Justia Contracts Opinion Summaries
Articles Posted in Construction Law
J.D. Donovan, Inc. v. Minn. Dep’t of Transp.
At issue in this case was whether truck drivers hauling asphalt cement from a commercial oil refinery to a contractor’s facility are performing “work under a contract” under Minn. Stat. 177.44(1) and, therefore, must be paid prevailing wages. The Minnesota Department of Transportation (MDOT) determined that the construction companies that were awarded contracts to work on state highway projects violated the project contracts by failing to ensure that drivers that assisted in the acquisition and transport of asphalt cement for the projects were paid prevailing wages. Appellants argued that the hauling activities of these drivers did not constitute “work under a contract” under Minn. Stat. 177.44(1) and, alternatively, that the hauling activities were exempt from the prevailing wage requirements under the “commercial establishment exception” in the Prevailing Wage Act. The district courts granted summary judgment to MDOT. The court of appeals affirmed. The Supreme Court reversed, holding that hauling activities must be to, from, or on the site of a public works project to qualify as “work under a contract,” and therefore, the hauling activities in this case did not constitute “work under the contract” subject to the prevailing wage requirements. View "J.D. Donovan, Inc. v. Minn. Dep’t of Transp." on Justia Law
LTL Acres Limited Partnership v. Butler Manufacturing Co.
This litigation arose from the construction of a "Johnny Janosik" furniture store in Laurel. The Plaintiff-appellant LTL Acres Limited Partnership (LTL) was the owner of the Janosik Building. Defendant-appellee Butler Manufacturing Company (Butler) provided pre-engineered components which were used to build the roof and exterior walls. Defendant-appellee Dryvit Systems, Inc. (Dryvit) supplied a product used on the exterior finish of the walls, to protect and seal them. Dryvit warranted its product for ten years from the "date of substantial completion of the project." The building was completed in 2006. Unfortunately, the building had issues with water infiltration from the beginning. By February 2012, cladding began to crack and buckle. The water infiltration and delamination persisted through 2013 despite attempts to fix the issues. LTL brought this action in 2013, alleging breach of warranty, breach of contract, and negligence claims against Butler; and breach of warranty and breach of contract claims against Dryvit. The Superior Court granted summary judgment to both Butler and Dryvit on the grounds that the actions against both were barred by the applicable statute of limitations. It held that the action against Butler was barred by 10 Del. C. sec. 8127,which is a six year statute of limitations relating to alleged defective construction of an improvement to real property. After review, the Supreme Court concluded that summary judgment in favor of Butler was proper. The Superior Court ruled that LTL’s action against Dryvit was barred by a four year statute of limitations set forth in 6 Del. C. sec. 2-725. Dryvit gave LTL a ten year express warranty. The Superior Court described the warranty as a “repair and replacement warranty” and reasoned that such a warranty cannot be one that extended to future performance. It therefore concluded that the statute of limitations for an action on the warranty expired not later than four years after the Dryvit product was tendered and applied to the building; that is, not later than four years after 2006. The Supreme Court concluded that grant of summary judgment in favor of Dryvit was inappropriate, and had to be reversed. The case was remanded for further proceedings. View "LTL Acres Limited Partnership v. Butler Manufacturing Co." on Justia Law
Blois Construction v. FCI/Fluor/Parsons
Pursuant to Public Contract Code section 7107, when a project owner pays a direct contractor the amount it had previously withheld as retentions, the direct contractor must pay its subcontractors their share of the retention within seven days or face penalties. The court concluded that, in this case, the decision by the owner to stop withholding future retentions and pay full progress payments to the contractor was not equivalent to a payment by the owner of past retentions under section 7107. Accordingly, the court concluded that the subcontractor is not entitled to late payment penalties under section 7107. The court affirmed the trial court's judgment. View "Blois Construction v. FCI/Fluor/Parsons" on Justia Law
Welch Construction & Excavating, LLC v. Duong
Linh Duc Duong, doing business as Classy Nails, appealed after a bench trial awarded Welch Construction & Excavating, LLC, $30,825, plus interest, for the balance due on a construction contract. Welch Construction sued Duong, alleging the parties contracted for Welch Construction to remodel a vacant retail space in Kirkwood Mall into a Classy Nails salon for $92,225. Welch Construction alleged it completed the work and Duong failed to pay the balance of $30,825 due under the contract. Duong answered and counterclaimed, denying he owed an outstanding balance under the contract and alleging Welch Construction breached the contract by failing to remodel the retail space in a timely and workmanlike manner according to his specifications. Duong claimed he was entitled to a setoff against any balance owed under the contract for his damages caused by Welch Construction's failure to complete the work before Thanksgiving 2013 and failure to construct the salon according to his specifications. Duong sought lost profits and damages for repairing the work according to his specifications. After review, the Supreme Court concluded the district court did not clearly err in finding: (1) the parties did not orally contract for a specific completion date for the construction project; (2) Welch Construction did not unreasonably delay completion of the project; and (3) Duong failed to establish his damages for costs to repair and lost profits for Welch Construction's claimed failure to complete the project according to his specifications. View "Welch Construction & Excavating, LLC v. Duong" on Justia Law
Tom v. Innovative Home Sys.
Respondent, a contractor, and Appellant, a homeowner, entered into a contract under which Respondent agreed to install automation, sound, surveillance, and landscaping systems in Appellant’s residence. Respondent did not have an electrical contractor’s license when it bid the contract and began the work but did receive a license before it completed the work. When the parties disagreed on the performance of the contract, Appellant refused to tender further payment to Respondent, and Respondent filed a notice of lien against Appellant’s residence. Respondent filed a complaint alleging breach of contract, breach of the covenant of good faith and fair dealing, foreclosure of notice of lien, and declaratory relief, alleging that an electrical license was not required for the work performed on Appellant’s residence and that its lien was proper and perfected. The district court granted summary judgment in favor of Respondent. The Supreme Court reversed, holding that genuine issues of material fact existed regarding whether Respondent’s work on Appellant’s residence required a license and whether Respondent completed the contract in a workmanlike manner, thereby possibly negating Appellant’s obligation to make final payment under the contract. Remanded. View "Tom v. Innovative Home Sys." on Justia Law
Hoover General Contractors – Homewood, Inc. v. Key
Hoover General Contractors – Homewood, Inc. ("HGCH"), appealed a circuit court order denying its motion to compel arbitration of its dispute with Gary Key regarding work performed by HGCH on Key's house in Jasper after that house was damaged by a fire. Six months after Key sued HGCH asserting claims stemming from HGCH's work rebuilding Key's house after a fire, HGCH moved the trial court to compel Key to arbitrate those claims pursuant to an arbitration clause in the contract Key had entered into with HGCH. The trial court denied HGCH's motion to compel; however, that denial was error because Key failed to establish through substantial evidence that HGCH had waived its right to arbitration by substantially invoking the litigation process. Accordingly, the order entered by the trial court denying HGCH's motion to compel arbitration was reversed by the Supreme Court and the case remanded for the trial court to enter a new order compelling Key to arbitrate his claims ursuant to the terms of his contract with HGCH. View "Hoover General Contractors - Homewood, Inc. v. Key" on Justia Law
Shell v. Schollander Companies, Inc.
Defendant was a general contractor that builds “spec” houses (houses built without pre-existing construction contracts in anticipation of eventual sale to the public). On May 30, 2000, defendant and plaintiff entered into a purchase and sale agreement for a house. Although most of the construction had been completed, the agreement specified that defendant would make changes to the interior of the house. Specifically, defendant agreed to upgrade some of the flooring, install an air conditioning unit, and install a gas dryer in the laundry room. After defendant made those changes and the parties conducted a walk-through inspection, the sale closed on July 12, 2000. The primary question in this construction defect case was which of two statutes of repose applied when a buyer enters into a purchase and sale agreement to buy an existing home. Although each statute provided for a 10-year period of repose, the two periods of repose ran from different dates. One runs from “the date of the act or omission complained of;” the other ran from the date that construction is “substantial[ly] complet[e].” In this case, the trial court found that plaintiff filed her action more than 10 years after “the date of the act or omission complained of” but less than 10 years after the construction was “substantial[ly] complet[e].” The trial court ruled that the first statute, ORS 12.115(1), applied and accordingly entered judgment in defendant’s favor. The Court of Appeals affirmed. After review of the parties' arguments on appeal, the Supreme Court found no reversible error in the Court of Appeals' decision and affirmed. View "Shell v. Schollander Companies, Inc." on Justia Law
William H. Gordon Assocs. v. Heritage Fellowship, United Church of Christ
Church entered into an engineering contract with Civil Engineer (Engineer) to design site plans for a rain tank system. Church entered into a contract with General Contractor (GC) for the construction of the rain tank. After GC installed the rain tank, the tank collapsed. Engineer designed and GC installed a different storm water management system, but Church refused to pay GC for installing the new storm water system. GC sued Church for payment, and Church counterclaimed against GC for breach of contract. Church filed a third-party claim against Engineer for repair and replacement costs it was found to owe GC because of the rain tank collapse. Church filed a separate suit against Engineer. The circuit court concluded that the rain tank collapse was the failure of Engineer, entered judgment for GC on its claims against Church, and awarded Church damages for delay and other damages associated with removing and replacing the rain tank. Engineer appealed. The Supreme Court (1) affirmed the judgment of the circuit court finding Church’s claims timely and Engineer liable on Church’s breach of contract claims; and (2) reversed the circuit court’s judgment granting Church damages in the form of construction loan interest that was not incurred as a result of the breach of contract. Remanded. View "William H. Gordon Assocs. v. Heritage Fellowship, United Church of Christ" on Justia Law
Wall v. Circle C Constr., LLC
Over the course of seven years, Circle C, a contractor that built 42 warehouses at Fort Campbell Army base, paid some electricians about $9,900 less than the Davis-Bacon (40 U.S.C. 3142) wages specified in its contract with the Army. The government obtained a damages award of $763,000 under the False Claims Act, 31 U.S.C. 3729, arguing that all of the electrical work was “tainted” by the $9,900 underpayment and, therefore, worthless. The Sixth Circuit, reversed the damage award and remanded for entry of an award of $14,748. Actual damages are the difference in value between what the government bargained for and what the government received. The government bargained for the buildings and payment of Davis-Bacon wages. It got the buildings but not quite all of the wages. The shortfall was $9,916--the government’s actual damages. That amount tripled is $29,748 (31 U.S.C. 3729(a)(1)(G)). Minus a $15,000 settlement payment, Circle C is liable for a total of $14,748. View "Wall v. Circle C Constr., LLC" on Justia Law
Dannelly Enterprises, LLC v. Palm Beach Grading, Inc.
Dannelly Enterprises, LLC ("Dannelly"), appealed a circuit court order granting a motion to compel arbitration filed by Palm Beach Grading, Inc. ("PBG"). In the fall of 2006, PBG entered into negotiations with Corvias Military Living, LLC, f/k/a Picerne Military Housing LLC; Picerne Construction/FRK, LLC; Rucker-Picerne Partners, LLC; and Rucker Communities, LLC (collectively, "the contractors"), to perform work on a project known as the Ft. Rucker RCI Family Housing, Munson Heights, Phase 1A, at Fort Rucker, Alabama. Apparently, in preparing to bid on the project, PBG contacted various subcontractors, including Dannelly, to get bids for various aspects of the project that PBG would be responsible for if it entered into an agreement with the contractors to complete the project. Although the work order issued by PBG stated that "[a] Sub-contract will be created by PBG for billing purposes," neither party submitted into evidence such a contract between PBG and Dannelly. PBG argued that Donnelly accepted benefits under existing contracts because Dannelly was hired by PBG to perform work on the project and was paid for the work it completed. The Supreme Court found, however, that PBG did not present any argument as to why it believed Dannelly was not simply operating under and benefiting from the agreement between PBG and Dannelly, which was memorialized by PBG's work order. The Court concluded that PBG failed to demonstrate that the arbitration provision in the master subcontract agreement applied to the third-party claims it asserted against Dannelly. Furthermore, there was a genuine issue of material fact as to whether Dannelly and PBG entered into PBG's standard subcontract agreement. The case was reversed and remanded to the circuit court for further proceedings. View "Dannelly Enterprises, LLC v. Palm Beach Grading, Inc." on Justia Law