Justia Contracts Opinion Summaries

Articles Posted in Construction Law
by
The Wicks Law requires public entities seeking bids on construction contracts to obtain separate specifications for three subdivisions of the work to be performed. Until 2008 when the law was amended to raise the threshold, the Wicks Law applied to contracts whose cost exceeded $50,000. The new, higher thresholds, unlike the old one, were not uniform throughout the State. Plaintiffs claimed, inter alia, that the amendments violated the Home Rule section of the State Constitution by unjustifiably favoring the eight counties with higher thresholds. Supreme Court dismissed the complaint, holding that Plaintiffs lacked standing to assert the Home Rule cause of action and that, in any event, the challenged amendments did not violate the Home Rule section because they "were enacted in furtherance of and bear a reasonable relationship to a substantial State-wide concern." The Appellate Division affirmed. The Court of Appeals affirmed as modified, holding (1) at least one plaintiff had standing to assert the Home Rule claim, but that claim failed on the merits; and (2) most of Plaintiffs' other claims failed, but four causes of action challenging the apprenticeship requirements as applied to out-of-state contracts should be reinstated. View "Empire State Chapter of Associated Builders & Contractors v. Smith" on Justia Law

by
Ground Control, LLC appealed the grant of summary judgment in favor of Capsco Industries, W.G. Yates & Sons Construction and Harrah's Entertainment, Inc. The parties contracted to build the "Margaritaville Spa and Hotel" in Biloxi. The circuit court held in part that Ground Control's failure to obtain a certificate of responsibility rendered its contract with Capsco null and void. After its review of the circuit court record, the Supreme Court agreed (and affirmed) that the lack of the certificate of responsibility rendered the contract null and void. However, the Court reversed the grant of summary judgment in part so that the circuit court could determine whether Ground Control was entitled to recover based on claims of unjust enrichment and/or quantum meruit. View "Ground Control, LLC v. Capsco Industries, Inc." on Justia Law

by
Guardian Builders, LLC, and Wayne Tackett (collectively "Guardian") appealed an order that denied its motion to vacate or modify an arbitration award entered in favor of Randy and Melissa Uselton. In April 2010, the Useltons sued Guardian alleging several claims arising from Guardian's construction of a house. Guardian subsequently filed a motion to compel arbitration, and the circuit court granted that motion. The arbitrator entered a final award in favor of the Useltons in the amount of $452,275.20. Upon review, the Supreme Court construed Guardian's motion to vacate or modify the arbitration award of as a notice of appeal under Rule 71B, thus effectuating the appeal of the award to the circuit court. However, because the clerk of the circuit court never entered the award as the judgment of that court, the circuit court's order denying Guardian's motion to vacate or modify was void. "Essentially, Guardian's appeal remains pending in the circuit court, awaiting further procedures under Rule 71B. Further, because Guardian has appealed from the arbitration award under Rule 71B, that award could not be entered as the judgment of the court under 71C. Thus, the circuit court lacked authority to enter a judgment on the award under Rule 71C and to award Better Business Bureau fees and facility costs in connection with the entry of that judgment." View "Guardian Builders, LLC v. Uselton " on Justia Law

by
Compass Construction and First Baptist Church were named as defendants in an action arising from a construction accident. Ultimately, First Baptist prevailed against the plaintiff in the main action and on its cross-claim for indemnity against Compass. First Baptist was awarded attorneys fees as part of its indemnity claim, but the parties disagreed about the appropriate hourly rate at which the fee for First Baptist's attorney should be calculated. In the main action, First Baptist's insurance company assigned an attorney to represent First Baptist. The attorney had a written fee agreement with the insurance company providing that attorney would be paid $170 per hour. In an alternative fee recovery clause, however, the agreement provided that if anyone other than the insurance company was required to pay attorney's fees, the attorney's hourly rate would be $300. The trial court calculated the award at the higher rate. The court of appeal reversed. The Supreme Court reversed, holding that the alternative fee recovery clause was valid. Remanded for reinstatement of the judgment awarding attorney's fees. View "First Baptist Church of Cape Coral, Fla., Inc. v. Compass Constr., Inc." on Justia Law

by
Western Wyoming Construction Company (WWC) submitted a bid for a highway project in Sublette County. The Board of County Commissioners of Sublette County (Commissioners) awarded the contract to another resident contractor whose bid was higher than WWC's. WWC filed a complaint in district court for an order awarding it the contract for the project. The district court granted summary judgment in favor of the Commissioners. At issue on appeal was whether Wyo. Stat. 16-6-102(a) required the Commissioners to award the contract to the responsible certified Wyoming resident making the lowest bid. The Supreme Court reversed, holding (1) section 16-6-102 has no application in the context of two resident contractors; and (2) because no evidence was presented showing where the funds came from to pay for the project, (i) there could be no finding as to what statutory provision, if any, was applicable, and (ii) a judicial determination as to the appropriateness of the bid award was not possible. Remanded. View "W. Wyo. Constr. Co., Inc. v. Bd. of County Comm'rs" on Justia Law

by
Plaintiffs entered into a contract with DJ Construction (DJ) to build a home on their property. Construction was halted two years later after Plaintiffs discovered significant water damage in the home. Plaintiffs sued DJ, seeking to recover for the damage to their home and DJ's failure to complete the house. Auto-Owners Insurance Company, DJ's insurer, denied DJ's requests for defense and indemnity against Plaintiffs' claims, determining coverage was not provided for under the terms of the policy. Plaintiffs subsequently entered into a stipulated judgment and settlement agreement with DJ in which DJ confessed judgment and assigned its rights and claims against Owners to Plaintiffs. Plaintiffs then filed suit against Owners based on Owners' failure to defend and indemnify DJ. The circuit court granted summary judgment in favor of Owners, determining there was no coverage under the policy because multiple policy exclusions applied. The Supreme Court affirmed, holding that the circuit court did not err in granting summary judgment in favor of Owners on Plaintiffs' breach of contract and bad faith claims based upon its determination that multiple policy exclusions applied. View "Swenson v. Owners Ins. Co." on Justia Law

by
This dispute centered on a contract for the construction of a residence. The contract between the general contractor (Contractor) and the owners (Owners) was contingent upon Owners obtaining financing. After construction was completed, Contractor asserted a materialman's lien on the house, arguing that Owners had refused to fully compensate Contractor. After Owners filed suit to protest the lien, the parties agreed to discharge the lien. Contractor later sued Owners based on Owners' failure to disclose that they had obtained inadequate financing. The circuit court dismissed the complaint on the grounds that Contractor's claims were statutorily barred for failure to strictly comply with requirements for the notice of its lien. The order was silent as to the other two grounds Owners had asserted for dismissal and with respect to any of the arguments raised in defense of Owners' motion to dismiss. Contractor appealed, arguing reversal based on other arguments raised below but not ruled on. The Supreme Court affirmed, as (1) the circuit court did not provide a ruling on Contractor's first three arguments, and they were therefore not preserved for appellate review; and (2) Contractor's fourth argument had no merit given the Court's summary affirmance on the first three points. View "TEMCO Constr., LLC v. Gann" on Justia Law

by
The Supreme Court granted certiorari to review the court of appeals decision affirming the circuit court's order that upheld an arbitration award. The underlying dispute arose from a construction contract whereby general contractor respondent C-Sculptures, LLC agreed to build a home for Petitioners Gregory and Kerry Brown. The contract price was in excess of $800,000. However, Respondent only possessed what is referred to as a Group II license, limiting Respondent to construction projects that did not exceed $100,000. A dispute arose between the parties, and Respondent filed an action in circuit court seeking to enforce a mechanic's lien against Petitioners. Upon Petitioners' motion and pursuant to an arbitration clause in the parties' contract, the circuit court matter was stayed pending arbitration. Petitioners sought to have the matter dismissed after they learned Respondent held only a Group II license. The arbitrator was apprised of the applicable law, but nevertheless denied Petitioners' motion to dismiss "after due consideration of all the evidence and authorities presented by the parties in this Arbitration." Respondent prevailed at arbitration, receiving an award of damages and an award of attorney's fees as the prevailing party pursuant to S.C. Code Ann. section 29-5-10(b) (Supp. 2012). Petitioners challenged the arbitration award, contending the arbitrator's denial of their motion to dismiss amounted to a manifest disregard of the law. Following adverse decisions in the circuit court and the court of appeals, the Supreme Court granted a writ of certiorari. Petitioners argue the court of appeals erred in refusing to find the arbitrator manifestly disregarded the law in declining to dismiss the action. Upon review, the Court agreed, and reversed the appellate court and directed that judgment be entered for Petitioners. View "C-Sculptures v. Brown" on Justia Law

by
A construction company and its principals (collectively, Appellants) hired a plumbing company (Peters), excavation company (Bostic), and marble company (Esquire) as subcontractors for the construction of Appellants' home. After Buyers purchased the home, Buyers filed a complaint against Appellants, alleging negligence and breach of the implied warranties of habitability, sound workmanship, and proper construction. Appellants filed a third-party complaint against Peters, Bostic, and Esquire, alleging several causes of action. Bostic subsequently filed cross-claims against Peters, and Peters filed cross-claims against both Bostic and Esquire. Thereafter, the circuit court (1) granted Peters' motion for summary judgment on the third-party complaint, (2) granted summary judgment for Bostic on Peters' cross-claim, and (3) granted Esquire's motion for summary judgment on the third-party complaint. Appellants appealed. The Supreme Court dismissed the appeal, holding that the Court lacked jurisdiction because a final order had not been entered disposing of all the claims. View "J-McDaniel Constr. Co. v. Dale E. Peters Plumbing Ltd." on Justia Law

by
This case arose out of several business transactions entered into by parties involved in the development of condominiums on Hauser Lake. Cherrad, Merritt & Marie, and Max & V (the Hale interests) were limited liability companies owned by Conrad and Cheryl Hale. Craig Kinnaman was sole proprietor of a business called CK Design. Merritt & Marie purchased the Hauser Lake property. Subsequently, the Hales and Kinnaman agreed to develop a portion of the property. Cherrad was the developer, and Mountain West Bank (MWB) made three loans to Cherrad to develop the project. CK Design suffered delays in the project and later left the project. In 2007, Kinnaman committed suicide, and the Estate recorded a $3.3 million construction lien on the condominiums. MWB brought this action 2008 against the Hale interests and the Estate seeking foreclosure on the three secured loans. The Hale interests and the Estate cross-claimed against each other. The district court (1) declared the Estate's construction lien invalid; and (2) determined Cherrad owed the Estate $76,278 for work that CK Design performed on the project. Finding no error, the Supreme Court affirmed. View "Mountain West Bank, N.A. v. Cherrad, LLC" on Justia Law