Articles Posted in Construction Law
by
Tharaldson Ethanol Plant I, LLC and Tharaldson Financial Group, Inc. appealed a judgment and amended judgment ordering Tharaldson Financial to pay VEI Global, Inc., $1,150,000 plus interest, and an order granting certification under N.D.R.Civ.P. 54(b). VEI provided design and construction management services for an ethanol plant owned and operated by Tharaldson Ethanol. In 2009, Tharaldson Ethanol and VEI reached a settlement on disputed fees, agreeing Tharaldson Ethanol would pay VEI $1,350,000 for all work VEI performed through February 28, 2009. The agreement also provided Tharaldson Financial would enter into a $1,350,000 promissory note payable to VEI, and a copy of the note was attached and incorporated into the agreement. Tharaldson Ethanol and Tharaldson Financial sued VEI, claiming VEI negligently designed and constructed the ethanol plant. The complaint sought damages for breach of warranty, breach of contract, and negligence claims; and sought a declaratory judgment that Tharaldson Ethanol and Tharaldson Financial did not owe VEI anything under the settlement agreement or promissory note because of damages VEI caused by its breaches of contract and warranty and other wrongful acts. VEI answered and counterclaimed, including a breach of contract claim against Tharaldson Financial for failing to make payments on the promissory note. The district court ultimately granted VEI's motion for partial summary judgment, finding there were no genuine issues of material fact and VEI was entitled to judgment as a matter of law, and ordered VEI was entitled to judgment against Tharaldson Financial in the amount of $1,150,000, with interest. The Supreme Court dismissed Tharaldson Ethanol and Tharaldson Financial's appeal, holding that "[c]ertification under N.D.R.Civ.P. 54(b) must be reserved for 'the unusual case in which the costs and risks of multiplying the number of proceedings and of overcrowding the appellate docket are outbalanced by pressing needs of the litigants for an early and separate judgment as to some claims or parties.'" The Court concluded this case did not present "out-of-the-ordinary circumstances" or the "infrequent harsh case" warranting its immediate review. Consequently, the Court did not reach the merits of Tharaldson Ethanol and Tharaldson Financial's appeal. View "Tharaldson Ethanol Plant I, LLC v. VEI Global, Inc." on Justia Law

by
Technica, a subcontractor on a federal construction project in California, filed suit under the Miller Act, 40 U.S.C. 3131-3134, against Candelaria, the prime contractor, and its surety CCIC. On appeal, Technica challenged the district court's grant of summary judgment in favor of defendants. The Supreme Court and the Eighth and Tenth Circuits have held that rights and remedies under the Miller Act may not be conditioned by state laws. The court applied their reasoning and held that the limitation in California Business and Professions Code 7031(a) on the right of a non-licensed contractor to maintain an action for collection of unpaid services did not apply to an action under the Miller Act. Because the California licensing requirement is not a defense to a claim under the Miller Act, the court need not address whether Technica falls within the labor provider exception to the statute. Accordingly, the court reversed the judgment of the district court and remanded. View "Technica LLC v. Carolina Cas. Ins. Co." on Justia Law

by
Consumers Energy entered into a Purchase Order, under which DynaSteel, operating in Tennessee and Mississippi, would fabricate ductwork for shipment to an Essexville, Michigan power plant for installation by a third party. The PO contained a Michigan choice-of-law provision. Consumers was to pay $10,634,755. PCI, with locations in Kansas and Tennessee, was to supply the insulation requested by Consumers for $1,842,890. The contract between DynaSteel and PCI contained a Tennessee choice-of-law provision. As the project progressed, Consumers paid DynaSteel $2.9 million, but DynaSteel did not pay PCI $1,542,890 it owed. DynaSteel also owed PCI more than $3.2 million for other projects. DynaSteel allegedly comingled Consumer’s payments with funds from other projects. Under a “Payment Plan Proposal,” DynaSteel was to make payments, which would apply to the unpaid orders in chronological order (the Consumers project came last in this order). The PPP did not contain a choice-of-law provision. DynaSteel paid PCI $2.1 million, which satisfied its obligations concerning the other projects, but did not fulfill its obligation as to the Consumers project. PCI sued in Michigan, alleging that DynaSteel violated the Michigan Builders Trust Fund Act. The district court entered summary judgment for Dynasteel, reasoning that the PO between PCI and DynaSteel was controlling, that the Tennessee choice-of-law provision was binding, and that the Trust Fund Act did not apply extraterritorially by its own force. The Sixth Circuit affirmed. View "Performance Contracting Inc. v. Dynasteel Corp." on Justia Law

by
Defendant general contractor Super One, Inc., and various subcontractors, including defendant subcontractor T. T. & L. Sheet Metal, Inc., contracted with VIP's Industries, Inc. and VIP's Motor Inns, Inc. (VIP's) to build a hotel. Defendants began work in 1996. In early 1997, VIP's posted a "completion notice" pursuant to ORS 87.045. On or about that same date, VIP's also obtained a certificate for temporary occupancy and began accepting paying guests. However, a Certificate of Substantial Completion was not issued by the architect or accepted by VIP's as had been contemplated by the contract between the parties. After the date on which VIP's posted the completion notice, defendants continued to perform construction work. The county issued a certificate of final occupancy later that year. In 2006, plaintiff purchased the hotel and soon thereafter allegedly discovered damage. Plaintiff filed an action against defendants for negligence, nuisance, and trespass in 2007, a date more than 10 years after the posting of the completion notice but less than 10 years after the issuance of the certificate of final occupancy. Defendants moved for summary judgment, arguing that plaintiff's claims were barred by ORS 12.135. The issue this case presented to the Supreme Court was the meaning of the term "substantial completion" as used in ORS 12.135. The Court affirmed the decision of the Court of Appeals, and remanded the case to the circuit court for further proceedings. View "PIH Beaverton, LLC v. Super One, Inc." on Justia Law

by
Plaintiff Sunset Presbyterian Church contracted with defendant Brockamp & Jaeger to act as its general contractor and build a new church facility. Defendant then subcontracted with Anderson Roofing Company and other subcontractors to perform various specialized construction tasks. Plaintiff did not enter into a contractual relationship with any of the subcontractors. In early 2009, plaintiff allegedly discovered extensive water damage in the church, and filed an action asserting tort claims against defendants. Defendant general contractor filed an affirmative defense alleging that, by the terms of the parties' contract, plaintiff's claims accrued on the "date of substantial completion" and were time-barred. A defendant-subcontractor, which was not a party to that contract, filed an affirmative defense alleging that plaintiff's claims were barred by the statute of ultimate repose. Both defendants moved for summary judgment. The trial court granted their motions and dismissed the case. The Court of Appeals reversed. Defendants then petitioned for review. The Supreme Court concluded that defendants were not entitled to summary judgment, affirmed the decision of the Court of Appeals, reversed the decision of the trial court, and remanded the case to the trial court for further proceedings. View "Sunset Presbyterian Church v. Brockamp & Jaeger" on Justia Law

by
Guardian Builders, LLC, and E. Wayne Tackett appealed a Circuit Court order denying their motion to vacate or modify an arbitration award entered in favor of Randy Uselton and his wife Melissa. In 2010, the Useltons sued Guardian alleging several claims arising from Guardian's construction of a house for the Useltons. Guardian subsequently filed a motion to compel arbitration, and the circuit court granted that motion. In late 2011, the arbitrator entered a final award in favor of the Useltons. Guardian subsequently filed a motion to vacate or modify the arbitration award to the circuit court, to which it attached a copy of the arbitration award. The Useltons filed a 'motion to confirm' the arbitration award. The circuit court entered an order purporting to deny Guardian's motion to vacate or modify the arbitration award, purporting to grant the Useltons' motion to confirm the arbitration award, and purporting to order Guardian to pay $1,421.75 in Better Business Bureau fees and facility costs related to the arbitration. Guardian objected only to a subset of the damages that were awarded the Useltons that were not directly related to the poorly constructed house, specifically, attorney fees and arbitration fees (including both the arbitrator fee and the forum fee charged by the Better Business Bureau of North Alabama ("the BBB"), which administered the arbitration). Furthermore, Guardian argued the arbitrator lacked the authority to award the Useltons attorney fees and arbitration fees. The Supreme Court agreed that the arbitrator exceeded his authority by awarding those remedies. The trial court's judgment was reversed and the case remanded for the trial court to enter a modified judgment subtracting attorney fees and arbitration fees from the award made to the Useltons. View "Guardian Builders, LLC v. Uselton " on Justia Law

by
The Minnesota Laborers Health and Welfare Fund (“the Funds”) filed a declaratory judgment action against Granite Re, Inc. seeking clarification of their right to payment on a surety bond. The district court granted summary judgment to Granite Re, concluding, among other things, that the Funds’ lawsuit was time-barred because the Funds failed to commence litigation within the one-year contractual limitations period set out in the bond. The court of appeals reversed and remanded, concluding that fraudulent concealment by the bond principal tolled the limitations period set out in the bond. The Supreme Court affirmed, holding (1) fraudulent concealment can be applied to a surety that was not involved in the fraudulent concealment by the principal; and (2) therefore, the one-year contractual limitations period set out in the bond may be tolled against Granite Re. View "Minn. Laborers Health & Welfare Fund v. Granite Re, Inc." on Justia Law

by
Appellant Charles DeGroot and DeGroot Farms, LLC appealed the district court's grant of summary judgment on its claims against Standley Trenching, Inc. d/b/a Standley & Co., relating to the construction and installation of a manure handling system at the DeGroot dairy. Beltman Construction, Inc., d/b/a Beltman Weldling and Construction, was the general contractor for the project. Beltman subcontracted with Standley for the installation of the manure handling equipment. J. Houle & Fils, Inc. manufactured the manure handling equipment installed at the DeGroot dairy. Because of maintenance problems with the manure handling equipment, DeGroot initiated litigation against Standley and Houle. DeGroot then initiated litigation against Beltman. Beltman brought a third party complaint against Standley. Standley counterclaimed against DeGroot for amounts due for parts and services. The district court granted Standley summary judgment on its counterclaim, granted Standley summary judgment on DeGroot's claims, and granted Standley summary judgment on Beltman's third party complaint. DeGroot appealed. Finding no reversible error, the Supreme Court affirmed. View "DeGroot v. Standley Trenching, Inc." on Justia Law

by
The developer (“Developer”) of a residential community hired a general contractor (“Contractor”) to construct homes in the community, and Contractor subcontracted with Subcontractor for construction services. Subcontractor performed services on several homes, including Appellant’s. Because Subcontractor was not fully paid, it recorded liens on properties within the community, including Appellant’s. Subcontractor filed a civil action against Developer, Contractor, Appellant, and other homeowners, seeking to foreclose on its liens. Appellant filed a cross-claim against Developer and Contractor for breach of contract and seeking to recover attorney fees as damages. The district court denied Appellant’s request to recover attorney fees, concluding that, under the standard set forth in Horgan v. Felton regarding the recovery of attorney fees in cloud-on-title cases, because the breach of contract in this case related to title of real property, and because Appellant failed to allege and prove slander of title, she could not recover the attorney fees that she sought as special damages. The Supreme Court reversed the district court’s judgment to the extent that it denied Appellant’s request for special damages, holding that Horgan did not apply to preclude such recovery in this case. View "Liu v. Christopher Homes, LLC" on Justia Law

by
At issue in this case was the State Center Project, a $1.5 billion redevelopment project intended to revitalize property owned by the State in Baltimore. In 2005, the State issued a public request for qualifications to solicit a master developer for the project. The State Center, LLC was chosen as the master developer. The Maryland Department of General Services (“DGS”), the Maryland Department of Transportation (“MDOT”) and the State Center, LLC negotiated for the Project, entering a series of agreements between 2007 and 2010 to complete the Project in a timely manner. In 2010, Plaintiffs, property owners in downtown Baltimore and taxpayers, filed suit against the DGS, MDOT, and the State Center and its subsidiaries, seeking a declaratory judgment that the formative contracts for the Project were void and seeking an injunction to halt the Project. The trial court voided the formative contracts, concluding that they violated the State Procurement Law. The Court of Appeals vacated the judgment of the circuit court and remanded with directions to dismiss Plaintiffs’ complaint with prejudice, holding that Plaintiffs’ claims were barred by the doctrine of laches due to an unreasonable delay in bringing their claims, causing prejudice to the defendants. View "State Ctr., LLC v. Lexington Charles Ltd. P'ship" on Justia Law