Justia Contracts Opinion Summaries
Articles Posted in Construction Law
Golden State v. Eastern Municipal Water Dist.
The Eastern Municipal Water District (EMWD) hired general contractor S.J. and Burkhardt, Inc. (SJB) for a public works construction project in 2006. Safeco Insurance Company (Safeco) executed performance and payment bonds for the project. Plaintiff Golden State Boring & Pipe Jacking, Inc. (GSB) was a subcontractor for the project, completing its work by September 2006, but it did not receive payment. In March 2008, SJB sent a voluntary default letter to Safeco. In July 2008, GSB sued SJB, EMWD, and Safeco for the unpaid amounts under the contract, separately seeking payment from Safeco under its payment bond. EMWD filed a cross-complaint to interplead retained sums. Safeco made a motion for summary judgment on the cause of action for payment under the bond on the ground that GSB’s claim was untimely. The trial court granted the motion, finding that there had been three cessations of labor that triggered GSB’s duty to file a stop notice in order to secure payment under Safeco's payment bond. At a subsequent court trial on the contract claims, GSB was awarded judgment against SJB, and Safeco was awarded judgment on the interpleader action. GSB appealed the summary judgment ruling, arguing: (1) the trial court erroneously overruled its objections to evidentiary matters presented in support of Safeco’s summary judgment; and (2) the court erred in finding the action was untimely. Finding no reversible error, the Court of Appeal affirmed.
View "Golden State v. Eastern Municipal Water Dist." on Justia Law
Shafer Electric & Construction v. Mantia
In August, 2010, Appellants, Washington County residents Raymond and Donna Mantia, hired Appellee, West Virginia contractor Shafer Electric & Construction, to build a 34 foot by 24 foot, two-car garage addition onto their house. The proposals for the garage did not comply with several requirements of Section 517.7 of the Home Improvement Consumer Protection Act. Specifically, any home improvement contract, in order to be valid and enforceable against the owner of real property, had to be legible, in writing, and contain thirteen other specific requirements. Despite the detail in the specifications for the work to be completed, the contract here only complied with subsections (5), (7), and (8) of Section 517.7(a). Notwithstanding these deficiencies, work on the project began in October, 2010, when Appellants, who owned their own excavation business, began the foundation excavation. When Appellee commenced construction of the addition, it contended that problems surfaced because of Appellants' failure to complete the excavation work properly. During the subsequent months, Appellants eventually reexcavated the foundation area for the addition and, in the process (according to Appellee), changed the design of the addition several times. Negotiations into these design changes and other necessary alterations as a result of the excavation problems occurred, but ultimately failed when Appellants apparently refused to enter into a new contract with Appellee. Upon the breakdown of the negotiations, the parties mutually agreed that Appellee would invoice Appellants for the work completed, and that Appellee would discontinue efforts on the project. Appellants refused to pay the bill. Appellee responded by filing a mechanic's lien in the Washington County Court of Common Pleas. When Appellants still had failed to satisfy the outstanding balance, Appellee filed a civil action in the common pleas court, alleging both breach of contract and quantum meruit causes of action. The Supreme Court granted allowance of appeal in this matter to determine whether the Act barred a contractor from recovery under a theory of quantum meruit in the absence of a valid and enforceable home improvement contract as defined by the Act. The Superior Court held that the Act did not bar a cause of action sounding in quantum meruit and, for slightly different reasons, the Supreme Court affirmed.
View "Shafer Electric & Construction v. Mantia" on Justia Law
Transtar Elec., Inc. v. A.E.M. Elec. Servs. Corp.
A.E.M. Electric Services Corporation, a general contractor, contracted with Transtar Electric, Inc., a subcontractor, to provide electrical services for the installation of a pool at Holiday Inn. A.E.M. did not pay Transtar for its last three invoices because the owner of the project had failed to pay A.E.M. for the work performed by Transtar. A.E.M. alleged that the contract between the parties, which used the phrase “receipt of payment by contractor from the owner for work performed by subcontractor is a condition precedent to payment by contractor to subcontractor for that work”, was sufficient to establish a pay-if-paid payment provision. The court of appeals concluded that the payment provision in the contract was not specific enough to show that both parties understood and agreed that the risk of the owner’s nonpayment would be borne by Transtar instead of A.E.M. The Supreme Court reversed, holding that the use of the term “condition precedent” was an explicit statement of the parties’ intent to transfer the risk of the project owner’s nonpayment from A.E.M. to Transtar. View "Transtar Elec., Inc. v. A.E.M. Elec. Servs. Corp." on Justia Law
Ferguson Fire v. Preferred Fire
This case arose out of plaintiff Ferguson Fire's efforts to obtain payment for materials it supplied to defendant Preferred Fire Protection, LLC for defendant Immedion's data center. In 2007, Immedion, a telecommunications company, hired Rescom, L.L.C. to be the general contractor for improvements planned for its data center on property Immedion leased in Greenville. Rescom, in turn, hired Preferred Fire, a fire sprinkler company, as a subcontractor. In addition, Immedion directly hired Preferred Fire under a separate contract to install a special "pre-action" fire suppression system1 in its data center. To complete this work, Preferred Fire purchased materials from Ferguson Fire. Ferguson Fire began delivering materials to Preferred Fire in August, 2007, and the deliveries continued through October. In September, while its deliveries were in progress, Ferguson Fire sent a "Notice of Furnishing Labor and Materials" to Immedion advising it in relevant part that it had been employed by Preferred Fire to deliver labor, services, or materials with an estimated value of $15,000.00 to Immedion's premises. The Notice of Furnishing advised that it was being given as "a routine procedure to comply with certain state requirements that may exist," and that it was not a lien, nor any reflection on Preferred Fire's credit standing. Immedion paid Preferred approximately half of the contract price for installation of the system before receiving Ferguson Fire's Notice of Furnishing. After receiving the Notice, Immedion issued two additional checks to Preferred Fire for the unpaid balance of the contract price. Immedion paid everything it owed to Rescom, and it also paid its contractor Preferred Fire in full under the separate contract for the fire suppression system. However, Preferred Fire never paid Ferguson Fire for the materials it furnished. Ferguson brought a mechanic's lien foreclosure action against Immedion and Preferred Fire. Ferguson Fire contended (and the Supreme Court agreed) that the Court of Appeals erred in adding requirements to S.C Code Ann. 29-5-40 (2007) (governing a notice of furnishing) that were not in the statute itself and in concluding Ferguson Fire did not establish an effective lien upon which a foreclosure action could be premised. The Supreme Court reversed and remanded for further proceedings.
View "Ferguson Fire v. Preferred Fire" on Justia Law
C&C Plumbing and Heating, LLP v. Williams County
American General Contractors, Inc. ("AGC"), appealed a judgment assessing liability and awarding damages and interest for the cost of delays in the construction of the Williams County Law Enforcement Center in Williston. C&C Plumbing and Heating, LLP ("C&C"), the successful bidder for the mechanical prime contract, filed suit when construction the center was delayed approximately two years after "substantial completion" was supposed to have happened. The district court concluded it was appropriate for the County and AGC to share responsibility for providing temporary shelter and heat on the project. The court apportioned 47 percent of the liability for the costs of the delay for the three and one-half months of active interference to the County and 53 percent to AGC, for the four months delay inherent to the industry. The court awarded C&C approximately $73,000 on its claim against the County. After offsetting amounts owed between the parties, the court awarded AGC approximately $424,000 on its claim against the County. The court awarded Davis Masonry approximately $96,000 from AGC for masonry work completed under its subcontract with AGC, and rejected AGC's claimed offsets to that amount. Davis had provided heat, cover and shelter for the project during cold weather and sought $649,000 from the County and AGC for that expense including prompt payment interest. Davis had settled with the County for $530,000, and the court ruled AGC was responsible for 53 percent of the remaining $119,000, or $63,070. AGC argues the district court erred in determining AGC was liable for any of the costs incurred from the delay under its contract with the County. Finding no reversible error, the Supreme Court affirmed the district court.
View "C&C Plumbing and Heating, LLP v. Williams County" on Justia Law
MMS Construction & Paving v. Head, Inc., et al
MMS Construction & Paving, L.L.C. entered into a subcontract with Head, Inc. to pave asphalt runway shoulders at Altus Air Force Base in Oklahoma. The project was delayed and MMS, expressing concern that Head had not been making agreed payments, quit the job. MMS also complained that completing the job would be more expensive than it originally believed because certain requirements were being imposed that Head said would be waived. After MMS quit, Head finished the job, relying on other subcontractors. MMS sued Head on state-law claims of breach of contract, tortious breach of contract, quantum meruit, and misrepresentation, and brought a claim under the federal Miller Act on Head’s surety bond for the project. Head filed a counterclaim, alleging that MMS breached the contract. After a jury trial, MMS was awarded damages and attorney fees. Head filed a motion for judgment as a matter of law or for a new trial, both of which the district court denied. Head appealed, arguing: (1) the evidence at trial was insufficient to show that Head breached the contract; (2) if there was a breach, it was not material; (3) an Oklahoma statute limited MMS’s breach-of-contract damages to the amount unpaid plus interest; (4) the evidence was not sufficient to establish MMS’s alleged lost-profits damages for breach of contract; (5) MMS did not present sufficient evidence to prove misrepresentation or any damages from misrepresentation, MMS waived the misrepresentation claim, and the award of misrepresentation damages duplicated the award of damages for breach of contract; and (6) MMS was not entitled to attorney fees from Head because the Miller Act does not allow recovery of those fees. Upon careful consideration of the district court record, the Tenth Circuit reversed damages award based on the misrepresentation claim because the jury’s award was not supported by any evidence at trial. On all other issues, the Court affirmed.
View "MMS Construction & Paving v. Head, Inc., et al" on Justia Law
Stern Oil Co. v. Border States Paving, Inc.
Border States Paving Company, Inc. was the prime contractor on a South Dakota Department of Transportation road construction project. Weatherton Contracting Company, Inc. entered into a subcontract with Border States to supply crushed aggregate for the project. Stern Oil Company sold Weatherton fuel and petroleum products necessary for Weatherton to perform its subcontract, but Weatherton failed to pay Stern Oil for the products. Stern Oil Company brought suit against Border States and its surety, Liberty Mutual Insurance Company, pleading causes of action against Border States for unjust enrichment and breach of an alleged third-party beneficiary payment agreement to pay the bill and against Liberty Mutual for payment on the bond. The circuit court granted summary judgment against Stern Oil on all claims. The Supreme court affirmed, holding that the circuit court did not err in granting summary judgment against Stern Oil on its claims. View "Stern Oil Co. v. Border States Paving, Inc." on Justia Law
Miller-Davis Co. v. Ahrens Construction, Inc.
Miller-Davis Company was an "at risk" contractor for the Sherman Lake YMCA's natatorium project. Miller-Davis hired defendant Ahrens Construction, Inc., as a subcontractor to install similar roof systems on three rooms, including the natatorium. After nearly a decade of litigation and alternative dispute resolution proceedings, the indemnification contract underlying the troubled natatorium roof in this case was brought before the Supreme Court. The Court previously held that the six-year period of limitations of MCL 600.5807(8) applied to the parties’ indemnification contract. Upon further review, the Court held that the indemnity clauses in the parties’ subcontract applied here, because the plain language of the indemnification clauses extended to Ahrens’s failure to undertake corrective work as obligated by the subcontract. Furthermore, because the Sherman Lake YMCA made a "claim" upon Miller-Davis which triggered Ahrens’s liability under the indemnity clauses, Ahrens’ failure to indemnify caused the damages Miller-Davis sustained in undertaking the corrective work itself. Finally, the Court held that Miller-Davis’ claim was not barred by the six-year statute of limitations found in MCL 600.5807(8). Rather, Miller-Davis’ breach of contract claim for Ahrens’s failure to indemnify is distinct from its breach of contract claim based on Ahrens’s failure to install the roof according to specifications, and Miller-Davis’s indemnity action necessarily accrued at a later point. The Court reversed that portion of the Court of Appeals’ opinion discussing Miller-Davis’s indemnity claim, and remanded this case to the Circuit Court for entry of judgment in Miller-Davis’s favor and to determine whether Miller-Davis is entitled to attorney’s fees under the relevant indemnification clauses.
View "Miller-Davis Co. v. Ahrens Construction, Inc." on Justia Law
Johnson Controls, Inc. v. Liberty Mutual Insurance Company
This case arose from a contract between Roanoke Healthcare Authority (doing business as Randolph Medical Center) and Batson-Cook Company, a general contractor, to renovate the medical center, located in Roanoke. Batson-Cook received written notice from Roanoke Healthcare that work on the renovation project had been suspended. Batson-Cook notified one of its subcontractors, Hardy, of the suspension and stated that "[t]he contract has been suspended by [Roanoke Healthcare] through no fault of Batson-Cook ... or its subcontractors. [Roanoke Healthcare] is currently out of funding and has subsequently closed the facility while seeking a buyer." Liberty Mutual, the project's insurer, alleged in its answer that Roanoke Healthcare failed to pay Batson-Cook $241,940.51 for work performed pursuant to the contract. Batson-Cook sent Hardy a change order the change order deducted from the subcontract the $147,000 in equipment and materials another subcontractor Hardy hired, Johnson Controls, Inc. (JCI), had furnished for the renovation project and for which it has not received payment. JCI notified Liberty Mutual, Roanoke Healthcare, Batson-Cook, and Hardy by certified letters of its claim on a payment bond. The letters identified Batson-Cook as the general contractor and Hardy as the debtor. Liberty Mutual denied the claim. JCI sued Liberty Mutual, alleging JCI was entitled to payment on the payment bond Liberty Mutual had issued to Batson-Cook. Upon review, the Supreme Court concluded JCI was a proper claimant on the payment bond. Therefore, the circuit court erred in entering a summary judgment in favor of Liberty Mutual and denying JCI's summary judgment motion. View "Johnson Controls, Inc. v. Liberty Mutual Insurance Company " on Justia Law
Hanover Ins. Co. v. Northern Bldg. Co.
Northern, operated by VanDuinen, was a general contractor on public construction projects, legally required to obtain surety bonds. Hanover was Northern’s bonding agent and required Northern to enter into an Indemnity Agreement, which VanDuinen signed in his individual capacity and as Northern’s President. The Midway Airport Project was financed by the FAA and managed by Parsons. In 2008 Northern won the bid and began subcontracting. in 2009 subcontractors complained that Northern failed to pay them in accordance with the bonds and contracts. Work was halted, resulting in a separate complaint, by Parsons, for failure to complete the Project as required. The FAA opted to retain possession of remaining contract funds, $127,086.00, pending resolution of the disputes and completion of the work. Hanover received claims from subcontractors McDaniel ($127,452.78) and Rex Electric ($78,495.00) and a claim for performance from Parsons. Hanover demanded collateral under the Agreement. Northern refused to post collateral or to indemnify Hanover. In 2009 McDaniel filed for bankruptcy; the bankruptcy trustee sued Hanover seeking payment for work performed. In 2012, Hanover paid the trustee $127,452.78 to resolve both McDaniels’s and Rex Electric’s claims. Hanover resolved Parson’s claim by stepping in as general contractor and arranging for completion of the Project. Parsons paid Hanover the $127,086.00 of contract funds the FAA had withheld. Hanover sued Northern and VanDuinen. The district court granted summary judgment in Hanover’s favor. The Seventh Circuit affirmed. The Agreement is unambiguous. Northern breached it, and Hanover is entitled to contractual damages. View "Hanover Ins. Co. v. Northern Bldg. Co." on Justia Law