Smith v. Gebhardt
The Supreme Court reversed the order of the circuit court dismissing Petitioners’ civil action as a sanction for alleged discovery violations, holding that the circuit court abused its discretion by imposing the sanction of dismissal.Petitioners bought this civil action against Respondent alleging unfair and deceptive acts, breach of express and implied warranties, breach of contract, and other causes of action. Respondent eventually filed a second motion to dismiss the civil action as a sanction for alleged discovery violations. The circuit court identified ten instances of alleged wrongful conduct by Petitioners and granted Respondent’s motion to dismiss. The Supreme Court reversed, holding that, even assuming that there was a discovery violation, the circuit court’s imposition of the extreme sanction of dismissal was an abuse of discretion. View "Smith v. Gebhardt" on Justia Law
Dudley Construction, Ltd. v. ACT Pipe & Supply, Inc.
In this billing dispute between a general contractor, Dudley Construction, Ltd., and a pipe supplier, ACT Pipe and Supply, Inc., the Supreme Court affirmed the judgment of the court of appeals in part and reversed it in part, holding (1) in defending a favorable judgment notwithstanding the jury’s verdict, ACT successfully raised a “cross-point” in the court of appeals that preserved an alternative argument proscribing the jury’s original verdict, even though ACT did not formally label its argument a “cross-point”; and (2) attorney’s fees are not recoverable for a claim brought under the Texas Construction Trust Fund Act. The Court remanded this case to the trial court for further proceedings. View "Dudley Construction, Ltd. v. ACT Pipe & Supply, Inc." on Justia Law
Gilbane Building Co./TDX Construction Corp. v St. Paul Fire & Marine Insurance Co.
The terms of the insurance policy at issue in this coverage dispute required a written contract between the named insured and an additional insured if coverage was to be extended to an additional insured, and therefore, Liberty Insurance Underwriters was entitled to summary judgment.Gilbane Building Co. and TDX Construction Corporation (collectively, Gilbane JV) was the construction manager for a new forensic laboratory, and Samson Construction Co. was the general contractor. Samson obtained general liability insurance coverage from Liberty Insurance Underwriters. When disputes arose over the construction, Gilbane JV commerced this lawsuit arguing that it qualified for coverage under the Liberty policy as an additional insured. Gilbane JV had no written contract with Samson denominating it as an additional insured but argued that no such contract was necessary. Supreme Court denied Liberty’s motion for summary judgment, determining that Gilbane JV was an additional insured under the policy. The Appellate Division reversed and granted Liberty’s motion. The Court of Appeals affirmed based on the terms of the policy at issue. View "Gilbane Building Co./TDX Construction Corp. v St. Paul Fire & Marine Insurance Co." on Justia Law
Gilbane Building Co./TDX Construction Corp. v St. Paul Fire & Marine Insurance Co.
The terms of the insurance policy at issue in this coverage dispute required a written contract between the named insured and an additional insured if coverage was to be extended to an additional insured, and therefore, Liberty Insurance Underwriters was entitled to summary judgment.Gilbane Building Co. and TDX Construction Corporation (collectively, Gilbane JV) was the construction manager for a new forensic laboratory, and Samson Construction Co. was the general contractor. Samson obtained general liability insurance coverage from Liberty Insurance Underwriters. When disputes arose over the construction, Gilbane JV commerced this lawsuit arguing that it qualified for coverage under the Liberty policy as an additional insured. Gilbane JV had no written contract with Samson denominating it as an additional insured but argued that no such contract was necessary. Supreme Court denied Liberty’s motion for summary judgment, determining that Gilbane JV was an additional insured under the policy. The Appellate Division reversed and granted Liberty’s motion. The Court of Appeals affirmed based on the terms of the policy at issue. View "Gilbane Building Co./TDX Construction Corp. v St. Paul Fire & Marine Insurance Co." on Justia Law
Vanhook Enterprises, Inc. v. Kay & Kay Contracting, LLC
In this construction dispute, Plaintiff was not entitled to relief on its breach of contract claim or under a quantum meruit theory.Plaintiff and Defendant entered into a subcontract agreement that outlined services that Plaintiff was to perform as a subcontractor for the construction of the Bridge Street Bridge. Plaintiff later sued Defendant for breach of contract and quantum meruit in the alternative, asserting that the parties had entered into a separate agreement before the subcontract agreement and that, under that alleged agreement, Defendant was obligated to pay for additional work performed. The circuit court granted Defendant’s motion for judgment for the pleadings, concluding that the subcontract agreement was a complete integration of the dealings between the parties. The court of appeals determined that it was unclear whether the subcontract agreement was a full integration or a partial integration. Thus, the court declared that whether any additional work Plaintiff allegedly performed was covered by the subcontract agreement was an issue of fact for the jury. The Supreme Court reversed, holding (1) by its own terms, the subcontract agreement was a full integration of the parties’ contract for Plaintiff’s subcontracting work on the bridge; and (2) Plaintiff was not entitled to relief under a quantum meruit theory. View "Vanhook Enterprises, Inc. v. Kay & Kay Contracting, LLC" on Justia Law
Vanhook Enterprises, Inc. v. Kay & Kay Contracting, LLC
In this construction dispute, Plaintiff was not entitled to relief on its breach of contract claim or under a quantum meruit theory.Plaintiff and Defendant entered into a subcontract agreement that outlined services that Plaintiff was to perform as a subcontractor for the construction of the Bridge Street Bridge. Plaintiff later sued Defendant for breach of contract and quantum meruit in the alternative, asserting that the parties had entered into a separate agreement before the subcontract agreement and that, under that alleged agreement, Defendant was obligated to pay for additional work performed. The circuit court granted Defendant’s motion for judgment for the pleadings, concluding that the subcontract agreement was a complete integration of the dealings between the parties. The court of appeals determined that it was unclear whether the subcontract agreement was a full integration or a partial integration. Thus, the court declared that whether any additional work Plaintiff allegedly performed was covered by the subcontract agreement was an issue of fact for the jury. The Supreme Court reversed, holding (1) by its own terms, the subcontract agreement was a full integration of the parties’ contract for Plaintiff’s subcontracting work on the bridge; and (2) Plaintiff was not entitled to relief under a quantum meruit theory. View "Vanhook Enterprises, Inc. v. Kay & Kay Contracting, LLC" on Justia Law
Meridian Engineering Co. v. United States
Meridian contracted to construct the Chula Vista Project flood control project, including construction of concrete channels, relocation of a sewer line, and dewatering and water diversion. After commencing work, Meridian encountered problems relating to “a layer of dripping saturated dark clay material under which a clean layer of sand is producing water” with “the potential for serious structural damage.” The government issued contract modifications, including an increase in funds for larger pipe, addition of a reinforced concrete access ramp, investigation of soil properties, remediation of saturated soils, and additional sheet piling. The government directed Meridian to suspend work following structural failures and terminated the project following a final inspection. Meridian sued for breach of contract, breach of the duty of good faith and fair dealing, and violation of the Contract Disputes Act, 41 U.S.C. 601−613. The government conceded liability for certain costs relating to suspension of work, channel fill, and interim protection. With respect to other claims, the Federal Circuit affirmed in part. Meridian’s interpretation of the contract was not reasonable; the existence of subsurface saturated soil conditions was “reasonably foreseeable.” The Trade Court did not impose an improper requirement for investigation of site conditions beyond what a reasonable contractor would undertake. The court remanded for consideration of whether the parties reached a meeting of the minds on flood event claims and held that the Trade Court erred dismissing Meridian’s unpaid contract quantities claim, in light of conflicting information. View "Meridian Engineering Co. v. United States" on Justia Law
Meridian Engineering Co. v. United States
Meridian contracted to construct the Chula Vista Project flood control project, including construction of concrete channels, relocation of a sewer line, and dewatering and water diversion. After commencing work, Meridian encountered problems relating to “a layer of dripping saturated dark clay material under which a clean layer of sand is producing water” with “the potential for serious structural damage.” The government issued contract modifications, including an increase in funds for larger pipe, addition of a reinforced concrete access ramp, investigation of soil properties, remediation of saturated soils, and additional sheet piling. The government directed Meridian to suspend work following structural failures and terminated the project following a final inspection. Meridian sued for breach of contract, breach of the duty of good faith and fair dealing, and violation of the Contract Disputes Act, 41 U.S.C. 601−613. The government conceded liability for certain costs relating to suspension of work, channel fill, and interim protection. With respect to other claims, the Federal Circuit affirmed in part. Meridian’s interpretation of the contract was not reasonable; the existence of subsurface saturated soil conditions was “reasonably foreseeable.” The Trade Court did not impose an improper requirement for investigation of site conditions beyond what a reasonable contractor would undertake. The court remanded for consideration of whether the parties reached a meeting of the minds on flood event claims and held that the Trade Court erred dismissing Meridian’s unpaid contract quantities claim, in light of conflicting information. View "Meridian Engineering Co. v. United States" on Justia Law
Snider v. Dickinson Elks Building, LLC
Dickinson Elks Building, LLC, appealed a judgment awarding Rick and Janan Snider, doing business as RJ Snider Construction ("RJ Snider"), $198,255.08 for unjust enrichment and quantum meruit claims. In 2011, RJ Snider contracted with Granville Brinkman to furnish materials and labor for construction work on real property owned by Dickinson Elks. RJ Snider's principal place of business was located in Washington. In 2012, RJ Snider applied for a contractor license from the North Dakota Secretary of State, and the license was issued on in February 2012. RJ Snider provided services and materials for Dickinson Elks' property from December 26, 2011, to November 30, 2012. Dickinson Elks paid RJ Snider for all of the services and materials it provided between December 26, 2011, and February 1, 2012. RJ Snider billed Dickinson Elks $174,642.10 for the services and materials it provided from March 15, 2012, until November 30, 2012. Dickinson Elks did not pay any of this amount. In January 2013, RJ Snider recorded a construction lien against Dickinson Elks' property. In May 2014, Dickinson Elks served RJ Snider with a demand to start a lawsuit to enforce the lien and record a lis pendens within 30 days of the demand. RJ Snider sued Dickinson Elks in June 2014, seeking foreclosure of the construction lien and a money judgment. RJ Snider recorded a notice of lis pendens on July 28, 2014. Dickinson Elks moved for summary judgment, arguing RJ Snider's complaint should be dismissed under N.D.C.C. 43-07-02 because RJ Snider was not a licensed contractor when it started work on the property. Dickinson Elks also argued RJ Snider did not have a valid construction lien, because RJ Snider did not record a lis pendens within 30 days of receiving the demand to enforce the lien. The district court partially granted the motion and entered a judgment forfeiting RJ Snider's construction lien because RJ Snider did not record a lis pendens within 30 days of receiving Dickinson Elks' demand to enforce the lien as required under N.D.C.C. 35-27-25. The court concluded RJ Snider's claims were not precluded under N.D.C.C. 43-07-02. RJ Snider amended its complaint, claiming it was entitled to a money judgment against Dickinson Elks under the principles of quantum meruit and unjust enrichment. The North Dakota Supreme Court concluded RJ Snider was not precluded from maintaining its claims; however, the Court reversed and remanded for the district court to determine whether any of the damages awarded were for services and materials provided before RJ Snider was licensed. View "Snider v. Dickinson Elks Building, LLC" on Justia Law
Black & Veatch Corp. v. Aspen Insurance
At issue in this case was whether Aspen Insurance (UK) Ltd. And Lloyd’s Syndicate 2003 (collectively, “Aspen”) had to reimburse Black & Veatch Corporation (“B&V”) for costs B&V incurred due to damaged equipment a subcontractor made for power plants in Ohio and Indiana. The district court held Aspen did not have to pay B&V’s claim under its commercial general liability (“CGL”) insurance policy because B&V’s expenses arose from property damages that were not covered “occurrences” under the Policy. Because the only damages involved here were to B&V’s own work product arising from its subcontractor’s faulty workmanship, the court concluded that the Policy did not provide coverage and granted Aspen’s motion for partial summary judgment. B&V appealed. The Tenth Circuit found that the Policy contained a choice-of-law clause, making the Policy subject to New York law. The Court also found a trend among state supreme courts that supported the contention that construction defects could constitute “occurrences” under CGL policies, and that contractors have coverage for the unexpected damage caused by defective workmanship done by subcontractors. The Tenth Circuit predicted the New York Court of Appeals would decide that the damages here constituted an “occurrence” under the Policy, and as such, vacated the district court’s summary judgment decision and remand for further proceedings. View "Black & Veatch Corp. v. Aspen Insurance" on Justia Law