Land Holdings I, LLC d/b/a Scarlet Pearl, LLC v. GSI Services, LLC
Land Holdings I, LLC, d/b/a Scarlet Pearl, LLC (“Casino”), sought to expunge a lien filed by GSI Services, LLC (“GSI”). The chancellor denied the Casino’s petition to expunge the lien because GSI performed work at the Casino within ninety days of filing its lien. Finding no error, the Mississippi Supreme Court affirmed the chancellor’s order. View "Land Holdings I, LLC d/b/a Scarlet Pearl, LLC v. GSI Services, LLC" on Justia Law
Hexagon Holdings, Inc. v. Carlisle Syntec Inc.
The Supreme Court affirmed the judgment of the superior court granting summary judgment in favor of Defendant in this construction dispute, holding that summary judgment was appropriate.Plaintiff entered into a contract with a general contractor to construct a facility. The general contractor subcontracted the roofing installation to Defendant. When the roof began to leak, Plaintiff filed a complaint against the general contractor and Defendant, alleging breach of contract, breach of the implied warranty to construct in good and workmanlike manner, misrepresentation, and negligence. The superior court granted Defendant’s motion for summary judgment, holding that Plaintiff was only an incidental beneficiary, as opposed to an intended beneficiary, of the subcontract between Defendant and the general contractor. The Supreme Court affirmed, holding that the motion justice appropriately granted summary judgment in favor of Defendant on Plaintiff’s claims. View "Hexagon Holdings, Inc. v. Carlisle Syntec Inc." on Justia Law
Berkeley Cement, Inc. v. Regents of the University of California
Berkeley appealed the judgment against it in a construction dispute regarding a building on the Merced Campus. After the University denied Berkeley's claim for compensation for work performed, Berkeley filed suit alleging causes of action for breach of contract, breach of the implied covenant of good faith and fair dealing, and breach of the implied covenant of the correctness of the plans and specifications.The Court of Appeal held that the jury's findings were not fatally inconsistent and the verdict was not against the law; the trial court did not err in instructing the jury that specification 03300 of the contract constituted a performance specification, and Berkeley was required to exercise its skill and judgment in selecting the means, methods, and equipment necessary to meet the end result called for in the specification; there was no abuse of discretion or deprivation of a fair trial; Berkeley has not demonstrated any prejudicial error in the trial court's exclusion of evidence of the total cost method of calculating damages; and Berkeley has not established any reversible error in the trial court's award of mediation fees as costs. However, the court held that the expert witness fees were improperly included in the award of costs and therefore must be modified. The court otherwise affirmed the judgment. View "Berkeley Cement, Inc. v. Regents of the University of California" on Justia Law
International Brotherhood of Teamsters v. City of Monterey Park
Petitioners sought a writ of mandate and declaratory relief, alleging that the City of Monterey Park breached its duty under Labor Code section 1072 to award a 10-percent bidding preference only to contractors who declare in their bids they will retain existing employees for at least 90 days. The trial court held that there was no such duty and ruled in favor of the City.The Court of Appeal held that words "shall declare as part of the bid" in Labor Code section 1072, subdivision (a), mean the bidder must state in its bid whether it will retain the employees of the prior contractor for 90 days. If the public agency (or "awarding authority") gives the statutory preference to bidders who do not agree in their bids to retain the employees of the prior contractor for at least 90 days, a bidder who makes the commitment is not really getting a statutory preference. The court held that whether a variance is inconsequential is a question of fact, subject to review for substantial evidence, that is not properly decided on demurrer. Therefore, the court reversed and remanded with directions for the trial court to vacate its order sustaining the demurrer without leave to amend and to enter a new order overruling the demurrer. View "International Brotherhood of Teamsters v. City of Monterey Park" on Justia Law
JMS Air Conditioning & Appliance Service, Inc. v. Santa Monica Community College District
The Court of Appeal affirmed the superior court's denial of JMS's petition for writ of administrative mandate seeking to set aside an administrative decision by the District that allowed a contractor to substitute another subcontractor in the place of JMS on a construction project. The court held that the hearing officer had jurisdiction to approve the request for substitution under Public Contract Code section 4107; neither substitution hearing nor the substitution decision affected a fundamental vested right; the hearing afforded JMS the due process required for a substitution hearing; substantial evidence supported the substitution decision; and thus the petition was properly denied. View "JMS Air Conditioning & Appliance Service, Inc. v. Santa Monica Community College District" on Justia Law
Sienna Court Condominium Assoc. v. Champion Aluminum Corp.
The owners of units in Sienna Court Condominiums, a newly-constructed 111-residential-unit Evanston property sued, alleging that the developer, TR, sold the units with latent defects that resulted in water infiltration and other conditions that rendered the individual units and common areas unfit for habitation. The complaint alleged breach of an express warranty and breach of an implied warranty of habitability against TR, the general contractor, the architect and engineering design firms, material suppliers and several subcontractors. TR and the general contractor were bankrupt. The unit owners obtained relief from the automatic bankruptcy stay. TR and the general contractor had two separate insurance policies, each providing coverage of $1 million per occurrence with $2 million aggregate limits. Plaintiffs had recovered approximately $308,000 from TR through a warranty escrow fund required by Evanston ordinance. Subcontractors and the material suppliers asserted that they were not subject to an implied warranty of habitabililty. The circuit court denied their motion to dismiss. The Illinois Supreme Court reversed, holding that a purchaser of a newly constructed home may not assert a claim for breach of an implied warranty of habitability against a subcontractor who took part in the construction of the home, where the subcontractor had no contractual relationship with the purchaser. View "Sienna Court Condominium Assoc. v. Champion Aluminum Corp." on Justia Law
M.E.S., Inc. v. Safeco Insurance Co. of America
The Second Circuit affirmed the district court's summary judgment dismissal of all claims in the Second Amended Complaint against defendants in an action stemming from construction projects with the U.S. Army Corps of Engineers. The court held that MES's claims failed to articulate any support for its accusations that Safeco breached its contractual obligations or engaged in bad faith or tortious conduct. The court noted that the claim that Safeco acted inappropriately by attending the cure meetings was particularly frivolous. In this case, MES failed to identify any good faith basis, in law or on the basis of the agreements at issue, for its assertion that Safeco had no right to take steps to meet its obligations under the surety bonds. The court sua sponte awarded Safeco double costs. View "M.E.S., Inc. v. Safeco Insurance Co. of America" on Justia Law
Bakke v. Magi-Touch Carpet One Floor & Home, Inc.
Shannon Bakke appeals a judgment in favor of Magi-Touch Carpet One Floor & Home, Inc. and denial of her motion to amend her complaint. Bakke entered into a contract with Magi-Touch for the installation of floor tiles, a shower base, and related products in a bathroom within Bakke's home. Magi-Touch arranged to have the shower base and tile installed by VA Solutions, LLC, an independent contractor. Bakke contended the shower door was improperly installed; the improper installation resulted in the shower door imploding, and the implosion caused damage to property in and around the shower requiring the bathroom door and trim to be repainted. Bakke argued the district court erred in concluding she could not pursue a claim against Magi-Touch because Magi-Touch was not liable for the acts of its independent contractor. Bakke also asserts the district court erred in denying, as futile, her motion to amend her complaint to assert a contract claim against Magi-Touch. Assuming Bakke properly asserted a claim for breach of the parties' contract, the North Dakota Supreme Court held the delegation of Magi-Touch's obligation to provide labor to VA Solutions did not preclude a cause of action against Magi-Touch for a breach of the contract. Further, the Court held the existence of the independent contractor did not relieve Magi-Touch of its obligation to perform under the terms of its contract with Bakke. In the context of a claim for a breach of the parties' contract, the amendment was not futile and should have been allowed. The Court affirmed as to all other issues, and remanded this case for further proceedings. View "Bakke v. Magi-Touch Carpet One Floor & Home, Inc." on Justia Law
NOVA Contracting, Inc. v. City of Olympia
The City of Olympia, Washington contracted with NOVA Contracting, Inc. to replace a deteriorating culvert. The contract contained a "notice of protest" provision, which was taken from the Washington Department of Transportation's "standard Specifications for Road, Bridge, and Municipal Construction (2012) manual. NOVA sued the City for breach of the implied covenant of good faith and fair dealing; the City moved to dismiss based in part on NOVA's filature to file a protest first before taking the City to court. The trial court dismissed NOVA's claim, but the Court of Appeals reversed. The Washington Supreme Court has addressed this written notice issue twice before; the Court of Appeals interpreted those holdings, however, as only applying to claims for cost of work performed and not claims for expectancy and consequential damages. The Supreme Court held the two prior cases applied even to claims of expectancy and consequential damages. Therefore, the Court reversed the appellate court and remanded this case for further proceedings. View "NOVA Contracting, Inc. v. City of Olympia" on Justia Law
Randy Kinder Excavating, Inc. v. JA Manning Construction Co.
Kinder filed suit against Manning, alleging that Manning breached a contract to build a pumping station. The Eighth Circuit affirmed the district court's judgment in favor of Manning, holding that Kinder committed the first material breach of contract by threatening to assess delay-related damages without any justification, interfering with the relationship between Manning and EarthTec, and failing to provide adequate assurances that Manning would be paid for its work. The court also held that the district court correctly found that Kinder wrongfully terminated the contract and that evidence at trial supported the damage award. View "Randy Kinder Excavating, Inc. v. JA Manning Construction Co." on Justia Law