Justia Contracts Opinion Summaries

Articles Posted in Construction Law
by
A general contractor (Carlisle) for a construction project contracted with Plaintiff to perform carpentry work for the project. A bond was issued for the project. Carlisle was the principal on the bond, and International Fidelity Insurance Company (IFIC) was the surety. Plaintiff later filed suit against Carlisle and IFIC seeking to recover payment for the work it performed. The arbitrator issued two amended awards. Plaintiff moved the superior court to confirm the second amended awarded concerning Carlisle's liability and to modify it as to IFIC. The trial justice remanded the matter back to the arbitrator for a determination as to IFIC's liability. The arbitrator on remand found that both Carlisle and IFIC were liable to Plaintiff for $43,543. The trial justice confirmed the post-remand arbitration award. The Supreme Court affirmed but on different grounds, holding (1) the second amended award should have been vacated under R.I. Stat. 37-16-18(2), and the trial justice was authorized, under section 37-16-19, to remand the case to the same arbitrator for a hearing; and (2) because the remand in this case accomplished the same result that could have been accomplished under section 37-16-18 and 37-16-19, the judgment was affirmed. View "Drago Custom Interiors, LLC v. Carlisle Bldg. Sys., Inc." on Justia Law

by
Kadrmas, Lee & Jackson, Inc., ("KLJ") appealed a district court judgment awarding the City of Valley City ("City") costs and expenses the City incurred defending itself in the underlying lawsuit and pursuing its indemnity claim against KLJ. The City entered into a contract with KLJ to provide engineering services for a paving and sewer project. The City hired a general contractor for the project. The contract between the City and the contractor required the contractor to furnish all labor, materials, and equipment for the project. The contractor was required to provide a payment bond under the terms of its contract with the City, and St. Paul Fire & Marine Insurance Company ("St. Paul") was the surety under the bond. Specialized Contracting, Inc. ("SCI"), entered into a subcontract with the contractor to complete some of the work on the project. In 2007, SCI sued St. Paul for breach of its duties under the payment bond, seeking compensation for additional work SCI alleged it completed on the project for which the contractor refused to pay. St. Paul served a third-party complaint against the City for breach of contract and indemnity, alleging the concrete repair work was outside the scope of the City's contract with the contractor, the City was liable to the contractor for any additional compensation SCI was claiming against the payment bond if SCI established KLJ's decision to replace the concrete was beyond the scope of the contract, and the City was required to indemnify St. Paul for any judgments against it in favor of SCI arising from decisions made by KLJ. Upon review of the matter, the Supreme Court concluded KLJ did not have a duty to defend the City. The Court reversed the district court's judgment awarding the City costs and expenses, and remanded the case for a determination of whether KLJ was entitled to recover its costs and expenses as a prevailing party. View "Specialized Contracting, Inc. v. St. Paul Fire & Marine Ins." on Justia Law

by
The owners of two properties leased them to developer-tenants for the purpose of building an apartment building on each. As construction was beginning, the landlords breached the leases by refusing to provide estoppel certificates and contesting the tenants' building permits. The landlords' breach prevented the tenants from obtaining financing, which ended the development project. The tenants sued for lost profits. Before trial, the circuit court ruled against the landlords on several motions, holding in part (1) the landlords could not introduce evidence of the 2008 crash in the real estate market to show that the tenants would not have made profits, and (2) the tenants could introduce evidence of the landlords' reasons for breaching, including communications with their former counsel. The jury awarded the tenants over $36 million in damages, holding the landlords jointly and severally liable. The court of special appeals held the landlords could not be held jointly and severally liable but otherwise affirmed. The Court of Appeals affirmed, holding (1) the trial court did nor err in excluding all evidence of post-breach market data in measuring damages; and (2) the landlord waived the attorney-client privilege as to communications relevant to the subject matter of the claim of bad faith. View "CR-RSC Tower I, LLC v. RSC Tower I, LLC" on Justia Law

by
The Corps contracted with Atlantic for the construction of a child development center and Atlantic entered into a Subcontract Agreement with J-Crew for labor and materials. The Subcontract Agreement included a forum-selection clause, which provided that disputes shall be litigated in Virginia courts. Ignoring the forum-selection clause, J-Crew filed suit against Atlantic in Texas. Applying 28 U.S.C. 1404(a), the district court denied Atlantic's motion to transfer, finding that Atlantic had not met its burden of showing why the interest of justice or the convenience of the parties and their witnesses weighed in favor of transferring the case to Virginia. Atlantic subsequently petitioned the court for a writ of mandamus to dismiss or transfer the case. Because the court found that the district court did not clearly abuse its discretion by considering enforcement of the forum-selection clause under section 1404(a), instead of under Rule 12(b)(3) and section 1406; and by conducting its analysis under section 1404(a), the court denied the petition. View "In re: Atlantic Marine Const Co. Inc." on Justia Law

by
In this construction defect case, defendant moved for summary judgment, and the trial court granted the motion. Plaintiff then filed a "motion for reconsideration" of the summary judgment ruling. The court meanwhile entered judgment, and plaintiff filed a notice of appeal. When the trial court later denied the motion for reconsideration, plaintiff did not file a new notice of appeal. The question in this case was whether plaintiff needed to do so. Defendant argued that, because a motion for reconsideration constitutes a motion for new trial, its filing rendered plaintiff's earlier notice of appeal premature and, as a consequence, a nullity. Plaintiff argued that the motion for reconsideration did not constitute a motion for a new trial and thus had no effect on the filing of the notice of appeal. The Court of Appeals concluded that, under "Carter v. U.S. National Bank," (747 P2d 980 (1987)), a motion for reconsideration constitutes a motion for a new trial. Nevertheless, the court held that the filing of the motion did not have the effect of rendering the appeal a nullity. Consequently, the court concluded that plaintiff was not required to file a new notice of appeal. Upon review, the Supreme Court held that "Carter" and earlier decisions declaring that a motion for reconsideration of a summary judgment constitutes a motion for a new trial were incorrectly decided. In this case, plaintiff's filing of the motion for reconsideration of the summary judgment did not render the filing of the notice of appeal premature. Accordingly, the Court affirmed the decision of the Court of Appeals on different grounds. View "Assoc. Unit Owners of Timbercrest Condo v. Warren" on Justia Law

by
The Phenix City Board of Education ("the Board") sought mandamus relief from the Russell Circuit Court's denial of the Board's motion to dismiss or, in the alternative, for a summary judgment on claims brought against it by The Lisle Company, Inc. ("Lisle"). Because the Board is immune from suit pursuant to § 14, Ala. Const. 1901, the Supreme Court granted the Board's petition and issued the writ. View "Lisle Company, Inc. v. Phenix City Board of Education" on Justia Law

by
Riverbend Community, LLC and Parkway Gravel, Inc. jointly owned a parcel of land (the Property), which they intended to develop into residential real estate. Before purchasing the Property, Riverbend and Green Stone Engineering, LLC signed a August 2005 Contract, which required Green Stone to perform four tasks: (1) Site Evaluation and Regulatory Review, (2) Wetlands Restoration Conceptual Design, (3) Wetland Enhancement Conceptual Layout, and (4) Regulatory Meetings and Presentation. In March 2006, the parties signed a second contract which required Green Stone to provide design services for the site and roadways, the stormwater collection and conveyance systems, the sanitary sewer system, the water supply piping system, the stormwater management plans, the sediment and erosion control plans, and the landscape plans. Green Stone left the project in late 2007. Riverbend hired a new engineering firm to complete the work, but the new firm needed Green Stone's work product. Green Stone would not release its work product unless Riverbend executed a release. In 2009, the U.S. Army Corps of Engineers issued two Cease and Desist Letters against Riverbend because of the work in the wetlands. Meanwhile, the Delaware Department of Natural Resources and Environmental Control filed a complaint against Riverbend too. As a result of the federal and state issues, Riverbend could not sell houses, and its lender foreclosed on and purchased the Property at a sheriff's sale in April 2012. Riverbend sued Green Stone for breach of contract, professional negligence, and simple negligence. Green Stone moved for summary judgment on the grounds that the economic loss doctrine barred the tort claims and the general release barred all claims. The trial judge granted the motion, and Riverbend appealed. Upon review, the Supreme Court interpreted the release as a general release, and did not address the application of the economic loss doctrine. Because the Court found the release was a general release that unambiguously waived all claims, the Court affirmed the grant of summary judgment below on both the tort and contract claims. View "Riverbend Community, LLC, et al. v. Green Stone Engineering, LLC, et al." on Justia Law

by
Younglove Construction entered into a contract with PSD Development for the construction of a feed-manufacturing plant. When PSD withheld payment, Younglove brought this diversity suit against PSD and three other defendants. In its answer, PSD alleged it had sustained damages as a result of defects in a steel grain bin constructed by Custom Agri Systems, Inc. as a subcontractor. Younglove filed a third-party complaint against Custom Agri Systems, Inc. for contribution and indemnity. Custom turned to its insurer, Westfield Insurance Company, to defend and indemnify it in the litigation. Westfield intervened to pursue a judgment declaring it had no such duty under the terms of its commercial general liability (CGL) policy with Custom. At issue was whether the claims against Custom sought compensation for "property damage" caused by an "occurrence" under the policy. The district court granted summary judgment for Westfield. On appeal, the federal court of appeals certified questions of state law to the Supreme Court. The Court answered by holding that claims of defective construction or workmanship brought by a property owner are not claims for "property damage" caused by an "occurrence" under a CGL. View "Westfield Ins. Co. v. Custom Agri Sys., Inc." on Justia Law

by
This action arose from a bidding dispute between Bidder and Owner over a contract to install rubber flooring for a renovation project. Bidder filed a complaint against Owner, alleging that the biding specifications were ambiguous, the bidding process was unfair, and that Owner improperly imposed a sole source specification in violation of law. Bidder also sought recovery of attorneys' fees incurred in bringing this action. Later, Owner withdrew the solicitation, rendering Bidder's complaint moot. The parties subsequently filed cross-motions for summary judgment on Bidder's request for attorneys' fees. The Court of Chancery granted Owner's motion for summary judgment, holding that Bidder failed to demonstrate that Owner's conduct warranted an award of attorneys' fees and expenses. View "Marra v. Brandywine Sch. Dist." on Justia Law

by
Plaintiffs, owners of condominium units that were destroyed by Hurricane Katrina, sued defendants after defendants failed to complete construction of the rebuild. Plaintiffs appealed the district court's grant of summary judgment in favor of defendants, based on the district court's finding that the 24-month construction obligations in the Purchase Agreements were not illusory and, therefore, the parties' contracts were exempted from the Interstate Land Sales Full Disclosures Act (ILSA), 15 U.S.C. 1701, et seq. The court found that the language of the Purchase Agreements did not negate plaintiffs' abilities to seek damage and specific performance remedies. Accordingly, the court affirmed the district court's grant of summary judgment. View "Hillman, et al v. Loga, III, et al" on Justia Law