Justia Contracts Opinion Summaries
Articles Posted in Construction Law
AVL Test Systems v. Hensel Phelps Construction
The dispute arose from a contract in which a company specializing in vehicle emissions testing equipment agreed to supply and install its products in a facility being constructed by a general contractor for a state agency. After receiving substantial payments, the equipment supplier sought additional compensation through arbitration. The general contractor defended by arguing that the supplier was not properly licensed as required by California’s Contractors State Licensing Law (CSLL), and thus could not recover payment. The supplier then initiated a lawsuit seeking a judicial declaration that it was exempt from the CSLL’s licensing requirements because its equipment did not become a “fixed part of the structure,” referencing an exemption in the law.The Superior Court of Riverside County reviewed cross-motions for summary judgment. The general contractor argued the exemption did not apply because the equipment became permanently affixed to the building, and the supplier had performed work before obtaining a license. The supplier contended its products were portable and not intended to be permanent fixtures, and that it acted as an equipment installer exempt under the law. The superior court granted summary judgment for the general contractor, finding that the evidence showed the equipment did become a fixed part of the structure and thus the supplier needed a contractor’s license.On appeal, the California Court of Appeal, Fourth Appellate District, Division One, found the lower court erred by deciding as a matter of law that the exemption did not apply. The appellate court held that whether the equipment became a fixed part of the structure is a factual question, not one suitable for summary judgment on the record before it. Because there was conflicting evidence—including expert declarations—on this issue, the trial court should have permitted the factual dispute to be resolved by a trier of fact. The appellate court reversed the judgment and remanded the case for further proceedings. View "AVL Test Systems v. Hensel Phelps Construction" on Justia Law
Cuevas Machine v. Calgon Carbon
Cuevas Machine Company entered into a subcontract with O’Neal Constructors for fabrication and machining work at a filtration plant owned by Calgon Carbon Corporation in Mississippi. Under the subcontract, Cuevas was to be paid after Calgon paid O’Neal. Despite nonpayment from O’Neal, Cuevas continued its work. In October 2023, Cuevas recorded two construction liens totaling over $1.2 million against Calgon’s property, but the lien documents did not explicitly state the last date labor, services, or materials were supplied—a statutory requirement. Instead, Cuevas attached invoices to the liens, which included dates, but it was unclear whether these dates satisfied the statutory requirement.After Cuevas filed suit to foreclose on the liens in Mississippi state court, Calgon removed the case to the United States District Court for the Southern District of Mississippi and moved to dismiss. The district court granted Calgon’s motion, dismissing Cuevas’s complaint with prejudice under Rule 12(b)(6). The district court concluded, making an Erie guess, that the liens were unenforceable because they did not clearly specify the required “last date” in the manner demanded by Mississippi law, and found that the attached invoices did not sufficiently cure this defect.On appeal, the United States Court of Appeals for the Fifth Circuit reviewed the district court’s decision de novo. Finding Mississippi law ambiguous on whether attachments that do not plainly state the “last date” can satisfy the statutory requirement, the Fifth Circuit certified the following question to the Mississippi Supreme Court: whether attaching invoices that do not explicitly state the “last date labor, services or materials were supplied” satisfies the requirement under Miss. Code Ann. § 85-7-405(1)(b) that a lien “specify the date the claim was due.” The Fifth Circuit did not decide the merits, instead certifying the question for authoritative resolution. View "Cuevas Machine v. Calgon Carbon" on Justia Law
Ralph L. Wadsworth Constr. Co. v. Reg’l Rail Partners
A public entity contracted with a general contractor to construct a major rail line project. The general contractor, in turn, subcontracted a significant portion of the work to a subcontractor. As the project progressed, it experienced numerous delays and disruptions, which the subcontractor claimed increased its costs. After completing its performance, the subcontractor, relying on expert analysis of its additional costs, filed a verified statement of claim under the Colorado Public Works Act, asserting it was owed additional millions for labor, materials, and other costs, including those stemming from delay and disruption.Following the filing, the general contractor substituted a surety bond for the retained project funds and the subcontractor initiated litigation in Denver District Court. After a bench trial, the trial court found in favor of the subcontractor, concluding that its verified statement of claim was not excessive and that there was a reasonable possibility the claimed amount was due. The court awarded the subcontractor damages for delay, disruption, and unpaid funds. The general contractor appealed, contending the claim was excessive and should result in forfeiture of all rights to the claimed amount. The Colorado Court of Appeals reversed in relevant part, holding that the verified statement of claim was excessive as a matter of law and that the subcontractor forfeited all rights to the amount claimed. This disposition left certain issues raised by the subcontractor on cross-appeal unaddressed.The Supreme Court of Colorado granted review and held that, under the Public Works Act, disputed or unliquidated amounts—including delay and disruption damages—may be included in a verified statement of claim if they represent the specified categories of costs and the claim is not excessive under the statute. The court also held that filing an excessive claim results only in forfeiture of statutory remedies under the Act, not all legal remedies. The Supreme Court reversed the Court of Appeals’ judgment and remanded for further proceedings. View "Ralph L. Wadsworth Constr. Co. v. Reg'l Rail Partners" on Justia Law
John B. Cruz Construction Co. v. Beacon Communities Corp.
A black-owned construction company was not invited to bid as general contractor on a major Boston public housing redevelopment project after participating in pre-construction work. Years earlier, the developer had called the company’s president to discuss possible involvement, but the parties disputed what promises, if any, were made during that conversation. The construction company performed pre-construction work and was later selected as general contractor for the first phase (Camden), but after performance and communication issues arose during that project, the developer chose a different, white-owned company for the second phase (Lenox). The construction company did not protest at the time but later sued, alleging breach of contract, quasi-contract, violation of Massachusetts consumer protection law, and racial discrimination under 42 U.S.C. § 1981.The matter was first brought in Massachusetts state court, then removed to the United States District Court for the District of Massachusetts based on federal question jurisdiction. After discovery, the developer moved for summary judgment. The District Court granted summary judgment for the developer, finding no enforceable contract or promise had been made regarding the Lenox phase, that the quasi-contract and Chapter 93A claims failed as derivative, and that there was insufficient evidence of racial discrimination.The United States Court of Appeals for the First Circuit affirmed the District Court’s decision. The First Circuit held that the summary judgment record did not contain evidence from which a reasonable jury could find an enforceable implied-in-fact contract or a promise sufficient for promissory estoppel. It further held that the plaintiff failed to create a triable issue of fact regarding pretext or discriminatory intent under § 1981, given the legitimate business reasons cited for the company’s exclusion. Thus, summary judgment on all claims was proper. View "John B. Cruz Construction Co. v. Beacon Communities Corp." on Justia Law
Eastern Steel v. Int Fidelity Ins. Co.
A steel subcontractor was hired to perform work for a university construction project and entered into a subcontract with the general contractor. The general contractor began defaulting on payments, prompting the subcontractor to notify the surety insurance company, which had issued a payment bond guaranteeing payment for labor, materials, and equipment. The surety made partial payment but disputed the remaining amount. The subcontractor then demanded arbitration against the contractor, with the surety notified and invited to participate. The contractor filed for bankruptcy and did not defend in arbitration, nor did the surety participate. The arbitrator awarded the subcontractor damages, including attorneys’ fees and interest, and the award was confirmed in court. The subcontractor sought to enforce the arbitration award against the surety, including attorneys’ fees and prejudgment interest, and also brought a bad faith claim under Pennsylvania’s insurance statute.The Centre County Court of Common Pleas initially excluded evidence of the arbitration award against the surety at trial and ruled the surety was not liable for attorneys’ fees or bad faith damages. A jury found for the subcontractor on the underlying debt, and the court awarded prejudgment interest at the statutory rate. Both parties appealed. The Superior Court held the arbitration award was binding and conclusive against the surety, who had notice and opportunity to participate, and affirmed liability for attorneys’ fees related to pursuing the contractor in arbitration. The court rejected the bad faith claim, holding the statute did not apply to surety bonds, and confirmed the statutory interest rate.On appeal, the Supreme Court of Pennsylvania affirmed in all respects. It held that Pennsylvania’s insurance bad faith statute does not apply to surety bonds, based on statutory language. The court also held that the surety is bound by the arbitration award against its principal, and is liable for attorneys’ fees incurred in arbitration and prejudgment interest at the statutory rate. View "Eastern Steel v. Int Fidelity Ins. Co." on Justia Law
Gunwerks, LLC v. Forward Cody Wyoming, Inc.
A Wyoming firearms manufacturer sought to expand its operations by constructing a new facility. The company, unable to directly access specific state economic development funds, partnered with a city and a local non-profit to obtain funding, resulting in a written agreement outlining each party’s roles. The non-profit was charged with managing the project, including hiring architects and contractors. During and after construction, the manufacturer identified substantial design and construction defects, including climate control problems, leaks, and structural issues. The manufacturer sued the non-profit for breach of contract and also sued the architect and contractor, asserting it was a third-party beneficiary of their contracts with the non-profit.In the District Court of Park County, the court dismissed the manufacturer’s claims against the architect and contractor, finding it was not an intended third-party beneficiary under their contracts, and granted summary judgment to the non-profit on all but one claim, determining that the non-profit’s contractual obligations were limited to financial administration of the project. The remaining claim was later dismissed by stipulation.The Supreme Court of Wyoming reviewed the case de novo. The court held that the district court erred in dismissing the manufacturer’s claims against the architect and contractor because, accepting the complaint’s factual allegations as true and considering the relevant contracts, the manufacturer had sufficiently alleged facts that could support third-party beneficiary status and breach of contract. The court also found the district court erred in granting summary judgment to the non-profit, concluding that the contract’s language and context imposed broader duties on the non-profit, including project administration and construction oversight, not merely financial management. The Supreme Court of Wyoming reversed the lower court’s orders of dismissal and summary judgment, allowing the manufacturer’s claims to proceed. View "Gunwerks, LLC v. Forward Cody Wyoming, Inc." on Justia Law
Heritage Const. Companies, LLC v. Keithahn
The dispute arose from a failed attempt to construct an osteopathic medical school in Gaylord, Minnesota. Philip Keithahn formed Minnesota Medical University, LLC (MMU) and retained Heritage Construction Companies, LLC as the general contractor. MMU planned to finance the project through bond proceeds, with a portion immediately available and the remainder contingent on achieving pre-accreditation. Representatives from Heritage sought confirmation of available funds prior to construction, and Keithahn assured them that the project would be funded and that millions would be available after closing. However, after initial payments, MMU ran out of funds when pre-accreditation was denied, leading Heritage to halt construction and terminate its contract.The United States District Court for the District of Minnesota oversaw the case after Heritage and its affiliates faced indemnification claims and filed a third-party complaint against Keithahn and MMU. The defendants’ motion for summary judgment was denied, and the case proceeded to trial on claims including breach of contract, indemnification, negligent misrepresentation, fraudulent misrepresentation, and fraud by omission. MMU admitted liability for breach of contract and damages. The jury found the defendants liable on all claims except fraudulent misrepresentation. Post-verdict, the district court denied defendants’ motions for judgment as a matter of law or for a new trial, addressing issues of jury instructions, violations of in limine orders, improper statements, and impeachment.The United States Court of Appeals for the Eighth Circuit reviewed the appeal. It held that Keithahn’s representations regarding available financing were actionable as negligent misrepresentations, as they concerned present facts susceptible of knowledge rather than mere future assurances. The court found no error in the jury instructions, no prejudicial violation of evidentiary rulings, and no cumulative error warranting a new trial. The Eighth Circuit affirmed the district court’s judgment. View "Heritage Const. Companies, LLC v. Keithahn" on Justia Law
Sletten Construction of Wyoming, Inc. v. Big Horn Glass, Inc.
Gunwerks sought to expand its business by constructing a new manufacturing facility in Cody, Wyoming, a project involving public funds and coordinated through Forward Cody Wyoming, Inc. Forward Cody retained Plan One Architects and Sletten Construction of Wyoming, Inc. as the project's designer and general contractor, respectively. Sletten hired various subcontractors, including Big Horn Glass, Inc. (BHG), to perform specific tasks. After completion, Gunwerks alleged numerous construction defects in the facility, including issues with concrete, finishes, HVAC, siding, drainage, ceiling heights, door and window flashings, and the shooting tunnel. Gunwerks sued Forward Cody, Plan One, and Sletten for breach of contract and breach of the covenant of good faith and fair dealing.Sletten responded to Gunwerks’s lawsuit by filing a third-party complaint against its subcontractors, including BHG. Sletten claimed that, should it be found liable to Gunwerks, subcontractors responsible for any deficient work should indemnify it for those damages. Sletten did not specifically admit or allege deficiencies in BHG’s work but sought to preserve its right to recovery if any subcontractor was found at fault. Approximately ten months after Sletten’s third-party complaint, BHG moved for summary judgment in the District Court of Park County, arguing that Sletten had not presented evidence showing BHG caused any of the alleged damages. The district court granted summary judgment for BHG, finding that Sletten had not countered BHG’s prima facie showing with disputed facts, relying instead on speculation.On appeal, the Supreme Court of Wyoming reviewed the district court’s summary judgment ruling de novo, applying the same standard as the lower court and viewing the record most favorably to Sletten. The Supreme Court affirmed the district court’s decision, holding that Sletten failed to present admissible, competent evidence creating a genuine issue of material fact regarding BHG’s liability for any alleged defects. The court found Sletten’s evidence speculative and conclusory, insufficient to defeat summary judgment. The disposition was affirmed. View "Sletten Construction of Wyoming, Inc. v. Big Horn Glass, Inc." on Justia Law
Perkins v. RMR Building Group
A Nebraska limited liability company owned by Michael Perkins hired RMR Building Group, LLC, managed and solely owned by Robert M. Ryan II, as a general contractor to redevelop a shopping center. Their contract used a cost-plus billing arrangement, where Perkins paid RMR in advance for specific construction costs, including a substantial sum for HVAC equipment and RMR’s fee. RMR deposited the funds into its general operating account but did not pay for the HVAC equipment; instead, it used the money to cover other business obligations. Perkins terminated the contract after RMR failed to provide proof of payment for the equipment and then sued RMR and Ryan for breach of contract, unjust enrichment, conversion, and fraudulent misrepresentation, also seeking to pierce the corporate veil and hold Ryan personally liable.The District Court for Douglas County found that RMR breached the contract and was liable under theories of money had and received and unjust enrichment, but not for conversion or fraudulent misrepresentation. The court declined to disregard RMR’s corporate entity, finding no sufficient evidence that Ryan diverted funds for personal use or that RMR was a mere facade for Ryan’s dealings. Perkins appealed these findings.The Nebraska Court of Appeals reversed in part, concluding that the corporate veil should be pierced and Ryan held jointly and severally liable for the misappropriated funds, relying on factors from United States Nat. Bank of Omaha v. Rupe. On further review, the Nebraska Supreme Court reversed the Court of Appeals, holding that the evidence did not establish by a preponderance that RMR’s entity should be disregarded, nor did it support fraud or conversion claims against Ryan. The Supreme Court remanded with direction to affirm the district court’s judgment. View "Perkins v. RMR Building Group" on Justia Law
Ward v. Bishop Construction
Joel Ward performed construction work for Bishop Construction, LLC and its sole member, Ren Bishop, in Idaho, Montana, and Wyoming, with an agreed hourly wage and travel compensation. Despite keeping detailed records of his hours, Ward was not paid for work completed between 2017 and 2019, leading him to pursue payment through legal action. The dispute centered on whether Ward should be classified as an employee or an independent contractor and whether he was required to register as a contractor under Idaho law.The case was first heard in the District Court of the Seventh Judicial District of Idaho, Bonneville County. After a bench trial, and based on the parties’ stipulation that Ward was an independent contractor, the court dismissed his wage claims, leaving only breach of contract and unjust enrichment claims. The district court initially awarded Ward full damages for breach of contract. However, after Bishop raised the issue of contractor registration under the Idaho Contractor Registration Act (ICRA) in post-trial motions, the court amended its findings, limited contract damages to out-of-state work, awarded unjust enrichment damages for Idaho work, and granted costs and attorney fees.On appeal, the Supreme Court of the State of Idaho reviewed whether Ward was required to register as a contractor under ICRA and whether the contract was illegal. The Court held that Bishop failed to meet his burden to prove Ward was required to register under ICRA, as the record did not establish Ward’s status as a contractor for those purposes. The Supreme Court vacated the district court’s amended judgment and remanded with instructions to reinstate its original findings and amended judgment, including the previously awarded attorney fees and costs. The Court also awarded Ward attorney fees and costs on appeal as the prevailing party. View "Ward v. Bishop Construction" on Justia Law