Justia Contracts Opinion Summaries

Articles Posted in Civil Procedure
by
The U.S. District Court for the District of Colorado certified a question of Colorado law to the Colorado Supreme Court regarding the statute of limitations applicable to section 10-3-1116, C.R.S. (2017), which governed claims for unreasonable delay or denial of insurance benefits. Specifically, the question centered on whether a claim brought pursuant to Colorado Revised Statutes section 10-3-1116 was subject to the one-year statute of limitations found in Colorado Revised Statutes section 13-80-103(1)(d) and applicable to “[a]ll actions for any penalty or forfeiture of any penal statutes.” The Supreme Court held the one-year statute of limitations found in section 13-80-103(1)(d), C.R.S. (2017), did not apply to an action brought under section 10-3-1116(1) because section 10-3-1116(1) was not an “action[] for any penalty or forfeiture of any penal statute[]” within the meaning of section 13-80-103(1)(d). Therefore, the Court answered the certified question in the negative. View "Rooftop Restoration, Inc. v. Am. Family Mut. Ins. Co." on Justia Law

by
In 2009, a fire started in an apartment building owned by respondents Guillermo and Evelia Barriga and insured by petitioner American Family Mutual Insurance Company (“American Family”). American Family made various payments to the and on behalf of the Barrigas, totaling $209,816.43. However, after a substantial amount of repair work had been completed, the contractor revised its estimate for the cost of the repairs. The revised estimate was higher than American Family’s initial estimate, primarily because of the need for additional repairs and asbestos remediation. In response, American Family initiated a third-party appraisal process outlined in the insurance policy intended to provide an impartial assessment of the needed repair costs. The appraiser fixed the award at $322,141.79. American Family then paid that award, less the $209,816.43 that had been previously paid to the Barrigas, resulting in a payment of $122,325.36. American Family also made an additional payment of $5435.44 for emergency board-up services. The Barrigas sued American Family for breach of contract, common law bad-faith breach of insurance contract, and unreasonable delay and denial of insurance benefits under section 10-3-1116(1), C.R.S. (2017). The jury found for the Barrigas on all claims, awarding damages, as relevant here, of $9270 for breach of contract and $136,930.80 for benefits unreasonably delayed or denied. The issue raised on appeal for the Colorado Supreme Court's review centered on whether an award of damages under section 10-3-1116(1), C.R.S. (2017), had to be reduced by an insurance benefit unreasonably delayed but ultimately recovered by an insured outside of a lawsuit. The Court held that an award under section 10-3-1116(1) must not be reduced by an amount unreasonably delayed but eventually paid by an insurer because the plain text of the statute provided no basis for such a reduction. The Court also concluded that a general rule against double recovery for a single harm did not prohibit a litigant from recovering under claims for both a violation of section 10-3- 1116(1) and breach of contract. View "Am. Family Mut. Ins. Co. v. Barriga" on Justia Law

by
Prolite Building Supply bought Ply Gem windows, which it resold to Wisconsin builders. Some homeowners were not satisfied with the windows, which admitted air even when closed. Contractors stopped buying from Prolite, which stopped paying Ply Gem. Prolite and homeowners sued. Ply Gem removed the action to federal court and counter-claimed against Prolite for unpaid bills. Additional parties intervened. The Seventh Circuit affirmed summary judgment in favor of Prolite. The court vacated the judgment on the homeowners’ claims for remand to state court. The service agreement between Prolite and Ply Gem requires Prolite to repair the Ply Gem windows in exchange for a discount and needed parts. There was no breach of that agreement. The homeowners’ claims can be resolved under supplemental jurisdiction only if they “are so related to claims in the action within such original jurisdiction that they form part of the same case or controversy,” 28 U.S.C. 1367(a). The language of the window warranties received by the homeowners and the service agreement did not overlap. Prolite complained that Ply Gem did not do enough to ensure that its customers (the builders) remained willing to purchase Ply Gem windows. The homeowners just wanted to stop drafts and moisture. The nature of the work done differed. View "ProLite Building Supply, LLC v. Ply Gem Windows" on Justia Law

by
This case centered on a dispute between Green Meadow Realty Co. (Realtor) and Roger and Mary Gillock (Owners) over Realtor's right to a commission. Realtor sued to recover a commission on a sale to certain buyers that Owners believed were excluded from the listing agreement. Realtor relied on an addendum to the listing agreement that limited the period of time in which an excluded sale could occur as well as the fact that the sale closed outside the time period. Owners claimed they insisted on a complete exclusion and did not knowingly agree to a time limit for the excluded sale, despite having signed the addendum. Owners asserted that they signed the addendum without reading it based on Realtor's representation that it set forth "your exclusion." The trial court concluded Owners were bound by the addendum, having had the opportunity to read it and not doing so. The trial court granted summary judgment to Realtor. The Court of Civil Appeals affirmed the summary judgment awarding Realtor the commission, but reversed for further proceedings on a counter claim by Owners. Owners sought certiorari review. Realtor did not. The trial court and Court of Civil Appeals regarded Owners' failure to read the addendum when presented with it to be dispositive. The Oklahoma Supreme Court found while this was certainly important, ultimately, the communications and conduct of the parties with respect to the addendum "must be judged in the totality of the circumstances surrounding its creation. The conflicting positions and evidentiary materials of the parties in the case at hand pose a comparable controversy that would preclude summary judgment on Realtor's claim for a commission." View "Green Meadow Realty Co. v. Gillock" on Justia Law

by
The Supreme Court reversed the judgment of the Appellate Court affirming the judgment of the trial court in favor of Plaintiff against Defendants, Joan Frank and George Frank, holding that there was no final judgment as to George, and therefore, the Appellate Court lacked jurisdiction over Defendants’ joint appeal.Plaintiff filed this action alleging common-law enforcement of a foreign default judgment and seeking recovery under theories of breach of contract and quantum meruit. The trial court found in favor of Plaintiff on count one against George and on count two against Joan. The Appellate Court affirmed the trial court’s judgment, rejecting Defendants’ claims on appeal on the merits. The Supreme Court reversed, holding that the trial court’s failure to dispose of either the contract count or the quantum meruit count as to George resulted in the lack of a final judgment, and therefore, the Appellate Court should have dismissed Defendants’ joint appeal. View "Meribear Productions, Inc. v. Frank" on Justia Law

by
Yates Construction, LLC, and D.W. Caldwell, Inc., entered into a construction subcontract for the roof installation on a residential dormitory at Auburn University in Auburn, Alabama. When Caldwell completed both the repairs and the roof installation, it had yet to receive total payment for the structural repairs. The companies disputed the scope and expense of these repairs and quickly negotiated to an impasse. Thereafter, Caldwell filed a claim against Yates for causing delay and increased costs by failing to pay for work performed, which was in breach of the agreements between the parties. The parties proceeded to arbitration. Although the arbitration record was neither recorded nor transcribed, the parties conceded that the arbitrator considered arguments, reviewed evidence, and heard witness testimony over the course of three days. He then reopened the proceedings for additional documentation, before issuing his thirteen-page award. Within two weeks of the arbitrator’s decision to deny Yates’s motion for reconsideration, Caldwell requested that the circuit court confirm the award under Mississippi Code Section 11-15-125. Yates moved the trial court to alter, amend, or vacate the award under Mississippi Code Section 11-15-25. With the understanding that Yates would provide oral argument on its motion at the award confirmation hearing, Caldwell filed a request to limit the presentation of proof before the circuit court. Ultimately, the trial court reviewed fourteen exhibits and the testimony of one witness in making its decision. Based on this evidence, the court issued its order modifying the arbitrator’s award. Finding that the arbitrator had duplicated the labor costs for shingle installation in its award–once under the original subcontract and once under the oral agreement to repair the structural damage (referred to as the Repair Agreement)–it amended the award, reducing the total by $104,507. After its review, the Mississippi Supreme Court determined: (1) the miscalculations alleged in this matter were not evident from the award itself, nor were they apparent from the agreed-upon record; and (2) the judge erred when he allowed the parties to present witness testimony regarding the extent of any alleged miscalculations, rather than relying on the award and the arbitration record as the relevant law suggested. Finding error, the Court therefore reversed the circuit court’s decision and remanded this case to the circuit court with directions to confirm the arbitration award. Furthermore, because the subcontract between the parties provided that each contractor would be responsible for his own fees and costs, the Court declined to assess costs to one party over the other, and instead, enforced their bargained-for agreement. View "D. W. Caldwell, Inc. v. W.G. Yates & Sons Construction Company" on Justia Law

by
Ewing Construction Co., Inc., appeals from a judgment denying its N.D.R.Civ.P. 60(b) motion to vacate a $951,191.62 default judgment entered in favor of Key Energy Services, LLC. Ewing began serving as the designer of and general contractor for Key's construction of the P3 Service Center project in Williston. Ewing voluntarily canceled its North Dakota contractor license in October 2014. In January 2015, Key sued Ewing and 22 others to invalidate construction liens filed against its property and claiming Ewing failed to pay numerous subcontractors for their work on the project in violation of its contractual obligations. After Ewing failed to answer the complaint, Key moved in June 2016 for a default judgment against Ewing. The district court granted the motion and entered default judgment against Ewing, awarding Key $951,191.62. The default judgment was entered on June 24, 2016, and Key served notice of entry of judgment on June 27, 2016. On May 12, 2017, after attempts were made to enforce the default judgment in Texas, Ewing brought a N.D.R.Civ.P. 60(b) motion to vacate the default judgment "because of insufficient service of process, and excusable neglect." Key responded by filing a corrected return of service which the district court accepted and considered. The corrected return of service was notarized and identified the documents served. On July 28, 2017, the court denied the N.D.R.Civ.P. 60(b) motion, concluding service of process was sufficient, the motion was untimely, and Ewing failed to establish excusable neglect. Because the district court did not err in ruling service of process was proper and did not abuse its discretion in denying the motion to vacate, the North Dakota Supreme Court affirmed. View "Key Energy Services, LLC v. Ewing Construction Co., Inc., et. al." on Justia Law

by
Steven Kelly and Spirit Energy LLC (collectively "Spirit") appealed a district court order holding them in contempt for failing to return leased vehicles to Kettle Butte Trucking ("KBT"). KBT sued Spirit, alleging Spirit failed to pay numerous lease payments for trucks they leased from KBT. Spirit challenged the district court's underlying order that was alleged to have been violated. Spirit also argued the court did not have jurisdiction to hold it in contempt. When a contempt order is appealed, challenges to the underlying order will not be considered unless the underlying order is also appealed. When a court has issued an allegedly erroneous order, the party to whom the order was issued must obey it as long as it remains in force or until it is reversed on appeal, and the failure to obey the order is punishable as a contempt of court. Finding no reversible error, the North Dakota Supreme Court affirmed the district court's order holding Spirit in contempt. View "Kettle Butte Trucking, LLC v. Kelly" on Justia Law

by
Charles Erwin appeals from an amended judgment entered in favor of Alerus Financial, N.A., for $5,265,653.09. Starting in 2012 Alerus made a series of loans totaling more than $15 million to Diverse Energy Systems, LLC. The loan agreement specified "Events of Default," including the failure to pay the indebtedness, the insolvency of the borrower or guarantor or the commencement of bankruptcy proceedings. Erwin was Diverse's chief executive officer, and he signed multiple personal guaranties, promising to be personally responsible for payment of up to $4 million of Diverse's debt owed to Alerus. In September 2015 Diverse filed for bankruptcy. In May 2016 Alerus sued Erwin for breach of contract and unjust enrichment, alleging Diverse was in default under the loan agreement and Erwin failed to make payment on the amount due under the guaranties. Alerus alleged Diverse's indebtedness exceeded $12 million and under the guaranties Erwin was liable for at least $4 million in principal and interest. On September 6, 2016, Erwin filed an answer to Alerus' complaint. Alerus moved for summary judgment, arguing Diverse defaulted on its loan obligations and Erwin breached the guaranty contracts by failing to pay the amounts due under the guaranties. Alerus also filed an affidavit in support of its motion from an Alerus employee, which it claimed showed the total outstanding principal and interest on the loans to Diverse. Erwin argued on appeal to the North Dakota Supreme Court the district court abused its discretion by failing to rule on his motion to amend his answer and entering judgment without allowing him to conduct discovery on Alerus' damage claims. Finding no reversible error, the Supreme Court affirmed the amended judgment. View "Alerus Financial, N.A. v. Erwin" on Justia Law

by
The First Circuit vacated the judgment of the district court dismissing APB Realty, Inc.’s complaint against Georgia-Pacific alleging breach of contract stemming from the failure of a proposed deal concerning the purchase of rail freight cars. The district court dismssed the complaint for failure to state a claim upon which relief could be granted, finding that no contract had been formed between the parties. The First Circuit disagreed, holding that the complaint alleged facts from which the Court could plausibly infer the making and breaking of a contract. The Court remanded the cause for further proceedings. View "APB Realty, Inc. v. Georgia-Pacific LLC" on Justia Law