Justia Contracts Opinion Summaries
Articles Posted in Construction Law
Jed Spectrum, Inc. v. Stoakes
Bighorn Construction, LLC (Bighorn) and JED Spectrum, Inc. (JED) filed mechanic’s liens against property owned by Keith Stoakes, seeking to foreclose on the liens. Stoakes denied the validity of the liens and counterclaimed for slander of title against both companies, and for breach of contract, promissory estoppel, and fraud against JED. After a bench trial, the circuit court denied Bighorn’s and JED’s claims for lien foreclosure and ruled in favor of Stoakes on his slander of title claims, awarding him $252,225.27 in damages and $33,394.20 in attorney fees. The court denied relief on the remaining claims.The circuit court found that Bighorn had no reasonable grounds to file the lien after receiving a check for full payment, and that JED’s lien was untimely and insufficiently itemized. The court also found that Stoakes reasonably relied on JED’s promise of a shared well system, awarding him damages for promissory estoppel. However, the court later reversed its decision on the promissory estoppel claim and reduced the attorney fee award accordingly.The Supreme Court of South Dakota reviewed the case. It reversed the circuit court’s ruling on the slander of title claims, finding insufficient evidence to prove that Jerry, acting on behalf of Bighorn and JED, knew or recklessly disregarded the falsity of the liens. The court affirmed the denial of Stoakes’s promissory estoppel claim, concluding that Stoakes did not suffer substantial economic detriment. The court also affirmed the attorney fee award of $33,394.20 to Stoakes, as it was within the court’s discretion under SDCL 44-9-42. View "Jed Spectrum, Inc. v. Stoakes" on Justia Law
Kratzer Construction v. Hardy Construction
Kratzer Construction entered into a subcontract with Hardy Construction Co. to perform work on a building addition for Ekalaka Public Schools. Kratzer completed the work and submitted pay applications, including one for $92,856.45, which Hardy partially disputed due to unapproved change orders. Hardy offered to pay $81,153 upon Kratzer signing a release, but Kratzer refused, demanding the full amount plus interest. Hardy later offered the same amount without requiring a release, but Kratzer still declined, insisting on interest.The Sixteenth Judicial District Court granted summary judgment to Kratzer, ruling that Hardy owed $81,153 plus 18% interest from January 6, 2022, and attorney fees, as Kratzer was deemed the prevailing party. Hardy appealed, arguing that Kratzer failed to meet a condition precedent in the subcontract requiring submission of releases from his subcontractors before final payment.The Supreme Court of Montana reviewed the case and concluded that the subcontract's provisions were clear and unambiguous. The court determined that Kratzer's failure to submit the required releases constituted a breach of the subcontract, and Hardy was entitled to withhold payment. The court found that Hardy's offers to settle did not constitute a waiver of the condition precedent or a novation of the contract.The Supreme Court reversed the District Court's summary judgment in favor of Kratzer, including the awards for interest and attorney fees. The court remanded the case for entry of judgment in favor of Hardy, requiring Hardy to pay Kratzer $81,153 for services rendered under the subcontract, less reasonable attorney fees and costs incurred by Hardy. View "Kratzer Construction v. Hardy Construction" on Justia Law
Johnson v. Albin Carlson & Co.
A contractor hired a subcontractor to work on a remote bridge construction project. The scope of the work changed, and neither party kept detailed records of the changes and associated costs. Years after the project was completed, the subcontractor sued for damages, claiming unpaid work. The superior court found that the subcontract did not govern the extra work, awarded some damages to the subcontractor, and precluded some claims due to discovery violations. The court also found the contractor to be the prevailing party and awarded attorney’s fees. Both parties appealed.The superior court denied summary judgment motions from both parties, finding factual disputes. It precluded the subcontractor from pursuing certain damages claims due to insufficient documentation but allowed evidence for contingent findings. After a bench trial, the court awarded the subcontractor $191,443.42, later reduced to $146,693.42 upon reconsideration. The court found the contractor to be the prevailing party under Rule 68 and awarded attorney’s fees.The Supreme Court of Alaska reviewed the case. It concluded that the superior court abused its discretion by precluding the subcontractor’s claims for snowmachine use and labor without considering less severe sanctions. The court affirmed the superior court’s findings on other damages but reversed the awards for Morris Johnson’s labor and boat use, remanding for recalculation. The prevailing party determination and attorney’s fee award were vacated and remanded for reconsideration. The court otherwise affirmed the superior court’s judgment. View "Johnson v. Albin Carlson & Co." on Justia Law
Smith Masonry v. Wipi Group Inc.
Tom Smith Masonry (Smith Masonry) and WIPI Group USA, Inc. (WIPI) entered into a contract for Smith Masonry to construct a fence on WIPI’s property. After completing most of the work, Smith Masonry requested final payment, which WIPI withheld due to a dispute over the installation of a gate operator. Smith Masonry filed a mechanic’s lien and subsequently a lawsuit to foreclose on the lien, seeking the unpaid balance. WIPI counterclaimed for breach of contract and other issues, seeking damages for alleged faulty workmanship.The Circuit Court of the Second Judicial Circuit, Lincoln County, South Dakota, denied relief to both parties, finding that Smith Masonry’s work was defective and that WIPI’s damages were not established with exactitude. Smith Masonry appealed, and the South Dakota Supreme Court reversed and remanded, directing the lower court to enter a judgment of foreclosure in favor of Smith Masonry for the full amount of the lien and to reconsider Smith Masonry’s request for attorney fees.On remand, the circuit court entered a judgment in favor of Smith Masonry on the lien but denied the request for attorney fees. Smith Masonry appealed again. The South Dakota Supreme Court found that the circuit court violated the law of the case doctrine by revisiting issues already settled in the first appeal and by speculating on what might have occurred had the trial resumed. The Supreme Court also held that the circuit court abused its discretion by denying attorney fees based on irrelevant factors and an overly narrow interpretation of the statute governing attorney fees in mechanic’s lien cases.The South Dakota Supreme Court reversed the circuit court’s denial of attorney fees and remanded for a determination of an appropriate award of attorney fees consistent with its opinion. The court also awarded Smith Masonry $30,000 for appellate attorney fees. View "Smith Masonry v. Wipi Group Inc." on Justia Law
Edgerock Development, LLC v. C.H. Garmong & Son Inc
EdgeRock Development, LLC developed a planned unit development in Westfield, Indiana, comprising retail and residential projects. EdgeRock contracted with C.H. Garmong & Son, Inc. and Fox Contractors Corp. to develop the lots. When EdgeRock fell behind on payments, Garmong and Fox recorded construction liens on all five lots, including those sold to ZPS Westfield, LLC and a nonparty. The contractors sued EdgeRock for breach of contract and sought to foreclose the liens.The Hamilton Superior Court awarded the contractors most of the relief they sought, including foreclosure of the construction liens. The Indiana Court of Appeals reversed the foreclosure, concluding the liens were overstated as they were not limited to debts for improvements directly benefiting the properties to which the liens attached.The Indiana Supreme Court reviewed the case to address the validity and scope of the construction liens and the priority between the construction liens and First Bank Richmond’s mortgage lien. The court held that a construction lien secures only the debt for improvements directly benefiting the property to which the lien attaches. Therefore, the contractors can foreclose the liens on each property to recover only those amounts. The court also concluded that First Bank’s mortgage lien is senior to the construction liens for the amount loaned to satisfy Garmong’s prior construction lien but junior for the remaining amounts.The court affirmed the trial court’s judgment in part, reversed in part, and remanded for the trial court to amend the judgment consistent with its opinion. The court also noted that its holdings do not disturb the in personam judgments against EdgeRock on Garmong’s and Fox’s breach-of-contract claims. View "Edgerock Development, LLC v. C.H. Garmong & Son Inc" on Justia Law
Cashman Equipment Corporation, Inc. v. Cardi Corporation, Inc.
Cashman Equipment Corporation, Inc. (Cashman) was contracted by Cardi Corporation, Inc. (Cardi) to construct marine cofferdams for the Sakonnet River Bridge project. Cashman then subcontracted Specialty Diving Services, Inc. (SDS) to perform underwater aspects of the cofferdam installation. Cardi identified deficiencies in the cofferdams and sought to hold Cashman responsible. Cashman believed it had fulfilled its contractual obligations and sued Cardi for breach of contract, unjust enrichment, and quantum meruit. Cardi counterclaimed, alleging deficiencies in Cashman's construction. Cashman later added SDS as a defendant, claiming breach of contract and seeking indemnity and contribution.The Superior Court denied SDS's motion for summary judgment, finding genuine disputes of material fact. The case proceeded to a jury-waived trial, after which SDS moved for judgment as a matter of law. The trial justice granted SDS's motion, finding Cashman failed to establish that SDS breached any obligations. SDS then moved for attorneys' fees, which the trial justice granted, finding Cashman's claims were unsupported by evidence and lacked justiciable issues of fact or law. The trial justice ordered mediation over attorneys' fees, resulting in a stipulated amount of $224,671.14, excluding prejudgment interest.The Rhode Island Supreme Court reviewed the case and affirmed the Superior Court's amended judgment. The Supreme Court held that the trial justice did not err in granting judgment as a matter of law, as Cashman failed to provide specific evidence of justiciable issues of fact. The Court also upheld the award of attorneys' fees, finding no abuse of discretion. Additionally, the Court determined that the attorneys' fees were not barred by the Bankruptcy Code, as they arose post-confirmation and were not contingent claims. View "Cashman Equipment Corporation, Inc. v. Cardi Corporation, Inc." on Justia Law
Flintco, LLC v Total Installation Management Specialists, Inc.
A contractor, Flintco, LLC, entered into a subcontract with Total Installation Management Specialists, Inc. (Total) for flooring work on a construction project at Oklahoma State University. Total was required to secure a performance bond from Oklahoma Surety Company (OSC). Flintco later supplemented Total's workforce due to delays and performance issues but did not notify OSC until five weeks after taking over the work.The Tulsa County District Court ruled in favor of Flintco, awarding damages against Total and OSC. OSC appealed, arguing that Flintco failed to meet the performance bond's conditions requiring a declaration of default and reasonable notice before assuming control of the work. The Court of Civil Appeals reversed the district court's judgment, finding that the notice requirement was a mandatory condition precedent, and Flintco's failure to provide timely notice relieved OSC of liability.The Supreme Court of the State of Oklahoma reviewed the case and agreed with the Court of Civil Appeals. The court held that the performance bond's notice requirement constituted a mandatory condition precedent. Flintco's failure to provide timely notice to OSC so it could exercise its performance options under the bond relieved OSC from liability. The court vacated the Court of Civil Appeals' opinion, reversed the district court's judgment, and remanded the case with instructions to enter judgment consistent with this decision. The trial court's judgments against Total were not affected by this decision. View "Flintco, LLC v Total Installation Management Specialists, Inc." on Justia Law
Grosvold v. Neely
Neely, acting as his own general contractor, hired Grosvold to perform excavation work on his property under an oral contract. Grosvold worked from April to October 2021, but their relationship deteriorated, and Neely refused to pay for an invoice amounting to $55,858. Neely sent Grosvold a notice of alleged defects in the work, which Grosvold disputed. Grosvold then filed a complaint for breach of contract and prejudgment interest, while Neely counterclaimed for breach of contract, negligence, and construction defect.The District Court of the Third Judicial District in Anaconda-Deer Lodge County tried the case before a jury. The court refused to instruct the jury on Neely’s construction defect and negligence claims, reasoning that the evidence did not substantiate the work was done to a residence and that the case was strictly a breach of contract matter. The jury found Neely had breached the contract and awarded Grosvold $60,512.60 in damages. The court denied Grosvold’s request for prejudgment interest, finding the damages were not certain until the jury’s determination.The Supreme Court of the State of Montana reviewed the case. It affirmed the District Court’s decision not to instruct the jury on the construction defect claim, holding that the residential construction defect statute did not create an independent cause of action beyond breach of contract or tort. The court also affirmed the refusal to instruct the jury on negligence, finding that Neely’s substantial rights were not affected as the breach of contract instructions adequately covered the disputed subject matter. Finally, the court upheld the denial of prejudgment interest, concluding the amount of recovery was not capable of being made certain until the jury’s verdict. View "Grosvold v. Neely" on Justia Law
Palmetto Pointe v. Tri-County Roofing
In 2005, Island Pointe, LLC contracted Complete Building Corporation (CBC) to construct a condominium project, Palmetto Pointe at Peas Island. CBC subcontracted Tri-County Roofing (TCR) for roofing and related work. In 2014-2015, Palmetto discovered construction defects and sued CBC, TCR, and others for negligence and breach of warranty. Palmetto received $6,800,000 in settlements, including $1,000,000 from CBC's insurer for a covenant-not-to-execute and $1,975,000 from four other defendants.The trial began in May 2019, and the jury found CBC and TCR liable for $6,500,000 in actual damages and $500,000 each in punitive damages. The trial court apportioned 5% liability to two other defendants, making CBC and TCR jointly and severally liable for the remaining 90% of actual damages. TCR sought setoff for the $1,000,000 payment and the settlements from the four other defendants. The trial court denied TCR's motion for setoff, except for partial amounts conceded by Palmetto.The South Carolina Supreme Court reviewed the case. It reversed the court of appeals' decision, holding that TCR is entitled to set off the full $1,000,000 paid by CBC's insurer. The court affirmed the lower court's decision regarding the settlements from Novus, Atlantic, H and A, and Cohen's, agreeing that the trial court reasonably allocated the settlement amounts. The case was remanded to the trial court for the calculation of the judgment against TCR. View "Palmetto Pointe v. Tri-County Roofing" on Justia Law
Mid-Century Ins. Co. v. HIVE Construction
HIVE Construction, Inc. served as the general contractor for the construction of Masterpiece Kitchen, a restaurant. The contract required HIVE to follow specific architectural plans, including installing two layers of drywall on a wall separating the kitchen and dining area. Instead, HIVE installed one layer of drywall and one layer of combustible plywood without approval. A fire started within the wall, causing significant damage and forcing the restaurant to close. Mid-Century Insurance Company, as the property insurer and subrogee of Masterpiece Kitchen, paid for the damages and then sued HIVE for negligence, alleging willful and wanton conduct.The district court initially allowed Mid-Century to amend its complaint to include a breach of contract claim but later reversed this decision, requiring Mid-Century to proceed with the negligence claim. At trial, the jury found HIVE's conduct to be willful and wanton, awarding damages to Mid-Century. HIVE appealed, arguing that the economic loss rule barred the negligence claim. The Colorado Court of Appeals agreed, reversing the district court's decision and instructing a verdict in HIVE's favor.The Supreme Court of Colorado reviewed the case and concluded that the economic loss rule does not provide an exception for willful and wanton conduct. The court held that the rule barred Mid-Century's negligence claim because the duty HIVE allegedly breached was not independent of its contractual obligations. Consequently, the court affirmed the judgment of the Colorado Court of Appeals, upholding the application of the economic loss rule to bar the negligence claim. View "Mid-Century Ins. Co. v. HIVE Construction" on Justia Law