Justia Contracts Opinion Summaries

Articles Posted in Business Law
by
Plaintiffs, Lewis, Ross and Jennings, were limited guarantors of loans owed by River City, which filed for bankruptcy. Defendant acquired the original lender’s position and reported to credit reporting agencies that the plaintiffs were obligated in the full amount of the underlying loans rather than in limited amounts. In a suit under the Fair Credit Reporting Act 15 U.S.C.1681–1681x, defendant counterclaimed on the guaranty agreements. The district court found defendant liable to each plaintiff for FCRA violations and the plaintiffs in breach of their guaranty agreements. The court awarded Lewis $30,000 in actual damages and $120,000 in punitive damages and each remaining plaintiff $25,000 in actual damages and $100,000 in punitive damages. The court jointly awarded plaintiffs $20,024.55 in costs and $218,674.00 in attorney’s fees. On the breach of guaranty claims, the court found Lewises liable for $256,797.29, Jennings liable for $255,367.29, and Ross liable for $306,726.14. Defendant objected to Lewis’s garnishment, arguing that defendant was the net judgment creditor because the proper method of calculation required the court to: add the amounts defendant owed plaintiffs (including attorney’s fees and costs); add the amount paintiffs collectively owed defendant; then set off the former sum from the latter. The district court rejected the argument. The Sixth Circuit affirmed. View "Lewis v. United Joint Venture" on Justia Law

by
EAR, a seller of manufacturing equipment, defrauded creditors by financing non-existent or grossly overvalued equipment and pledging equipment multiple times to different creditors. After the fraud was discovered, EAR filed for bankruptcy. As Chief Restructuring Officer, Brandt abandoned and auctioned some assets. Five equipment leases granted a secured interest in EAR’s equipment; by amendment, EAR agreed to pay down the leases ($4.6 million) and give Republic a blanket security interest in all its assets. Republic would forebear on its claims against EAR. The amendment had a typographical error, giving Republic a security interest in Republic’s own assets. Republic filed UCC financing statements claiming a blanket lien on EAR’s assets. After the auction, Republic claimed the largest share of the proceeds. The matter is being separately litigated. First Premier, EAR’s largest creditor, is concerned that Republic, is working with Brandt to enlarge Republic’s secured interests. After the auction, EAR filed an action against its auditors for accounting malpractice, then sought to avoid the $4.6 million transfer to Republic. The bankruptcy court approved a settlement to end the EAR-Republic adversary action, continue the other suit, divvy proceeds from those suits, and retroactively modify the Republic lien to correct the typo. First Premier objected. The district court affirmed. The Seventh Circuit affirmed. First Premier was not prejudiced by the settlement. View "First Premier Capital, LLC v. Republic Bank of Chicago" on Justia Law

by
Plaintiff Gol TV produces soccer-related television programming, while Defendants EchoStar Satellite Corporation and EchoStar Satellite L.L.C. (known as DISH Network) distribute television programming to individual viewers via satellite. From 2003 until 2008, Gol TV’s programming was made available to subscribers of certain EchoStar service packages in exchange for EchoStar’s payment to Gol TV of contractually determined licensing fees. Gol TV brought a breach-of-contract suit against Echostar to recover monies due under the contract. The issue on appeal central to this dispute involved: (1) the calculation of licensing fees for the final ten days of the contract period; and (2) the accrual of interest for overdue payments. Upon review of the contract at issue, the Tenth Circuit agreed with the district court's interpretation and affirmed its disposition of the case. View "Gol TV v. Echostar" on Justia Law

by
For four years, subcontractor Precision Welding, Inc. provided construction services to Denbury Onshore, LLC, under an oral agreement. Denbury, claiming its contract with Precision was terminable at will, terminated the relationship in 2006. Precision filed suit, claiming Denbury had breached its obligation to keep Denbury on the job until the completion of the project. A jury found for Precision and awarded it $1,500,000 in damages. But because the oral contract between Denbury and Precision was for a particular hourly rate for work performed and not for any particular or definite time period, the Supreme Court held that the contract was terminable at will, and reversed the jury verdict. The Court remanded for a new trial on the issue of whether, under the circumstances, Denbury provided Precision reasonable notice of the termination and, if not, the damages it proximately caused. View "Denbury Onshore, LLC v. Precision Welding, Inc." on Justia Law

by
Eureka Water Company contended that a 1975 agreement granted it the exclusive license in 60 Oklahoma counties to sell spring water and other products using the "Ozarka" trademark. It sued Nestle Waters North America, Inc., the current owner of the Ozarka trademark, to obtain a declaratory judgment of that right and to obtain monetary relief under several theories, including breach of contract, tortious interference with business relations, unjust enrichment, and promissory estoppel. A jury found for Eureka on its contract and tortious interference claims, and the district court entered a judgment declaring that the 1975 agreement granted Eureka the exclusive right that it claimed in the Ozarka mark. In a post-verdict ruling, the district court denied as duplicative Eureka's equitable claims based on unjust enrichment and promissory estoppel. Nestle appealed. The Tenth Circuit agreed with most of Nestle's principal arguments. First, the Court reversed the district court's denial of Nestle's motion for JMOL on the contract claim because the 1975 agreement unambiguously did not cover spring water and under Oklahoma contract law. The Court reversed the denial of JMOL on the tortious-interference claim because Eureka failed to show that Nestle's decision to charge Eureka what it charged other vendors for bottled water was not privileged or justified. Third, the Court affirmed the denial of Eureka's unjust enrichment claim because the claim is based on the false premise that Eureka's license to use the Ozarka trademark covers spring water. The Court reversed, however, the denial of Eureka's promissory-estoppel claim, and remanded that claim for further consideration by the district court. View "Eureka Water Company v. Nestle Waters North America" on Justia Law

by
Milliken & Company sued Brian Morin after he resigned from the company and started a new venture using Milliken's proprietary information. The primary basis of the suit was that Morin breached the confidentiality and invention assignment agreements he signed when he started working for Milliken. A jury found for Milliken, and the court of appeals affirmed. The Supreme Court granted certiorari to review the narrow issue of whether these agreements are overbroad as a matter of law. Upon review, the Court held that they were not and affirmed as modified. View "Milliken & Company v. Morin" on Justia Law

by
Contractor contracted to build a restaurant in Minnesota, promising to pay each subcontractor, upon receipt of payment from the owner, the amount to which the subcontractor was entitled. Appellant became the subcontractor for carpentry and drywall work. Upon completing its work, Appellant was not paid the full amount owed. After Contractor settled a dispute with the restaurant, it offered Appellant a smaller sum, claiming it was Appellant's pro rata share of the settlement proceeds. Appellant rejected the offer and sued Contractor and its Owner in state court. Owner and his wife subsequently filed a petition for Chapter 7 bankruptcy relief, with the debt to Appellant unsatisfied. Appellant commenced this adversary proceeding to have the debt declared nondischargeable. The bankruptcy appellate panel (BAP) determined that neither 11 U.S.C. 523(a)(4) nor 11 U.S.C. 523(a)(6) barred discharge of the debt. The Eighth Circuit Court of Appeals affirmed, holding (1) Owner was not a section 523(a)(4) fiduciary by reason of a Minnesota statute or Owner's Minnesota common law duties, nor did Contractor's use of its own property amount to embezzlement; and (2) the BAP did not err in finding no malicious injury, which resolved the section 523(a)(6) issue. View "Reshetar Sys., Inc. v. Thompson" on Justia Law

by
Sea Hawk Seafoods, Inc. sued the City of Valdez for damages after Valdez applied for a grant from the State of Alaska for funding to convert Sea Hawk's seafood processing facility into a fish meal plant but then declined to accept the $600,000 grant that the State conditionally awarded to Valdez. On pre-trial motions, the superior court dismissed Sea Hawk's claims for breach of contract, breach of an agreement to negotiate, and breach of a duty to negotiate in good faith. Valdez and Sea Hawk filed cross-motions for summary judgment on Sea Hawk's remaining claim for promissory estoppel, which the court denied. Shortly before trial, the court dismissed Sea Hawk's promissory estoppel claim as a discovery sanction. Sea Hawk and Valdez both appealed. Upon review, the Supreme Court affirmed: Sea Hawk's claims were based on statements made and a letter sent by the Valdez City Manager to the owner of Sea Hawk. Because these communications, even when viewed in the light most favorable to Sea Hawk, were insufficient as a matter of law to support Sea Hawk's claims. The Court reversed the lower court's ruling denying Valdez summary judgment on Sea Hawk's promissory estoppel claim.

by
AECOM, Inc. hired Centennial Archaeology, Inc. to perform cultural resources survey work in connection with a wind-energy project. When AECOM refused to pay Centennial for some of its work, Centennial brought suit against AECOM in the United States District Court for the District of Wyoming. Centennial prevailed on several claims and the parties ultimately settled on appeal the issues raised with respect to the merits of the litigation. This appeal concerned the parties' dispute about the district court's postjudgment order requiring AECOM to pay Centennial $58,361.51 in attorney fees for misconduct in the course of discovery. Upon review, the Tenth Circuit affirmed: the magistrate judge and district court reasonably found that AECOM had frustrated the discovery process and stalled the resolution of this case. And the amount of the fee award was proper. In particular, Centennial was entitled to an award under Fed. R. Civ. P. 37 even though its attorneys were working for a fixed fee.

by
Joseph purchased the BP franchise in 2006 for $400,000. In 2009, Sasafrasnet purchased BP’s interests in the land and a Dealer Lease and Supply Agreement, becoming lessor and franchisor. The DLSA authorizes Sasafrasnet to terminate if Joseph fails to make payment according to EFT policy, causing a draft to be dishonored as NSF more than once in 12 months; Sasafrasnet is not obligated to extend credit, but did deliver fuel before collecting payment. There were several instances of NSF EFTs; Sasafrasnet began to require payment in advance. Later, Sasafrasnet allowed Joseph to resume paying by EFT within three days of delivery, but established a $2,500 penalty for any NSF and stated that pre-pay would resume if he incurred two more NSFs. There were additional NSFs, so that Joseph had incurred nine for amounts over $20,000 and three for amounts over $45,000. Sasafrasnet gave Joseph 90 days’ notice that it was terminating his franchise, listing the NSFs and failing scores on a mystery shopper inspection as bases for termination. Joseph sued under the Petroleum Marketing Practices Act, 15 U.S.C. 2801. The district court denied a preliminary injunction to prevent the termination. The Seventh Circuit reversed, holding that the statute requires additional findings.