion applied in this case and that no exception restored coverage. The insured construction company faced liability, if at all, because it contracted to construct usable tennis courts for the school district and it had allegedly failed to perform. The court held that the district court correctly interpreted the contractual liability exclusion and correctly applied that exclusion with respect to the insurer's duty to defend the construction company. The court held, however, that the district court was premature in applying the exclusion to the insurer's duty to indemnify.

by
David Bennett and Bennett & Bennett Construction, Inc. ("Bennett") appealed the trial court's denial of their motion to compel arbitration of the claims alleging fraud in the inducement and the tort of outrage brought against them by Barbara and Leotes Skinner. The Skinners entered into a construction-services contract with Bennett, pursuant to which Bennett was to renovate and remodel their residence located in Oxford. After disagreements developed between the parties, the Skinners sued Bennett, alleging claims of breach of contract; breach of warranty; fraud in the inducement; assault and battery; the tort of outrage; and negligence, wantonness and recklessness. Bennett moved to compel arbitration of all claims, arguing that, because each of the claims alleged by the Skinners arose from the construction-services contract or were related to the construction-services contract, the claims were subject to arbitration. Furthermore, Bennett argued that the tort-of-outrage claim arose out of a disagreement concerning the construction-services contract and that the Skinners should not be allowed to avoid arbitration because they cast their claim as a tort. The Skinners responded, arguing that their agreement to the arbitration clause in the contract was obtained fraudulently. The trial court denied Bennett's motion. Upon review, the Supreme Court concluded that the Skinners' tort-of-outrage claim arose out of a disagreement concerning the construction-services contract and thus was a proper claim for arbitration. The Court reversed the trial court's ruling and remanded the case for further proceedings.

by
KM Upstream, LLC and Newpoint, Inc. entered into a contract whereby Newport would construct for KM's amine plant. Newpoint subcontracted with Elkorn Construction, Inc. to build the foundation and perform other work. Elkhorn subsequently filed a lien statement with the county clerk. Elkhorn later filed a complaint against KM for, inter alia, foreclosure of the lien as a mechanic's lien. Newpoint was later added as a defendant. The district court granted summary judgment to Elkhorn to allow foreclosure on the mechanic's lien. The Supreme Court (1) affirmed the grant of summary judgment; but (2) reversed and remanded the district court's determination that $181,369 of Elkhorn's lien claim was disputed and its subsequent order subtracting that amount from Elkhorn's judgment.

by
Andrews was designated as contractor for improvements to the sewage system, in a no-bid process involving kickbacks and bribery, having made numerous false statements in the bond application package. After the contract was terminated, he submitted a claim of $748,304, based on false statements and duplicate charges. Evidence indicated that Andrews was not capable of the project work and that the entire scheme was fraudulent. He was convicted of one count of conspiracy, 18 U.S.C. 371, four counts of wire fraud, 18 U.S.C. 1343, 1346, and 2, one count of program fraud, 18 U.S.C. 666(a)(1)(B) and 2, one count of making a false claim upon the Government of the Virgin Islands, 14 V.I.C. 843(4), and one count of inducing a conflict of interest, 3 V.I.C. 1102, 1103, and 1107. The Third Circuit affirmed the conviction, but remanded for resentencing. Errors in the indictment and jury instructions concerning honest services fraud did not affect substantial rights. Although the 151-month term of imprisonment was within the statutory maximum for Counts Two through Five, it exceeded the statutory maximum for Counts One and Six; it was not possible to determine whether the sentence was legal as to each count

by
An owner and contractor entered into an agreement for the construction of a new home. During construction, the owner refused to pay the contractor after discovering markups on the cost of materials. In response, the contractor halted construction and filed an action to enforce a mechanic's lien. The contractor subsequently filed a petition to foreclose the mechanic's lien. Although the contractor did not complete construction, the district court found the contractor rendered substantial performance under the contract and entered a judgment against the owner. The court of appeals affirmed. The Supreme Court affirmed in part and vacated in part the court of appeals and reversed the district court, holding that the trial court erred in concluding that the contractor had substantially completed work for the owner. Remanded.

by
Northstar Battery Company, LLC ("Northstar"), petitions this Court for a writ of mandamus directing the Cullman Circuit Court to vacate its order denying Northstar's motion to dismiss the action filed against it by Apel Steel Corporation ("Apel") and to enter an order dismissing the action for lack of in personam jurisdiction. The case stemmed from a contract in which Apel Steel was working as a subcontractor for a battery manufacturing plant in Springfield, Missouri. Northstar Battery, owner of the plant, contracted with Walton Construction to serve as general contractor. Apel had further subcontracted a portion of its work to JS Nationwide, who erected structural steel at the plant. Sparks from welding started a fire which resulted in the destruction of property/equipment, and caused heat and smoke damage in the affected area of the plant. The contract between Apel and Walton contained a provision by which Apel allegedly waived all rights against JS Nationwide. Counts against Northstar alleged negligence, unjust enrichment, breach of contract, misrepresentation and conspiracy. Northstar moved to dismiss citing lack of personal jurisdiction. Finding that Apel failed to carry its jurisdictional burden, the Supreme Court held that the trial court "clearly" erred in denying Northstar's motion to dismiss. Accordingly, the Court granted Northstar's petition and issued the writ.

by
Circle Y filed a complaint alleging, among other things, breach of contract when the school district terminated a construction management services contract with Circle Y. The trial court denied the school district's motion to dismiss and the court of appeals affirmed. The court held that, in light of the determination by the court of appeals that the trial court correctly denied the motion to dismiss because Circle Y's complaint alleged facts that, when taken as true, established that the contract was not void as a matter of law due to voter approval of the educational local option sales tax, it was not necessary for the court of appeals to construe OCGA 20-2-506(h) in order to resolve the appeal. Accordingly, the court remanded to the court of appeals with direction that it vacate that portion of the Division order that addressed OCGA 20-2-506.

by
Plaintiffs appealed the dismissal of their complaint challenging a number of agreements entered into by the City of New York with respect to labor conditions on certain City construction projects. Plaintiffs argued that the agreements regulated the labor market and were therefore preempted by the National Labor Relations Act, 29 U.S.C. 151-169. The court found the project labor agreements in this case materially indistinguishable from agreements the Supreme Court found permissible under the market participation exception to preemption in Building and Construction Trades Council of Metropolitan District v. Associated Builders and Contractors of Massachusetts/Rhode Island Inc. Because the City acted as a market participant and not a regulator in entering the agreements, its actions fell outside the scope of NLRA preemption. Therefore, the court affirmed the judgment of the district court.

by
This case arose when a real estate developer hired HOD to act as general contractor for the construction of two multi-family residences. HOD entered into a subcontract with Well Built for the masonry work. At issue was whether a general contractor acted as a joint employer of masonry workers, who were employed by one of its subcontractors, thereby owing unpaid wages to the subcontractor's workforce. The court held that the Board erred as a matter of law in relying on the federal six-factor test in Zheng v. Liberty Apparel Co., Inc. in reaching its determination of joint employment. Because the Board's factual findings indicated nothing more than that the usual contractor/subcontractor relationship existed between HOD and Well Built during the three-month period that Well Built's principal, Martin Bruten, was on the job, the court need not resort to federal precedent to resolve the issue. In any event, even if the court were to apply the Zheng test, the court would hold that HOD was not a joint employer of Well Built's employees. Accordingly, the judgment of the Appellate Division should be reversed and the matter remitted with directions to remand to the Board for further proceedings.