Buyers purchased two condominium units pursuant to contracts entered into in 2006. Buyers later contended that the contracts were voidable because Seller failed to maintain Buyers’ deposits in escrow in the manner required by the Condominium Act (the Act). The trial court dismissed the claims against Seller. The Third District Court of Appeal reversed, concluding (1) the contracts were voidable under the escrow provisions of the Act that were in force in 2006; and (2) the application of a 2010 amendment to the Act that was intended to have retroactive effect and that removed a statutory ground for determining that the contracts were voidable violated the constitutional prohibition on the impairment of vested contractual rights. The Supreme Court reversed, holding (1) the 2010 amendment did not make a substantive change in the law; and (2) the contracts were not voidable under the statutory provisions in force in 2006. View "N. Carillon, LLC v. CRC 603, LLC" on Justia Law

by
Arloe Designs, LLC proposed to build a building at an airport. Arkansas Capital Corporation (ACC) and National Bank of Arkansas (NBA) allegedly worked together to procure a loan for the building’s construction. After the NBA approved financing for the project, Arloe entered into a thirty-year lease for the new hangar. Later that month, Arloe learned that NBA would not close the loan without a bond as collateral, which Arloe did not give, and therefore, the loan was not closed. Arloe sued ACC and NBA, alleging breach of contract, violations of the Arkansas Deceptive Trades Practices Act, negligence, and promissory estoppel. The circuit court granted summary judgment to Defendants as to all but Arloe’s promissory estoppel claim, and limited damages for that claim to the money Arloe had spent in reliance on the claimed promise. At trial, a jury found Arloe had not proved that either defendant had made a promise to loan Arloe money. The Supreme Court affirmed, holding (1) Arloe’s claims that the circuit court erred in denying it recovery for lost profit damages and limiting its damages on its promissory-estoppel claim were moot; and (2) summary judgment was proper in regard to the remainder of Arloe’s claims. View "Arloe Designs LLC v. Ark. Capital Corp." on Justia Law

by
Nationwide Mutual Fire Insurance Company issued a policy to Danny Ludwick insuring his home and its contents. The policy named Citizens Bank & Trust Company as the first mortgagee. The dwelling was subsequently destroyed by fire. However, based on material misrepresentations in Ludwick's application, Nationwide voided the policy back to its inception. Citizens submitted a claim to Nationwide. Nationwide denied the claim on the basis that the policy was void ab initio, allegedly extinguishing not only Ludwick’s interest but also Citizen’s interest as mortgagee. Citizens filed a complaint for wrongful denial of its claim. The circuit court granted summary judgment to Citizens. The Supreme Court affirmed, holding (1) an insurance company is entitled to rescission of its insured’s policy based on the insured’s fraud or misrepresentation, but the rescission of the policy has no effect on an independent contract with the mortgagee; and (2) because the policy at issue contained a standard mortgage cause, which operated as an independent contract between the insurance company and the named mortgagee, the rescission of Nationwide’s policy had no effect on the independent contract with Citizens. View "Nationwide Mut. Ins. Co. v. Citizensbank & Trust Co." on Justia Law

by
The issue before the Supreme Court in this case centered on whether a minority stockholder in a closely held corporation had a right to a non-conflicted board decision on whether to repurchase her shares. That stockholder argued that such a right exists, under common law fiduciary duty principles and under the implied covenant of good faith and fair dealing. The Court of Chancery found that the common law did not impose any duties on directors to consider buying out minority stockholders. The trial court also found that, given the language in the repurchase provision of the stockholders agreement, the implied covenant of good faith and fair dealing did not create any duty to negotiate a reasonable repurchase price. The Supreme Court agreed and affirmed the trial court. View "Blaustein v. Lord Baltimore Capital Corp." on Justia Law

by
In 2003, multiple residents of Greenwood Health Center, a nursing home, died or were injured when another resident set fire to the facility. Thirteen negligence actions seeking damages for wrongful death or serious bodily injury were filed against Greenwood, the lessee of the property housing Greenwood, the owner and lessor of the property, and the operator of Greenwood. Lexington Insurance Company (Plaintiff) brought this declaratory judgment action against the lessor of the Greenwood property, which was the insured party under a policy issued by Plaintiff, the other Greenwood entities, and the victims’ personal representatives. Following the filing of cross motions for summary judgment, the trial court determined the amount of coverage available under the policy and rendered judgment accordingly. Plaintiff appealed the judgment of the trial court determining available coverage, and four of the individual defendants cross appealed. The Supreme Court reversed in part, holding (1) the trial court improperly interpreted the endorsement relating to the aggregate policy limit, thereby providing more coverage for the individual defendants’ claims than that to which they were entitled; and (2) the trial court improperly applied the self-insured retention endorsement to reduce the available coverage. Remanded. View "Lexington Ins. Co. v. Lexington Healthcare Group, Inc." on Justia Law

by
Then-owners of real property entered into a “Waiver of Right to Protest” the creation of special improvement districts (SIDs) for the purpose of making road and intersection improvements to Cottonwood Road between Huffine Lane and West Babcock Street. The waiver stated that the parties to the waiver would participate in alternate financing methods for completion of the road improvements if the SIDs were not utilized. No SIDs were implemented, and Covenant Investments, Inc. (Covenant) undertook and paid for all improvements to the intersection of Huffine and Cottonwood. First Security Bank (FSB), a successor to the original covenantor, subsequently constructed a building at the intersection. After FSB refused to reimburse Covenant for the costs of the street improvements, Covenant sued FSB seeking enforcement of the waiver agreement. The district court dismissed Covenant’s complaint, concluding that the waiver did not contain the essential elements of a contract and therefore did not bind FSB. The Supreme Court affirmed the dismissal of the complaint, holding (1) the waiver’s alternative financing provision was void for lack of certainty, (2) by acting unilaterally Covenant waived its right to belatedly demand enforcement of the waiver provision, and (3) Covenant’s complaint was barred by the statute of limitations. View "Covenant Invs., Inc. v. First Sec. Bank" on Justia Law

by
In the 1990s, Defendants (Employers) created a sick-leave policy allowing employees to bank their sick leave in a continued illness bank (CIB). In 2002, Employers modified the terms of the CIB to create the CIB pay-out benefit, which allowed a capped amount of unused CIB hours to be paid to departing employees who completed twenty-five years or more of service. In 2008, Employers terminated the CIB pay-out benefit, and only employees who had reached twenty-five years of employment with Employers were entitled to their earned but unused CIB hours upon termination. Plaintiffs in this case represented employees who had not reached twenty-five years of service before the benefit ended. Plaintiffs brought a class action complaint against Employers. The district court granted summary judgment for Employers. The Supreme Court affirmed, holding that the district court did not err in determining that (1) Employers’ policies did not constitute a standardized group employment contract; (2) the CIB pay-out benefit was not deferred compensation or wages under the Montana Wage and Wage Protection Act; and (3) the covenant of good faith and fair dealing did not apply to Plaintiffs’ claims. View "Chipman v. Northwest Healthcare Corp." on Justia Law

by
In November 2004, Dr. Ashard Yousuf sued Dr. George Cohlmia and Cardiovascular Surgical Specialists Corporation (CVSS) in Oklahoma state court for defamation, tortious interference with business relations/contract, intentional infliction of emotional distress/outrage, negligence, and breach of contract. Dr. Yousuf alleged that Dr. Cohlmia made a series of false statements to local media disparaging Dr. Yousuf's professional reputation. Dr. Cohlmia denied that the statements he made were false. CVSS held a professional liability policy with Physicians Liability Insurance Company (PLICO) and two identical general commercial liability policies with American National Property and Casualty Company (ANPAC, one for each business location), each of which covered Dr. Cohlmia as an additional insured. Dr. Cohlmia demanded that both insurers provide for his defense, pursuant to their respective policies. PLICO agreed to defend the lawsuit under a reservation of rights and requested ANPAC to share in the defense. ANPAC refused, contending its policy did not cover the alleged wrongdoing and that it owed no duty to defend. ANPAC further claimed that even if it erred in refusing to defend Dr. Cohlmia, PLICO had no right to indemnification or contribution for the defense costs it incurred. ANPAC appealed the district court's grant of summary judgment in favor of PLICO in a dispute regarding ANPAC's breach of its duty to defend a co-insured. PLICO cross-appealed the district court's denial of its motion for prejudgment interest. Finding no reversible error, the Tenth Circuit affirmed the district court's decision. View "Yousuf v. Cohlmia" on Justia Law

by
Plaintiffs, a class of cardholders who paid credit card penalty fees, challenged those fees on constitutional grounds. Plaintiffs argued that the fees are analogous to punitive damages imposed in the tort context and are subject to substantive due process limits described in BMW of North America, Inc. v. Gore. The court concluded that the due process analysis developed in the context of jury-awarded punitive damages was not applicable to contractual penalty clauses. Further, there was no derivative liability under the Unfair Competition Law. Accordingly, the district court did not err in dismissing the complaint where constitutional due process jurisprudence did not prevent enforcement of excessive penalty clauses in private contracts and the fees were permissible under the National Bank Act, 12 U.S.C. 85-86, and the Depository Institutions Deregulation and Monetary Control Act (DIDMCA), 12 U.S.C. 1831d(a). View "In re: Late Fee & Over-Limit Fee Litigation" on Justia Law

by
Ewing Construction Company entered into a contract with a school district to serve as general contractor on a project. The school district later filed suit against Ewing for faulty construction. Ewing tendered defense of the underlying suit to Amerisure Insurance Company, Ewing's insurer under a commercial package policy that included commercial general liability coverage. Amerisure denied coverage, and Ewing filed suit in federal district court seeking a declaration that Amerisure breached its duty to defend and indemnify Ewing for damages awarded in the underlying suit. The district court granted summary judgment for Amerisure, concluding that the policy’s contractual liability exclusion applied to exclude coverage because Ewing assumed liability for its own construction work pursuant to the contract such that it would be liable for damages arising out of its defective work. On appeal, the court of appeals certified questions to the Texas Supreme Court, which answered that “a general contractor that enters into a contract in which it agrees to perform its construction work in a good and workmanlike manner, without more specific provisions enlarging this obligation, does not ‘assume liability’ for damages arising out of the contractor’s defective work so as to trigger the contractual liability exclusion.” View "Ewing Constr. Co., Inc. v. Amerisure Ins. Co." on Justia Law