Storms, Inc. v. Mathy Constr. Co.

by
The Minnesota Department of Transportation (MnDOT) contracted with Mathy Construction Company for a public highway project. Mathy subcontracted with Storms, Inc. for excavation and fill work. After Storms completed its work, MnDOT issued a deductive change order reducing Mathy’s contract amount by $327,064 because of errors in the estimated quantities of excavation and fill required for Storms’ work. Mathy reduced Storms’ subcontract by the same amount. Storms subsequently sued Mathy for the reduction in the subcontract price. The district court granted summary judgment in favor of Storms, concluding that Mathy had breached the subcontract. The court of appeals affirmed. The Supreme Court reversed, holding that Mathy did not breach its subcontract with Storms by issuing a corresponding deductive change order to Storms. View "Storms, Inc. v. Mathy Constr. Co." on Justia Law