Justia Contracts Opinion Summaries

Articles Posted in Construction Law
by
Defendant Veterans Parkway Developers, LLC (“VPD”) appealed a Superior Court order granting injunctive relief and requiring an accounting in this suit by RMW Development Fund, II, LLC (“RMW”) stemming from VPD’s management of Veterans Parkway Apartments, LLC (the “Company”). The order at issue granted RMW an interlocutory injunction: (1) enjoining VPD from using funds in its possession or control to construct a second entrance to an apartment complex in Columbus (the “Property”), constructed and managed by the Company; (2) prohibiting VPD from using funds for any purpose other than the normal day-to-day expenses of the Property; and (3) requiring VPD to submit a monthly report of its expenses to the superior court, with copies to counsel for the parties. RMW filed suit against VPD alleging VPD’s breach of contract by its entering into an unauthorized management agreement and thereby paying an unauthorized management fee, and a claim for “promissory estoppel,” stemming from VPD’s alleged failure to use some of the Company’s funds for partial repayment of a development loan; RMW asked for VPD’s removal as manager of the Company and for the costs of litigation. Prior to the filing on the complaint, the Company had purchased a 60-foot strip of land for the purpose of creating a second entrance to the Property. At a hearing on the injunction, RMW argued that it could not undo any construction of the second entrance to the Property. VPD countered that RMW was, in reality, concerned about money being spent on the construction of the second entrance instead of being used to repay the loans made by RMW, and that any appropriate redress was monetary damages. Ultimately the injunction was granted and VPD appealed. The Supreme Court found after review of this matter that the trial court's injunction was not supported by the record, and that court abused its discretion in granting the injunction. The Supreme Court reversed the trial court and remanded this matter for further proceedings. View "Veterans Parkway Developers, LLC v. RMW Development Fund II, LLC" on Justia Law

by
The issue in this appeal centered on whether a force majeure clause in a written contract between the county and a developer did not apply to the developer’s failure to obtain zoning approval in order to construct the cement plant required in the agreement. After review of the contract and the clause at issue here, the Supreme Court held that the clause was broad enough to apply. Accordingly, the Court vacated the district court's judgment and remanded this case for further proceedings. View "Burns Concrete, Inc v. Teton County" on Justia Law

by
Kiva Lodge Condominium Owners' Association, Inc. ("Kiva Lodge") was an Alabama nonprofit corporation formed for the purpose of administering and maintaining the Kiva Dunes Clubhouse and Condominium ("Kiva Dunes") located in Gulf Shores. In 2009, Kiva Lodge contracted with Hudak & Dawson Construction Co., Inc. ("Hudak") to be the general contractor for the remediation of deficiencies in Kiva Dunes buildings that were allowing water to enter the buildings. Hudak subcontracted the stucco and/or sealant portion of the work to Don Colvin d/b/a Colvin Plastering ("Colvin"). The Hanover Insurance Company ("Hanover"), as surety for Hudak, issued to Kiva Lodge a performance bond ensuring and/or securing the full performance of Hudak's contractual obligations. In September 2012, Kiva Lodge informed Hudak and Colvin of leaks and bubbling in the stucco exterior of the buildings at Kiva Dunes caused by water intrusion. Kiva Lodge alleged that Hudak and Colvin failed to determine and/or disclose the course of the problems and the proper scope of repairs necessary. It also alleged that Hanover breached the terms of its performance bond by failing to promptly remedy the default, complete the work within the scope of the contract in accordance with the terms and conditions, or arrange for payment of an alternative contractor to complete the work. Hanover filed a motion to dismiss Kiva Lodge's claims against Hanover on the ground that, under its performance bond, its claims were time-barred, falling outside of a two-year statute of limitations. In 2015, the circuit court heard arguments concerning Kiva Lodge's motion to compel arbitration, eventually granting the stay and ordering the parties to arbitration. The court also denied Hanover's motion to dismiss. Hudak, Colvin, and Hanover timely appealed the circuit court's order. After review, the Supreme Court found no reversible error in the trial court's order and affirmed. View "Hanover Insurance Co. v. Kiva Lodge Condominium Owners' Association, Inc." on Justia Law

by
In 2014, Lend Lease, the construction manager of the Chicago River Point Tower Project, hired Cives as a subcontractor. Cives hired Midwest Steel. Midwest had, years before, hired AES to supply Midwest with additional workers, who were co‐employed by Midwest and AES. Lend Lease entered into a “contractor-controlled insurance program” with Starr Liability with a $500,000 deductible. All subcontractors were to join in the policy. AES had, several years earlier, obtained workers’ compensation for its workers from TIC, so that injured AES‐Midwest workers could obtain workers’ compensation from either Starr (or Lend Lease under the deductible) or TIC. Four ironworkers, jointly employed by Midwest and AES and performing work for Midwest were injured on the job and sought workers’ compensation. The claims exceeded $500,000, so Lend Lease had to pay its full deductible. Starr paid the remaining claims. Lend Lease filed suit against TIC, AES’s insurer, and AES, seeking reimbursement of the $500,000. The district court dismissed. The Seventh Circuit affirmed. Lend Lease made a deal with Starr and is bound by it. The court rejected an argument that AES has been unjustly enriched; AES was not obligated to purchase an insurance policy that would cover Lend Lease's deductible. View "Lend Lease (US) Construction, Inc. v. Administrative Employer Services, Inc." on Justia Law

by
In this appeal, the issue presented for the Supreme Court's review was whether a contractor could maintain an action under the Contractor and Subcontractor Payment Act (CASPA) against a property owner’s agents. Beginning in 2005, Appellant Scungio Borst & Associates (SBA) entered into a series of written and oral construction contracts with Appellee 410 Shurs Lane Developers, LLC (410 SLD), which 410 SLD’s part-owner and president, Appellee Robert DeBolt, executed on 410 SLD’s behalf. Therein, SBA agreed to improve real property owned by 410 SLD in connection with the development of a condominium complex, and did so until November 2006, when SBA’s contracts were terminated with approximately $1.5 million in outstanding payments due. SBA requested payment, but 410 SLD, again through DeBolt, refused. Accordingly, SBA sued 410 SLD; its alleged successor corporation, Appellee Kenworth II, LLC; and DeBolt in his personal capacity. SBA asserted, among other claims, violations of CASPA. After careful review, the Supreme Court held that a contractor could not maintain an action under CASPA, and, accordingly, affirmed the order of the Superior Court. View "Scungio Borst & Assoc. v. 410 Shurs Lane Developers, LLC" on Justia Law

by
Michael Mandell and Bayliss Ward and Bayliss Architects, P.C. (Bayliss) agreed that Bayliss would provide architectural and construction services for Mandell’s home. Mandell refused to pay Bayliss’s final invoice, and Bayliss filed a construction lien on the property. Mandell initiated this action stating counts of breach of contract, declaratory judgment that the lien was invalid, and quiet title to the property. Bayliss counterclaimed for foreclosure of the construction lien, quantum meruit, and breach of contract. The district court partially granted Mandell’s claim for declaratory relief, ruling that because Bayliss failed to obtain a written contract for construction services, the contract was void and the lien for those services was invalid. After a trial, the district court granted relief in quantum meruit and awarded attorney fees to Bayliss. The Supreme Court affirmed in part, reversed in part, and remanded, holding that the district court (1) did not err in granting equitable relief in quantum meruit, despite violation of the statutory requirement that residential construction contracts be in writing; and (2) erred in awarding attorney fees for the quantum meruit claim. Remanded. View "Mandell v. Bayliss Ward" on Justia Law

by
Dickinson Elks Building, LLC, appealed after the district court forfeited a construction lien filed by Rick and Janan Snider, doing business as RJ Snider Construction, and awarded the Dickinson Elks attorney's fees. In December 2011, Snider contracted with Beaver Brinkman to perform work on real property owned by the Dickinson Elks. Snider recorded a construction lien in January 2013 against the property after it did not get paid for all of its work. In May 2014, the Dickinson Elks served Snider with a demand to start a lawsuit to enforce the lien and record a lis pendens within 30 days of the demand. Snider sued the Dickinson Elks in June 2014, seeking foreclosure of the construction lien and a money judgment. Snider recorded a notice of lis pendens in July 2014. The Dickinson Elks moved for summary judgment, arguing Snider's complaint should have been dismissed because Snider was not a licensed contractor when it started the work on the property. The Dickinson Elks also argued Snider did not have a valid construction lien, because Snider did not record a lis pendens within 30 days of receiving the demand to enforce the lien. The district court granted the motion in part and entered a judgment forfeiting Snider's construction lien because Snider did not record a lis pendens within 30 days of receiving the Dickinson Elks' demand to enforce the lien. After review, the Supreme Court concluded it did not have jurisdiction and dismissed the appeal. View "Snider v. Dickinson Elks Building, LLC" on Justia Law

by
The Minnesota Department of Transportation (MnDOT) contracted with Mathy Construction Company for a public highway project. Mathy subcontracted with Storms, Inc. for excavation and fill work. After Storms completed its work, MnDOT issued a deductive change order reducing Mathy’s contract amount by $327,064 because of errors in the estimated quantities of excavation and fill required for Storms’ work. Mathy reduced Storms’ subcontract by the same amount. Storms subsequently sued Mathy for the reduction in the subcontract price. The district court granted summary judgment in favor of Storms, concluding that Mathy had breached the subcontract. The court of appeals affirmed. The Supreme Court reversed, holding that Mathy did not breach its subcontract with Storms by issuing a corresponding deductive change order to Storms. View "Storms, Inc. v. Mathy Constr. Co." on Justia Law

by
Concrete Construction (Contractor) was sued by employees of Nibbi Concrete, who were injured after a shoring system designed by Contractor collapsed. Subsequently, Contractor sued Employer for indemnification based on a specific provision in the parties’ contract. The trial court dismissed, relying on the allegations in the underlying lawsuit that set forth claims only against Contractor and not against Employer. The court of appeal reversed, stating that the allegations in the underlying lawsuit are not determinative of Contractor’s claim for indemnity. View "Aluma Systems Concrete Constr. of Cal. v. Nibbi Bros., Inc." on Justia Law

by
Pulte Homes Corporation sued Williams Mechanical, Inc. for defective performance of a plumbing subcontract. Even before the action was filed, however, Williams was defunct; first, it was suspended by the Secretary of State, and thereafter, it dissolved voluntarily. Pulte served Williams though an attorney whom Williams had designated as its agent for service of process. The attorney, however, did not notify Williams of the action; he also did not identify or notify Williams’s liability insurer. Williams failed to respond to the complaint, and Pulte obtained a default judgment. Pulte then notified Williams’s liability insurer of the default judgment. About four and a half months later, the insurer retained counsel to represent Williams, and Williams’ counsel filed a motion to set aside the default judgment. The trial court granted the motion. Pulte appealed, arguing (1) Williams lacked the capacity to defend this action because it had been suspended; and (2) Williams failed to establish that it was entitled to relief from the default and default judgment. After review, the Court of Appeal held the trial court abused its discretion by ruling that Williams was entitled to relief. Accordingly, the Court did not address whether Williams had the capacity to defend. View "Pulte Homes Corp. v. Williams Mechanical" on Justia Law