Stockton E. Water Dist. v. United States

by
In 1983, Central entered into a contract with the U.S. Bureau of Reclamation for an appropriation of water from the New Melones Reservoir in California’s San Joaquin Valley. Upon enactment of the Central Valley Project Improvement Act (CVPIA) in 1992, Reclamation made statements indicating that it would not be able to meet the quantity commitments in its contracts because of other demands for the water. In 1993, Central sued for breach of contract. After holding that breaches had occurred in certain years, the Federal Circuit reversed and remanded for determination of damages. The district court, on remand, awarded Central $149,950.00 in cost of cover damages, but denied any expectancy damages. The Federal Circuit reversed and remanded. The trial court erred by not properly considering the effect of Reclamation’s announced breaches on the amount of water that Central may have expected to need to meet demand. This caused the trial court to discount Central’s arguments regarding what would have happened in the non-breach world. View "Stockton E. Water Dist. v. United States" on Justia Law